01Facts
The Respondents (Union of India, through GTB Hospital) issued a Notice Inviting Tender for comprehensive maintenance and work at GTB Hospital.
¶ 2The Petitioner's bid, being the lowest, was accepted.
¶ 2The Petitioner states that the work was completed, but the Respondents breached several terms of the agreement and failed to release payments exceeding ₹8 crores.
¶ 3–4The agreement incorporates the General Conditions of Contract (GCC), 2019, whose Clause 25 contains an arbitration clause.
¶ 5Before invoking arbitration, the Petitioner wrote to the Respondents on 15.05.2025 seeking reference of the disputes to a Disputes Redressal Committee (DRC).
¶ 6No DRC was constituted.
¶ 6At the prior hearing, the CGSC stated, in fairness, that she had received no instructions on the DRC or the Petitioner's communication.
¶ 7–8The Petitioner then sought appointment of a Sole Arbitrator under Section 11(6)(a) of the Arbitration and Conciliation Act, 1996.
¶ 1Both sides agreed that the arbitrator must have a requisite engineering background, with experience in public works contracts, and must have previously held a post not below Chief Engineer (equivalent to Joint Secretary to the Government of India).
¶ 1002Issues
i.1. Whether the Court should appoint an arbitrator under Section 11(6) of the Act where the contractual pre-arbitral DRC mechanism was not constituted despite the Petitioner's request, and the existence of the arbitration agreement is undisputed.
¶ 6, 9ii.2. Whether the appointment should be made subject to the agreed qualifications of the arbitrator and institutional rules, with all other objections (including arbitrability, limitation, and misjoinder) reserved for the arbitrator.
¶ 10, 11(iii), 11(v)03Law Applied
Section 11(6)(a) of the Arbitration and Conciliation Act, 1996, under which a party may seek appointment of an arbitrator.
¶ 1The arbitration clause (Clause 25) of the General Conditions of Contract (GCC), 2019, which binds the parties.
¶ 5The Petitioner's 15.05.2025 request for DRC reference and the Respondents' failure to constitute the DRC were treated as the trigger for invoking arbitration.
¶ 6, 9The parties' agreed qualifications for the arbitrator, namely an engineering background and senior public-works experience, were given effect.
¶ 10The arbitration is to be administered by the Delhi International Arbitration Centre (DIAC) under its Rules, with the arbitrator's fee fixed per the DIAC (Administrative Cost and Arbitrator's Fees) Rules, 2018.
¶ 11(ii)Disclosure by the arbitrator under Section 12 of the Act.
¶ 11(iv)The judgment cites no case law.
Provisions in the judgment · 2 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 11Section 12
04Reasoning
The Court found the arbitration agreement undisputed and the Petitioner's invocation proper, because it followed the Respondents' failure to constitute the DRC after the Petitioner's written request.
¶ 9The Respondents' counsel offered no instructions to the contrary, which left the factual record unrebutted.
¶ 8–9Because the parties had already agreed on the arbitrator's profile, the Court incorporated that agreed criteria into its directions rather than selecting the arbitrator independently.
¶ 10, 11(iii)Routing the appointment through DIAC, under its Rules and fee schedule, provided a neutral institutional mechanism for constituting the tribunal.
¶ 11(ii)–(iii)The Court limited its inquiry to the appointment itself. It expressly left open arbitrability, limitation, misjoinder, and the merits of any claim or counterclaim for the arbitrator to decide.
¶ 11(v)This reflects the limited scope of Section 11 proceedings.
¶ 11(v)05Holding
The disputes under the agreement are referred to arbitration.
¶ 11(i)DIAC is directed to appoint a Sole Arbitrator who has the requisite engineering background and senior public-works experience, with the arbitration to be conducted under the aegis of DIAC and its Rules.
¶ 11(ii), 11(iii)The arbitrator must furnish a Section 12 declaration before entering the reference.
¶ 11(iv)All contentions, including arbitrability, limitation, misjoinder, and the merits, are left open for the arbitrator.
¶ 11(v)The parties must approach DIAC within one week, the petition is disposed of accordingly, and the Registry is to communicate the order to the DIAC coordinator.
¶ 11(vi), 12, 13Original Court PDF