Facts
Jaiprakash Associates Limited imported Digital and Network Video Recorders on 15 September 2023 under Bill of Entry No. 7856824 and availed concessional Basic Customs Duty under Serial No. 499A of CBIC Notification No. 50/2017-Customs.
Source reference: p.3, para. 5CIRP commenced against the Petitioner on 3 June 2024, following which a public announcement invited claims, with 17 June 2024 prescribed as the last date for submission.
Source reference: p.3–4, para. 6The Customs Department did not submit any claim before the Resolution Professional.
Source reference: p.4, para. 7During the CIRP, Customs issued a pre-notice consultation letter and subsequently a show-cause notice proposing recovery of differential customs duty of ₹5,89,366, interest and penalty on the ground that the concessional exemption was unavailable.
Source reference: p.4–5, paras. 7–8The Committee of Creditors approved a Resolution Plan on 31 October 2025, and the NCLT approved it under Section 31(1) of the Insolvency and Bankruptcy Code, 2016 on 17 March 2026.
Source reference: p.4, para. 9The Petitioner informed Customs of the NCLT approval and relied on Clause 4.12.1 of the Resolution Plan, which extinguished pre-CIRP claims not submitted to, or not verified by, the Resolution Professional.
Source reference: p.5, paras. 10–11Nevertheless, on 2 June 2026, the Additional Commissioner confirmed the differential duty and interest and imposed a penalty of ₹4,00,000 under Section 117 of the Customs Act.
Source reference: p.5–6, para. 12Issues
Whether a customs liability arising from a transaction predating the Insolvency Commencement Date constitutes a “claim” under Section 3(6) of the IBC, notwithstanding that the liability had not been adjudicated or quantified before commencement of CIRP?
Source reference: p.12–15, paras. 22–29Whether, after approval of the Resolution Plan under Section 31(1) of the IBC, the Customs Department could continue adjudication and enforcement proceedings in respect of an unfiled pre-CIRP claim?
Source reference: p.11–12, para. 20; p.28–30, paras. 52–60Whether the availability of an appellate remedy under the Customs Act barred exercise of writ jurisdiction where the challenge concerned the binding effect of the IBC and the alleged extinguishment of the claim?
Source reference: p.27–28, paras. 52–53Law Applied
The Court applied Section 3(6) of the IBC, which defines “claim” broadly to include a right to payment whether adjudicated or not, and whether fixed, disputed, unmatured or unsecured.
Source reference: p.12–13, paras. 22–25Sections 31(1) and 238 of the IBC were held to mean that an approved Resolution Plan binds the Corporate Debtor, creditors and governmental authorities to whom statutory dues are owed, and that claims not forming part of the plan stand extinguished and cannot thereafter be pursued; Section 238 gives the IBC overriding effect over inconsistent laws.
Source reference: p.15–17, paras. 30–32; p.20–21, paras. 35–38Relying principally on Ghanashyam Mishra & Sons (P) Ltd. v. Edelweiss Asset Reconstruction Co. Ltd., (2021) 9 SCC 657, and the principles reiterated in Essar Steel India Ltd. v. Committee of Creditors, (2020) 8 SCC 531, Ireo Fiveriver Pvt. Ltd. v. Income Tax Department, and Vaibhav Goel v. Deputy Commissioner of Income Tax, the Court held that the successful resolution applicant must receive the Corporate Debtor on a “fresh slate” and cannot be confronted with undisclosed or undecided pre-CIRP claims.
Source reference: p.16–20, paras. 32–36ABG Shipyard Liquidator v. Central Board of Indirect Taxes & Customs, (2023) 1 SCC 472, was distinguished as permitting determination of customs dues during CIRP subject to the IBC, but not enforcement of an unfiled pre-CIRP claim after approval of the Resolution Plan.
Source reference: p.21–22, paras. 40–42Reasoning
The Court held that the relevant customs liability arose from the import transaction of 15 September 2023, substantially before the CIRP commencement date of 3 June 2024.
Source reference: p.12–15, paras. 23–29Under Section 3(6) of the IBC, the underlying right to payment constituted a “claim” even though Customs issued the show-cause notice and quantified the duty only during the CIRP.
Source reference: p.12–15, paras. 23–29; p.25–26, paras. 47–49The statutory public-announcement mechanism placed the responsibility on Customs, as a creditor, to submit its claim; the absence of individual notice did not excuse its failure to participate.
Source reference: p.13–15, paras. 26–28Once the NCLT approved the Resolution Plan, Section 31(1), reinforced by Section 238 and Clause 4.12.1 of the Plan, extinguished pre-CIRP claims that had not been submitted or verified.
Source reference: p.24–29, paras. 45–59The Adjudicating Authority therefore erred in requiring the Petitioner to prove that the customs liability had been placed before the RP or considered by the NCLT; the material question was whether Customs had a pre-CIRP claim and failed to file it.
Source reference: p.24–29, paras. 45–59The Court further held that the Customs appeal remedy was not an adequate bar because the challenge concerned the legal authority to continue proceedings after extinguishment under the IBC, rather than the merits of classification or computation.
Source reference: p.27–28, paras. 52–53Holding
The Court answered the issues in favour of the Petitioner.
It held that the differential customs duty arose from a pre-CIRP claim, that the Customs Department’s failure to submit the claim during CIRP could not preserve an independent right of recovery, and that the claim stood extinguished upon approval of the Resolution Plan under Section 31(1) of the IBC.
Source reference: p.28–30, paras. 56–60The Order-in-Original dated 2 June 2026 confirming ₹5,89,366 as differential customs duty, directing recovery of interest and imposing the penalty was quashed and set aside.
Source reference: p.30–31, paras. 60–65The Court clarified that it expressed no opinion on the merits of classification or exemption eligibility under the Customs Act.
Source reference: p.31, para. 64The writ petition was allowed, the pending application was disposed of, and there was no order as to costs.
Source reference: p.31, para. 65Acts & Sections Cited
12 provisions across 4 statutes referred to in this judgment. Each provision opens on LawLens.
Customs Act,19623
Insolvency and Bankruptcy Code, 2016.7
Indian Contract Act, 18721
Gujarat Value Added Tax Act, 2003.1
Original Court PDF
Jaiprakash Associates LimitedvsThe Office Of The Commissioner Of Customs Air Cargo Complex Import & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
