Delhi High Court
Arbitration and MediationCivil Procedure and Evidence

Unilateral arbitrator appointment void without express waiver; even appointing party can challenge award, Delhi HC rules

Public Works Department vs B.L. Infra Projects Pvt Ltd

Delhi High CourtJUDGMENT: August 07, 20263 MIN READSOURCE JUDGMENT
Unilateral arbitrator appointment void without express waiver; even appointing party can challenge award, Delhi HC rules. Public Works Department vs B.L. Infra Projects Pvt Ltd. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Public Works Department awarded B.L. Infra Projects Pvt. Ltd. a contract for constructing additional SPS classrooms at schools in Delhi.

Source reference: p.1–2

The stipulated completion period was 135 days, from 16 March 2016 to 28 July 2016, but the work was completed approximately 437 days late.

Source reference: p.1–2

Disputes arose concerning the completion of the work, payments, escalation, prolongation costs, interest and other contractual claims.

Source reference: p.1–2

Pursuant to Clause 25 of the contract, the Chief Engineer, CPWD—an official of the Petitioner—unilaterally appointed the sole arbitrator.

Source reference: p.2, p.8–12

The arbitrator awarded the Respondent a total of ₹2,39,85,987, apart from granting declaratory relief regarding GST, and rejected or partly allowed various claims.

Source reference: p.5–7

The award dated 14 January 2022 was corrected on 9 February 2022 under Section 33 of the Arbitration and Conciliation Act, 1996 (“A&C Act”).

Source reference: p.7

In the Section 34 petition, the Petitioner principally challenged the award on the ground that the arbitrator had been unilaterally appointed by the Petitioner and was consequently ineligible under Section 12(5) read with the Seventh Schedule of the A&C Act.

Source reference: p.7–8
02

Issues

Whether an arbitrator unilaterally appointed by an interested party under the contractual arbitration clause is ineligible under Section 12(5) read with the Seventh Schedule of the A&C Act, rendering the appointment and award void ab initio?

Source reference: p.8–12, p.18–24

Whether participation in the arbitral proceedings, or the fact that the Petitioner itself made the appointment, constitutes an express written waiver under the proviso to Section 12(5) of the A&C Act?

Source reference: p.12–18, p.19–23

Whether the Petitioner could challenge the unilateral appointment for the first time in proceedings under Section 34 of the A&C Act despite having appointed the arbitrator?

Source reference: p.19–23
03

Law Applied

The Court applied Section 12(5) of the A&C Act, read with the Seventh Schedule, which renders a person having the specified relationships or interests with a party or the dispute ineligible to be appointed as an arbitrator.

Source reference: p.12–18

The proviso to Section 12(5) permits waiver only through an express agreement in writing made after the disputes have arisen.

Source reference: p.12–18

Relying on Bhadra International (India) (P) Ltd. v. Airports Authority of India, 2026 SCC OnLine SC 7, and Bharat Broadband Network Ltd. v. United Telecoms Ltd., the Court held that waiver cannot be inferred from conduct, participation or procedural acquiescence.

Source reference: p.12–18

It also relied on TRF Ltd. v. Energo Engineering Projects Ltd., (2017) 8 SCC 377, and the Division Bench decision in Mahavir Prasad Gupta & Sons v. State (NCT of Delhi), 2025 SCC OnLine Del 4241, for the principles that unilateral appointment is invalid, the appointing party is not deemed to have waived its objection merely by making the appointment, and an objection to inherent jurisdiction may be raised even at the Section 34 stage.

Source reference: p.14, p.19–23

An award rendered by an ineligible arbitrator is a nullity and may be set aside under Section 34(2)(b)(ii) of the A&C Act.

Source reference: p.18–23
04

Reasoning

Clause 25 vested the exclusive power to appoint the sole arbitrator in the Chief Engineer, CPWD, who was an official of the Petitioner and therefore lacked the requisite neutrality under Section 12(5) read with the Seventh Schedule.

Source reference: p.8–12, p.16

The Respondent’s reliance on paragraph 2 of the award and its participation in the arbitration could not establish a valid waiver because there was no clear, unequivocal and written agreement, executed after the disputes arose, waiving the arbitrator’s statutory ineligibility.

Source reference: p.12–18

The Court further held that the Petitioner’s own act of appointing the arbitrator did not amount to an express waiver.

Source reference: p.19–24

Since the appointment was void ab initio, the tribunal lacked inherent jurisdiction, and the resulting award was rendered a nullity.

Source reference: p.19–24

The Petitioner was therefore entitled to raise the objection for the first time in the Section 34 proceedings.

Source reference: p.19–24
05

Holding

The Court held that the unilateral appointment of the sole arbitrator by the Chief Engineer, CPWD, violated Section 12(5) read with the Seventh Schedule of the A&C Act.

No valid express written waiver had been executed by the parties after the disputes arose, and neither participation in the arbitration nor the Petitioner’s own appointment of the arbitrator cured the statutory ineligibility.

Source reference: p.16–18, p.23–24

Consequently, the arbitral appointment and proceedings were void ab initio, the award dated 14 January 2022, as corrected on 9 February 2022, was set aside, and the Section 34 petition was disposed of.

Source reference: p.24

Pending applications were also disposed of.

Source reference: p.24
Delhi High Court

Original Court PDF

Public Works DepartmentvsB.L. Infra Projects Pvt Ltd

Delhi High Court · August 07, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment