Facts
The Petitioner No. 1, a registered medical education trust, was allotted 64,890 sq. meters of land in Jaipur at a concessional rate by the Jaipur Development Authority (JDA) for a hospital project vide letter dated 22.03.2023
Source reference: para 2-4The premium was payable in four installments; the first was paid timely, and possession was handed over on 27.04.2023
Source reference: para 6-7The petitioner defaulted on the timelines for the second, third, and fourth installments, but eventually deposited the entire balance by 13.02.2025 following a JDA notice dated 21.01.2025
Source reference: para 10Despite accepting these payments and engaging with the petitioner on building plan revisions until April 2025, the JDA unilaterally refunded the installments on 11.03.2025 and cancelled the allotment on 08.04.2025, citing "automatic cancellation" under Condition No. 17 due to payment delays
Source reference: para 13-14, 20Issues
1. Whether the allotment stood automatically cancelled under Condition No. 17 despite JDA's subsequent acceptance of delayed payments and continued administrative engagement?
Source reference: para 272. Whether the cancellation of allotment and refund of deposits without prior notice or opportunity of hearing violated principles of natural justice?
Source reference: para 303. Whether the doctrines of legitimate expectation and promissory estoppel apply to preclude JDA from rescinding the allotment?
Source reference: para 324. Whether time was the essence of the allotment contract?
Source reference: para 35Law Applied
Principles of Natural Justice, specifically audi alteram partem, requiring a fair hearing before State action with civil consequences
Source reference: para 30Rule 15 and 17 of the Rajasthan Improvement (Disposal of Urban Land) Rules, 1974, governing institutional allotments
Source reference: para 17Doctrine of Promissory Estoppel from Motilal Padampat Sugar Mills v. State of UP
Source reference: para 32Doctrine of Legitimate Expectation from Union of India v. Hindustan Development Corporation
Source reference: para 32Principle from Chand Rani v. Kamal Rani and Hind Construction Contractors v. State of Maharashtra, holding that in immovable property transactions, time is ordinarily not of the essence unless explicitly intended and strictly pursued
Source reference: para 35-35.3.1Nemo potest mutare consilium suum in alterius injuriam (no one can change their position to the detriment of another)
Source reference: para 34.3Doctrine of Waiver by conduct
Source reference: para 29Reasoning
The Court reasoned that JDA’s invocation of "automatic cancellation" under Condition No. 17 was legally tenable only if the authority had not waived that condition through its conduct
Source reference: para 28-29By accepting the second installment in July 2024 and issuing a fresh demand notice in January 2025, JDA treated the allotment as subsisting, thereby waiving the rigors of the "automatic" clause
Source reference: para 28, 35.2The Court found that the petitioner had a "legitimate expectation" that the allotment was valid as they had altered their position by securing various NOCs (Medical, AYUSH, Airports Authority) and depositing nearly Rs. 27 Crores
Source reference: para 32-33JDA's action of seeking revised building plans even after the refund was initiated demonstrated a lack of internal consistency and arbitrariness
Source reference: para 38The Court held that since the land was for an institutional/philanthropic project and the JDA accepted delayed performance, time was not the essence of the contract
Source reference: para 35.1, 36The mid-stream cancellation without a show-cause notice was declared a "gross violation" of natural justice
Source reference: para 30-31Holding
The Court allowed the writ petition, quashing the cancellation orders dated 07.03.2025 and 08.04.2025
It held that the allotment is restored in favor of the Trust
Source reference: para 41.2The JDA was directed to: (i) accept the refunded balance of Rs. 20.98 Crores along with 6% annual interest for the delay periods; (ii) execute the lease deed within six weeks; and (iii) process building plans strictly in accordance with law
Source reference: para 41.3.1, 41.4The Petitioner was directed to complete construction within two years as per their undertaking
Source reference: para 42Original Court PDF
POORANMAL PHOOLA DEVI MEMORIAL TRUSTvsSTATE OF RAJASTHAN
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in