Delhi High Court

Use of Permissive Language "May" in Pre-Arbitral Tiers Renders Recourse to Dispute Redressal Committee Optional.

M/S Rudra Interiors Pvt.Ltd. vs Hindustan Prefab Limited & Anr.

Delhi High CourtJUDGMENT: April 22, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, M/S Rudra Interiors Pvt. Ltd., entered into an agreement dated 19.08.2020 with Respondent No. 1 (HPL)

Source reference: para. 4

Following disputes, the Petitioner initiated the multi-tier dispute resolution process under Clause 26 of the Special Conditions of Contract (SCC). The Petitioner’s grievances were rejected by the Project-In-Charge on 19.12.2024

Source reference: para. 5

Subsequently, the Petitioner appealed to the CMD of HPL, who refused to treat the communication as an appeal, citing a lack of "cogent reasons" and "justification," and directed the filing of a fresh appeal

Source reference: paras. 6-7

After further correspondence and a demand for the constitution of a Dispute Redressal Committee (DRC), which Respondent No. 1 resisted by claiming the Petitioner had skipped mandatory procedural steps, the Petitioner invoked arbitration under Section 21 of the A&C Act and filed the present petition under Section 11

Source reference: paras. 11-15
02

Issues

1. Whether the pre-arbitral deposit/appeal to the Dispute Redressal Committee (DRC) was a mandatory prerequisite for invoking arbitration under Clause 26 of the SCC

Source reference: paras. 14, 20

2. Whether the Court, under Section 11 of the A&C Act, is required to conduct a detailed inquiry into the compliance of pre-arbitral procedures formulated by the parties

Source reference: paras. 18, 24
03

Law Applied

The Court primarily applied Section 11(6) of the Arbitration and Conciliation Act, 1996 regarding the appointment of arbitrators

Source reference: para. 1

It relied on the seven-judge bench decision in Interplay Between Arbitration Agreements under Arbitration Act, 1996 & Stamp Act, 1899, In re, which established that judicial intervention at the Section 11 stage is confined to a prima facie examination of the existence of an arbitration agreement

Source reference: para. 24

Furthermore, it applied the principles from SBI General Insurance Co. Ltd. v. Krish Spinning, which clarified that the Referral Court should not delve into contested factual or legal issues like "accord and satisfaction" or procedural technicalities, as these fall within the exclusive jurisdiction of the Arbitral Tribunal under the principle of competence-competence

Source reference: para. 24

The court also applied Perkins Eastman Architects DPC v. HSCC (India) Ltd. regarding the impermissibility of unilateral arbitrator appointments

Source reference: para. 26
04

Reasoning

The Court reviewed Clause 26 of the SCC and found that the language used regarding appeals was "may," indicating that recourse to the DRC was directory rather than a mandatory bar to arbitration

Source reference: para. 20

The Court criticized Respondent No. 1 for reading extra-contractual requirements (such as "detailed reasons") into the appeal process, characterizing its conduct as an attempt to impose "manifestly onerous" interpretations on the Petitioner

Source reference: paras. 18-22

Based on Krish Spinning, the Court held that since a valid arbitration agreement exists, any dispute regarding whether the Petitioner sufficiently complied with pre-arbitral procedural steps is a "mixed question of law and fact" that must be decided by the Arbitral Tribunal, not the Referral Court

Source reference: para. 24

The Court noted that the unilateral appointment power reserved for the CMD in the contract was legally invalid under the Perkins Eastman doctrine

Source reference: para. 26
05

Holding

The Court allowed the petition, holding that the Respondent's objections regarding pre-arbitral non-compliance were unmerited at this stage

The Court appointed Mr. V. K. Jain (Retd. Delhi High Court Judge) as the Sole Arbitrator to adjudicate the disputes

Source reference: para. 28

It directed that all rights and contentions regarding the merits and procedural compliance remain open for the Arbitrator to decide. Final relief was granted by referring the parties to arbitration and directing the Arbitrator to file a Section 12(2) disclosure

Source reference: paras. 31, 29, 33
Delhi High Court

Original Court PDF

M/S Rudra Interiors Pvt.Ltd.vsHindustan Prefab Limited & Anr.

Delhi High Court · April 22, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment