01Facts
The petitioner, NHAI, challenged under Section 34 of the Arbitration and Conciliation Act, 1996 a majority arbitral award dated 13.05.2015.
The dispute arose under a Contract Agreement dated 12.04.2006 for widening and strengthening NH-26 (Package ADB-II/C-7, km 255 to 297), priced at Rs.189.63 crores.
¶ 2–3Work commenced 27.05.2006 with scheduled completion on 26.11.2008, but was completed on 05.12.2009.
¶ 2–3The Engineer recommended, and NHAI granted, an extension of time (EOT) of 374 days without penalty or liquidated damages.
¶ 2–3The contractor's claims before the Dispute Adjudication Board were not resolved, and arbitration was invoked on 05.02.2011.
¶ 4, 8The contractor claimed Rs.40,33,65,879 under seven heads, comprising material price claims (1A–1D), extended plant stay (2), financing charges (3), site and head-office overheads (4–5), loss of bonus (6), and loss of profit-earning capacity (7).
¶ 9–10NHAI contended that price escalation was already paid under Clause 70, that the delay was not attributable to it, and that notice and record requirements were not met.
¶ 11By majority, the Tribunal awarded Rs.15,80,42,030 under Claims 1A–1D, 2, 4 and 5, rejected Claims 3, 6 and 7, and awarded interest at 10% p.a. compounded monthly from 05.02.2011 under Sub-Clause 60.8.
¶ 6–7, 1902Issues
i.1. Whether the impugned award goes beyond the terms of the contract or otherwise falls within a ground for setting aside under Section 34 of the Act.
¶ 45(i)ii.2. Whether the Arbitral Tribunal was justified in allowing additional costs for the 374-day extended period.
¶ 45(ii), 50–60iii.3. Whether Claim Nos. 1A to 1D were barred by the price-adjustment provisions in Clause 70 of COPA.
¶ 45(iii), 61–72iv.4. Whether Claim No. 2 (extended stay of plant and equipment) lacks sufficient evidentiary or contractual support.
¶ 45(iv), 73–83v.5. Whether Claim Nos. 4 and 5 (site and head-office overheads) fail for want of notice, contemporary records and verification.
¶ 45(v), 84–99vi.6. Whether the award of interest under Sub-Clause 60.8 warrants interference.
¶ 45(vi), 102–10803Law Applied
The Court's review is confined to the grounds in Section 34 of the Act, and it does not sit in appeal over factual findings.
¶ 47Under Ssangyong Engineering & Construction Co. Ltd. v. NHAI (2019) 15 SCC 131, patent illegality under Section 34(2A) must go to the root of the matter, and an erroneous application of law does not by itself warrant setting aside.
¶ 48Under Sumitomo Heavy Industries Ltd. v. ONGC (2010) 11 SCC 296, a plausible contractual interpretation by the tribunal is not to be substituted by the Court.
¶ 49Under NHAI v. Progressive-MVR (JV) (2018) 14 SCC 688, Sub-Clauses 70.2 and 70.3 cannot be circumvented by relabelling an excluded escalation claim as a prolongation claim, though a separate entitlement under other clauses may survive.
¶ 63–65Under McDermott International Inc. v. Burn Standard Co. Ltd. (2006) 11 SCC 181, quantification is ordinarily for the tribunal, and Section 34 courts must not act as courts of appeal.
¶ 77, 111Under Batliboi Environmental Engineers Ltd. v. HPCL (2024) 2 SCC 375, a formula-based quantification must be rationally supported and must not yield an unjustified windfall or double recovery.
¶ 78On interest, NHAI v. Hindustan Construction Co. Ltd., 2025:DHC:9222, holds that Sub-Clause 60.8's "sums payable" may include amounts found due by the tribunal.
¶ 104The contractual clauses applied are COPA Clauses 6.4, 12.2, 42.2 (delay and employer-default compensation), 53.1–53.4 (notice and contemporary records), 60.8 (interest) and 70 (price adjustment).
¶ 22, 36–37, 62Provisions in the judgment · 6 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 34Section 23
Indian Contract Act, 1872 Section 6Section 12Section 42Section 44
04Reasoning
The Court held that the 374-day EOT, though not conclusive by itself, was supported by the Engineer's reasons, the absence of liquidated damages, the Tribunal's identification of specific employer-attributable delay events, and NHAI internal communication dated 25.01.2010.
¶ 50–57NHAI's request to reallocate responsibility event by event was held to be a factual reassessment outside Section 34.
¶ 54, 58, 60On Claims 1A–1D, the Court found the claims were limited to materials consumed during the extended period, were credited for Clause 70 adjustments, and were therefore compensation under Clauses 6.4, 12.2 and 42.2 rather than enhanced escalation.
¶ 67–72The Court held that the interpretation adopted by the Tribunal was plausible and harmonious, and that no double recovery was shown.
¶ 67–72On Claim No. 2, the Court held that the award of Rs.4,55,10,280 was the claimed actual ownership cost, not the higher Rs.11,80,32,831 formula figure, and that supporting monthly reports, invoices, the auditor's certificate and the Engineer's joint verification of 14.03.2009 provided an identifiable evidentiary basis.
¶ 74–83On Claims 4 and 5, the Court treated the MoRTH Data Book weighted-rate method (11.64%) with a 15% mitigation deduction as a discernible quantification method, and found that NHAI's criticism of its methodology did not show patent illegality or double recovery.
¶ 88–92The Court further held that the Tribunal's rejection of Claims 3, 6 and 7 showed it examined each head separately rather than accepting claims mechanically.
¶ 100–101On interest, the Court accepted that the rate and monthly compounding were drawn from Sub-Clause 60.8 and the Appendix to Bid, and that the commencement date of 05.02.2011 was not shown to contradict the contract, although the due date must ordinarily be tied to the contractual payment mechanism.
¶ 105–10805Holding
The Court held that NHAI did not establish any ground under Section 34 to set aside the award.
¶ 112–114The majority's conclusions on the 374-day extended period, the Clause 70 interpretation, Claim No. 2, Claims 4 and 5, and interest were held to be supported by the record and plausible contractual readings.
¶ 112–114The Section 34 petition is dismissed, and the award dated 13.05.2015 is upheld.
¶ 115, 117The amounts awarded under Claim Nos. 1A–1D, 2, 4 and 5, with interest as awarded, remain payable, and there is no order as to costs.
¶ 116, 118Original Court PDF
National Highways Authority Of IndiavsBscpl Infrastructure Limited