Facts
The petitions arose from nine arbitral proceedings between the parties.
Source reference: p.2, para. 5The Delhi High Court had initially appointed Hon’ble Mr. Justice Swatanter Kumar (Retd.), former Judge of the Supreme Court, as the Sole Arbitrator on 8 January 2021, before whom the proceedings substantially progressed.
Source reference: p.2, para. 5Following proceedings seeking substitution, the Court appointed Hon’ble Mr. Justice G.S. Sistani (Retd.) as the substituted Sole Arbitrator on 14 May 2024.
Source reference: p.2, para. 6By order dated 1 July 2024, Justice Sistani declined the Petitioners’ proposed fee and cancelled further hearings.
Source reference: p.2, para. 7; p.3, para. 8He subsequently confirmed his withdrawal from all nine proceedings by email dated 26 January 2025.
Source reference: p.3, para. 8The Petitioners therefore filed O.M.P.(T)(COMM.) 79/2024 under Sections 14 and 15 of the Arbitration and Conciliation Act, 1996 (“the Act”) for substitution of the Arbitrator, and O.M.P.(MISC.)(COMM.) 956/2025 under Section 29A for extension of the arbitral mandate.
Source reference: p.1, paras. 2–3Four references had reached the stage of final arguments, while the remaining five were at different stages.
Source reference: p.4, para. 15Issues
Whether Hon’ble Mr. Justice G.S. Sistani (Retd.), having withdrawn from the nine arbitral proceedings, should be substituted under Sections 14 and 15 of the Act.
Source reference: p.1, para. 2; p.3, paras. 9, 12–13Whether sufficient cause existed to extend the mandate of the nine arbitral proceedings under Section 29A of the Act, despite the mandate having expired.
Source reference: p.1, para. 3; p.5, paras. 17–18From what stage should the substituted Arbitrator continue the nine arbitral proceedings.
Source reference: p.4, paras. 14–16Law Applied
The Court applied Sections 14 and 15 of the Arbitration and Conciliation Act, 1996, which permit termination and substitution of an arbitrator where the arbitrator withdraws from office or is otherwise unable to perform the mandate.
Source reference: no citationIt also applied Section 29A of the Act, under which the Court may extend the arbitral mandate where sufficient cause is shown.
Source reference: no citationThe Court further applied the procedural principle that, upon substitution, the arbitral proceedings should ordinarily continue from the stage at which they were left, subject to directions necessary to ensure an expeditious and fair conclusion.
Source reference: no citationReasoning
The Court found that Justice Sistani had withdrawn from office and that, consequently, no further proceedings could take place in any of the nine references.
Source reference: p.3, para. 12Since the Respondents did not identify any objection on the merits either to substitution or to extension of the mandate, and there was no material suggesting prejudice to either party, substitution was considered necessary to secure the expeditious continuation of the arbitrations.
Source reference: p.3, paras. 11, 13The Court also held that the prolonged pendency and inconclusiveness of the proceedings resulted primarily from the Arbitrator’s withdrawal, constituting sufficient cause under Section 29A for extending the mandate.
Source reference: p.5, para. 17To preserve procedural progress, the substituted Arbitrator was directed to commence the four references in which final arguments had already been heard from that stage, and to continue the remaining five references from their respective stages.
Source reference: p.4, paras. 15–16Holding
The Court allowed both petitions in the terms stated.
Mr. Attau Rahman Masoodi, Retd. Judge of the Allahabad High Court, was appointed as the substitute Sole Arbitrator for all nine references and directed to proceed within three weeks.
Source reference: p.4, para. 14The four references at the stage of final arguments were to continue from that stage, while the remaining five were to proceed from the stages at which they had been interrupted.
Source reference: p.4, para. 16The mandate of all nine arbitral proceedings was extended for one year from 8 September 2026, and the period up to that date was regularised.
Source reference: p.5, para. 18The Arbitrator’s fees were left to be mutually determined by the parties and the Arbitrator.
Source reference: p.5, para. 19The petitions were accordingly disposed of.
Source reference: p.5, paras. 20–21Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19962
Original Court PDF
Dalmia Family Office Trust & Anr.vsAlmond Infrabuild Private Limited & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
