01Facts
The Petitioner, the Public Works Department, Govt. of NCT of Delhi, challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.
¶ 1The award was corrected on 27.09.2024.
¶ 8The Petitioner sought an opinion from its arbitration counsel, received on 25.09.2024, and then routed the matter through the Superintending Engineer, Finance Officer, Chief Engineer, Principal Chief Engineer, Engineer-in-Chief and the Law Department for approval.
¶ 2 · pp. 1–2The draft petition was sent for approval on 23.01.2025, and the petition was filed on 24.01.2025.
¶ 2, 8The 120-day outer limit was stated to expire on 25.01.2025.
¶ 3The Petitioner sought condonation of a 29-day delay in filing and a 264-day delay in re-filing.
¶ 1For re-filing, the Petitioner relied on the voluminous record (about 1,907 pages), a bereavement in counsel's family, and the serious illness of counsel's mother.
¶ 4, 13The Respondent opposed both applications, contending that the petition was beyond the statutory maximum and that the re-filing delay was unexplained.
¶ 602Issues
i.1. Whether the Petitioner has shown sufficient cause for condonation of the 29-day delay in filing beyond the three-month period under Section 34(3) of the Act, notwithstanding that the initial filing fell within the 120-day outer limit.
¶ 8–10ii.2. Whether the 264-day delay in re-filing can be condoned where the Petitioner has not satisfactorily explained the entire period of delay.
¶ 12–1703Law Applied
Section 34(3) of the Arbitration and Conciliation Act, 1996, under which an application to set aside an award must be filed within three months of receipt of the award, with a maximum extension to 120 days, and a filing within the outer limit does not by itself entitle a party to condonation beyond the three-month period.
¶ 6, 8Government of NCT of Delhi v. Shyam Sunder Tyagi (2026 SCC OnLine Del 5360), where the Division Bench held that delay in re-filing commercial matters must be treated with nearly the same seriousness as delay in filing, and that where counsel's personal exigencies are relied upon, the absence of explanation for the period after those exigencies ceased disentitles the litigant to condonation.
¶ 11, fn. 2Public Works Department v. Shyam Sunder Tyagi (2026 SCC OnLine Del 4214), which holds that the entire period of re-filing delay must be satisfactorily explained, and an unexplained period disentitles the party from condonation.
¶ 16, fn. 3Chief Engineer, ESIC v. Enarch Consultants Pvt. Ltd. (2026:DHC:5562), which holds that limitation cannot be circumvented by reference to internal administrative processes that do not furnish a legally sustainable explanation.
¶ 18, fn. 4Provisions in the judgment · 1 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 34
04Reasoning
The Court accepted that the initial petition was filed within the 120-day outer limit, but held that this did not dispense with the need to show sufficient cause for the 29-day delay beyond the three-month period.
¶ 8The internal movement of the file among departments and the time taken to obtain approvals were treated as administrative procedure, not circumstances beyond the Petitioner's control.
¶ 9–10On the re-filing delay, the Court held that the entire 264 days had to be accounted for.
¶ 12The personal difficulties of counsel related mainly to April 2025, whereas the delay extended from January to October 2025.
¶ 14No explanation was offered for the remaining period, and the voluminous record did not explain why defects could not be cured within a reasonable time.
¶ 15Applying the Division Bench principles in Shyam Sunder Tyagi and Enarch Consultants, the Court found the explanation neither comprehensive nor adequate.
¶ 17–1805Holding
The Court held that the Petitioner had not shown sufficient cause for either the 29-day delay in filing or the 264-day delay in re-filing.
¶ 17, 19I.A. 25871/2025 (delay in filing) and I.A. 25873/2025 (delay in re-filing) were dismissed, and consequently O.M.P. (COMM) 427/2025 under Section 34 of the Act was dismissed, and pending applications, if any, were disposed of.
¶ 19–21Original Court PDF
Public Works Department, Govt. Of Nct Of DelhivsM/S. Sps Infrabuild Pvt. Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
