01Facts
The appellant filed a Miscellaneous Appeal under Section 173(1) of the Motor Vehicles Act, 1988, challenging the award dated 09.11.2024 passed by the Motor Accident Claims Tribunal (MACT), Guna
¶ 1Accompanying the appeal was an application (I.A. No. 8259 of 2025) under Section 5 of the Limitation Act seeking to condone a delay of 240 days
¶ 2The appellant, an illiterate villager, contended that his trial counsel failed to inform him of the award and he only discovered the proceedings upon receiving execution notices on 25.07.2025
¶ 3The appellant obtained a certified copy on 10.09.2025 and subsequently filed the appeal, arguing the delay was bona fide and caused by the "pay and recover" recovery proceedings initiated by the Insurance Company
¶ 302Issues
i.Whether the appellant established "sufficient cause" under Section 5 of the Limitation Act to warrant the condonation of a 240-day delay in filing the appeal
¶ 5, 703Law Applied
The court primarily applied Section 5 of the Limitation Act, 1963, which requires the showing of "sufficient cause" for condoning delays
¶ 5It relied on the precedent in Esha Bhattacharjee v. Managing Committee of Raghunathpur Nafar Academy (2013) 12 SCC 649, which established that a liberal approach should not enable a party to take the law for granted or mask a lack of bona fides
¶ 6It applied the principle from Postmaster General v. Living Media India Ltd. (2012) 3 SCC 563, holding that in the absence of a plausible and acceptable explanation, delay cannot be condoned mechanically
¶ 6Provisions in the judgment · 2 · Linked ones open on LawLens
Motor Vehicles Act, 1988 Section 173
Limitation Act, 1963 Section 5
04Reasoning
The court reasoned that while the Motor Vehicles Act is beneficial legislation requiring a liberal approach, the law of limitation cannot be rendered otiose
¶ 5, 7The court found the appellant’s plea—shifting blame to the trial counsel for non-communication—to be a general statement unsupported by material evidence or proof of due diligence
¶ 7The court noted that the appellant, being a party to the original proceedings, had a duty to remain diligent and could not shift the entire burden onto his counsel
¶ 7The court further determined that the timeline provided regarding knowledge gained through execution proceedings did not satisfactorily explain the entire duration of the 240-day delay, concluding that the explanation lacked the necessary plausibility and bona fides
¶ 7, 805Holding
The court held that the appellant failed to establish sufficient cause for the delay of 240 days
¶ 8Consequently, the court dismissed I.A. No. 8259 of 2025 for condonation of delay and subsequently dismissed the Miscellaneous Appeal as barred by limitation
¶ 9Original Court PDF
Vijay SinghvsIffco Tokyo General Insurance Co. Ltd.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
