01Facts
The Petitioner (NHIDCL) awarded the Respondent (Sai GR Impex) an EPC contract, executed on 21.08.2020 for Rs. 28.3 crores, for a landslide protection gallery on NH-34 at Bareti, Uttarakhand.
Order ¶¶3–4The Respondent furnished bank guarantees and received a completion certificate.
Order ¶¶5–6The Respondent was also obliged to maintain the project for five years.
Order ¶7After a landslide in the 2023 monsoon, the Respondent carried out rectification work under protest between August and December 2023, contending the work was outside its scope.
Order ¶¶8–9The Petitioner issued a show-cause notice proposing termination and debarment, and on 13.11.2025 passed a debarment order.
Order ¶10 · ¶ 3 read with Order ¶13The Respondent invoked arbitration and filed a Section 9 petition. The Court directed no coercive action on 19.09.2025 and converted the petition into a Section 17 application on 08.10.2025.
Order ¶¶11–12On 24.03.2026, the Sole Arbitrator stayed the debarment order, prima facie finding the rectification work outside the contractual scope and taking note of the completion certificate.
Order ¶¶13–14The order was emailed to the parties on 25.03.2026.
¶ 4The Petitioner filed the appeal under Section 37(2)(b) on 30.06.2026.
¶ 2The Respondent objected that the appeal was filed 98 days after the order, i.e., 38 days beyond the 60-day limit.
¶ 2 · ¶ 5The Petitioner's explanation covered obtaining a legal opinion, seeking factual clarifications from the Project Management Unit, and finalising the draft appeal. It gave no particulars of why these could not be completed within time.
¶ 8 · ¶ 902Issues
i.1. Whether the appeal under Section 37(2)(b) of the Arbitration and Conciliation Act, 1996 is barred by limitation, having been filed beyond the 60-day period prescribed under Section 13(1A) of the Commercial Courts Act, 2015.
¶ 2–5ii.2. Whether the Petitioner has shown "sufficient cause" and due diligence warranting condonation of the 38-day delay.
¶ 6–1003Law Applied
The Court relied on Section 37(2)(b) of the Arbitration and Conciliation Act, 1996, read with Section 13(1A) of the Commercial Courts Act, 2015, which prescribe a 60-day limitation period for appeals against orders under Section 17.
¶ 3On condonation, the Court applied the Supreme Court's decision in Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460, which holds that condonation of delay in commercial matters is an exception, not the rule, and requires the appellant to show sufficient cause and requisite diligence.
¶ 7 · ¶ 10The Court also followed the Division Bench of this Court in Casablanca Apparels Pvt. Ltd. v. Polo/Lauren Company L.P., 2025 SCC OnLine Del 5191, which adopts the same strict approach.
¶ 7Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 37Section 17Section 9
Commercial Courts Act, 2015 Section 13
04Reasoning
The Court took the impugned order's date of 24.03.2026 as the starting point. It counted 98 days to the filing on 30.06.2026, which exceeds the 60-day limit by 38 days.
¶ 4–5The Court did not treat the email communication of 25.03.2026 as altering the computation.
¶ 4Applying Borse Brothers, the Court held that the reasons given (legal opinion, factual clarifications from the PMU, and finalisation of the draft) are administrative formalities and do not amount to sufficient cause.
¶ 8 · ¶ 10The application contained only a broad chronology and lacked material particulars explaining why these steps could not be completed within the limitation period. It therefore also failed to demonstrate the diligence required.
¶ 9 · ¶ 10Because the Court found that the delay was not condonable, it did not examine the merits of the Section 17 stay or the Arbitrator's prima facie findings.
05Holding
The Court held that the Petitioner failed to show sufficient cause for the 38-day delay. The appeal under Section 37(2)(b) is therefore barred by limitation.
¶ 11The appeal is dismissed as time-barred, along with all pending applications, if any.
¶ 12The merits of the Arbitrator's order dated 24.03.2026 staying the debarment order were not adjudicated.
¶ 11–12Original Court PDF
National Highway Infrastructure Development Corporation LtdvsSai Gr Impex Pvt Ltd