Delhi High CourtArbitration and MediationContract Law

Arbitral tribunal cannot create payment for excess cement absent contractual basis; such award is patently illegal under Section 34.

Delhi Development Authorityv.B.G.Shirke Constructions Technology Private Limited

Arbitral tribunal cannot create payment for excess cement absent contractual basis; such award is patently illegal under Section 34.. Delhi Development Authority vs B.G.Shirke Constructions Technology Private Limited. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Tribunal's holding that 330 kg/cum is the minimum cement content for M-30 concrete, based on a supposed inconsistency between Clauses 9.1.2 and 9.1.3, is a plausible contractual interpretation or is patently illegal.

The court held

The Tribunal's interpretation fixing 330 kg/cum as the minimum for M-30 and its award of payment for excess M-30 cement are patently illegal and cannot be sustained.

It also directed

Both awards dated 22.05.2017 are set aside insofar as they: (a) hold that 330 kg/cum is the minimum cement content for M-30; (b) award Rs. 3,16,78,614 for M-30 excess cement up to 30.06.2015; (c) direct payment at Rs. 6/kg from 01.07.2015; (d) direct refund of M-30 cement recoveries founded on the same erroneous reciprocal entitlement; and (e) award consequential interest on those reliefs. The Tribunal's findings on M-25 and M-35, and all other findings, remain undisturbed. Both petitions are allowed in these terms, with no order as to costs.

01Facts

The DDA invited tenders for LIG and EWS housing in Narela and Rohini, divided into Group-I and Group-II works.

¶ 2

Letters of award dated 18.04.2013 were issued to the Respondent and agreements were executed on 25.04.2013.

¶ 3

Clause 9.1.2 applied the minimum cement content under CPWD Specifications 2009 and IS:456, which permit 330–500 kg/cum.

¶ 5–6, 28

Clause 9.1.3 prescribed a minimum of 360 kg/cum for "any grade RCC," and specified 410 kg/cum (M-25) and 428 kg/cum (M-35) as recovery thresholds.

¶ 5, 30

The Respondent flagged this inconsistency at two pre-bid meetings; the DDA replied that the "NIT provision shall prevail."

¶ 7

On DDA's instructions, the Respondent used 410 kg/cum of cement in M-30 concrete and claimed payment for the excess above 330 kg/cum; the DDA refused.

¶ 8, 13

The Tribunal (S.R. Pandey, P.S. Chadha, K.K. Varma, JJ.) rejected the DDA's jurisdictional objection under Clause 8.2.

¶ 10–11

Applying contra proferentem against the DDA as drafter, the Tribunal held that 330 kg/cum applied to all grades, rejected the M-25 claim, and awarded Rs. 3,16,78,614 for M-30 excess cement up to 30.06.2015, plus Rs. 6/kg for later consumption and a refund of recoveries.

¶ 12–13

The DDA challenged both awards under Section 34 of the Act.

¶ 1

02Issues

i.1. Whether the Tribunal's holding that 330 kg/cum is the minimum cement content for M-30 concrete, based on a supposed inconsistency between Clauses 9.1.2 and 9.1.3, is a plausible contractual interpretation or is patently illegal.

¶ 30–38

ii.2. Whether the Tribunal could award payment for cement consumed in excess of the baseline for M-30 concrete when the Agreement provides no such entitlement and the claim was not founded on quantum meruit.

¶ 39–51

iii.3. Whether the Tribunal's interpretation of Clauses 9.1.2 and 9.1.3 as regards M-25 and M-35 warrants interference under Section 34.

¶ 35

03Law Applied

Section 34 of the Arbitration and Conciliation Act, 1996 provides that an award is reviewed only within its limited grounds, and an award that ignores express contractual stipulations or rewrites the contract is patently illegal.

¶ 24, 47

Under Section 28(2), an arbitral tribunal may decide ex aequo et bono only where the parties expressly authorise it, so equity cannot justify an award.

¶ 43

Following South East Asia Marine Engineering and Construction Ltd. (SEAMEC) v. Oil India Ltd. (2020) 5 SCC 164, a contract must be read as a whole and harmoniously, and an interpretation defeating its express wording is not a possible one.

¶ 25

Following GMR Ambala Chandigarh Expressways Pvt. Ltd. v. NHAI (O.M.P. (COMM) 480/2020), neither a court nor a tribunal may add to or subtract from commercial contracts or supply casus omissus.

¶ 26

A tribunal is a creature of the contract and must operate within its four corners.

¶ 47

In a lump-sum contract, parties are bound by their bargain.

¶ 48

The contra proferentem rule, applied by the Tribunal, operates only where a real ambiguity exists.

¶ 12, 32, 38

The Respondent's claims invoked Sections 70 and 73 of the Indian Contract Act, 1872, but these were not pleaded or adopted in the awards.

¶ 17, 23, 42

CPWD Specifications, paras. 5.8.4.1–5.8.4.2, permit cement content between 330 and 500 kg/cum, to be fixed through design mix.

¶ 15, 44

Provisions in the judgment · 4 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 34Section 28

Indian Contract Act, 1872 Section 70Section 73

04Reasoning

The Court first reaffirmed that interpretation of contract is for the Tribunal and that a plausible view cannot be disturbed under Section 34.

¶ 24, 35

The Court upheld the Tribunal's treatment of M-25 and M-35, since Clause 9.1.2 refers to those grades and the Tribunal's view of the inconsistency was plausible.

¶ 35

On M-30, the Court found the Tribunal erred because Clause 9.1.2 does not mention M-30, while Clause 9.1.3 expressly covers "any grade of RCC" and fixes 360 kg/cum.

¶ 36–37

No ambiguity therefore existed for M-30, so resort to contra proferentem was unwarranted, and the Tribunal overrode the express term.

¶ 38

The absence of a recovery threshold for M-30 only bars the DDA from recovering deficits. It does not create a corresponding right for the contractor to be paid for excess consumption.

¶ 41

Because the claim was not based on quantum meruit and no contractual clause authorised the payment, the Tribunal's award rested on fairness, which Section 28(2) prohibits.

¶ 42–43

The 410 kg/cum requirement fell within the CPWD range, so the Respondent should have priced for it.

¶ 44–45

The Tribunal's use of the Rs. 6/kg recovery rate in reverse, to pay for excess consumption, had no contractual basis.

¶ 46

Since the DDA's hands were not tied to a fixed baseline, a design-mix quantity could be fixed within the prescribed limits.

¶ 50

The M-30 award was not a contest between plausible interpretations but a creation of an entitlement with no contractual or legal foundation, making it patently illegal.

¶ 51

05Holding

The Tribunal's interpretation fixing 330 kg/cum as the minimum for M-30 and its award of payment for excess M-30 cement are patently illegal and cannot be sustained.

¶ 38, 51

Both awards dated 22.05.2017 are set aside insofar as they: (a) hold that 330 kg/cum is the minimum cement content for M-30; (b) award Rs. 3,16,78,614 for M-30 excess cement up to 30.06.2015; (c) direct payment at Rs. 6/kg from 01.07.2015; (d) direct refund of M-30 cement recoveries founded on the same erroneous reciprocal entitlement; and (e) award consequential interest on those reliefs. The Tribunal's findings on M-25 and M-35, and all other findings, remain undisturbed. Both petitions are allowed in these terms, with no order as to costs.

¶ 53–55
Delhi High Court

Original Court PDF

Delhi Development AuthorityvsB.G.Shirke Constructions Technology Private Limited

Delhi High Court · November 23, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment