01Facts
The petitioners claim interest in a portion of Survey No. 6/1A (now Survey No. 6), Govindapura Village, Yelahanka Hobli, Bengaluru North Taluk.
¶ 1The petitioners challenge a notice dated 13.10.2026 issued by the Fifth Respondent (Bengaluru North City Corporation).
¶ 1The notice refers to a Notification dated 13.01.2010 under Sections 3 and 7 of the Works of Defence Act, 1903, which bars construction within 100 metres of defence property, and alleges that the petitioners built contrary to that Notification.
¶ 1The notice also refers to contempt proceedings in CCC No. 575 of 2024 and to the Court's earlier order in W.P. No. 35240/2014.
¶ 1The petitioners' Senior Counsel submitted that (a) their predecessors-in-interest held the property in Survey No. 6; (b) they acquired title under registered documents from 03.09.2013, based on a compromise accepted by a competent civil court; and (c) the construction has remained unchanged since the Notification was gazetted.
¶ 2Counsel argued that the Court's order dated 07.09.2022 in the earlier writ petition requires proceedings under the Act to determine compensation, and that the petitioners cannot be compelled to vacate or demolish until compensation is determined.
¶ 2The petition also seeks directions for compensation proceedings under Sections 9, 10 and 12 of the Act and quashing of the Union's Guidelines dated 18.05.2011.
The Standing Counsel for the Respondents were heard.
¶ 302Issues
i.1. Whether this Court should intervene at the show-cause stage, before the Fifth Respondent determines whether the petitioners' property falls within the 2010 Notification.
¶ 3ii.2. Whether the petitioners must place material on record to show that their property is outside the Notification, and whether they are entitled to reasonable time to do so rather than the time contemplated in the contempt proceedings.
¶ 3iii.3. Whether the Sixth Respondent must decide the petitioners' reply in accordance with the procedure under the Act, considering all materials filed.
¶ 403Law Applied
The Works of Defence Act, 1903, particularly the Notification dated 13.01.2010 issued under Sections 3 and 7, which prohibits construction within 100 metres of defence property.
¶ 1The Act's compensation mechanism, including Sections 9, 10 and 12, governs the determination of compensation for affected property, and the petitioners contend that compensation must be determined before any demolition.
¶ 2A party asserting that its property falls outside a statutory notification bears the burden of placing material to establish that position, and the competent authority must first examine that material.
¶ 3The Court's earlier order in W.P. No. 35240/2014 dated 07.09.2022, which the petitioners invoked as directing compensation proceedings.
¶ 2No precedent is cited in the order.
Provisions in the judgment · 5 · Linked ones open on LawLens
Works of Defence Act, 1903 Section 9Section 10Section 12Section 3Section 7
04Reasoning
The Court declined to pronounce prima facie on whether the petitioners' property is covered by the Notification, because nothing on record at that stage supported such a view.
¶ 3The Court treated the coverage question as one for the Fifth Respondent, who issued the notice, to decide. If the property falls within the Act, the petitioners' claim to compensation would not arise.
¶ 3The burden to show exclusion from the Notification lies on the petitioners, who must be given reasonable time to file material.
¶ 3The Court expressly preferred that reasonable time over the shorter period implied by the pending contempt proceedings.
¶ 3To ensure a reasoned decision on that material, the Court directed the Sixth Respondent, the Deputy Commissioner, to consider the reply together with all materials filed and the procedure under the Act.
¶ 4The order does not address the petitioners' contention that compensation must precede demolition, the validity of the 2011 Guidelines, or the scope of the 2022 order, and leaves those questions open.
05Holding
The Court declined to interfere at this stage. It holds that the question whether the petitioners' property falls within the 2010 Notification must first be examined by the competent authority, and that the petitioners bear the burden of placing material on record to show otherwise.
¶ 3The petition is disposed of with liberty to the petitioners to file a response to the impugned Show Cause Notice by 30.11.2026.
¶ 4The Sixth Respondent is directed to examine that reply in light of the defence the petitioners present, including the contentions recorded in the order, and in accordance with the procedure under the Act.
¶ 4Original Court PDF