Facts
The Appellants were awarded an e-tender on January 17, 2024, for providing webcasting solutions for the 2024 Lok Sabha elections in West Bengal
Source reference: para. 2They furnished Earnest Money Deposit (EMD) and Performance Bank Guarantees (BGs) totaling approximately ₹2.59 Crores
Source reference: para. 4Following the completion of the work, the Appellants received completion certificates from 23 District Election Officers (DEOs)
Source reference: para. 6On December 30, 2024, the Respondent released the contract price (approx. ₹26.45 Crores) after a deduction of ₹93.80 lakhs recommended by the IT Steering Committee
Source reference: para. 11Despite full payment, the Respondent issued a show-cause notice (SCN) on July 7, 2025, alleging technical deficiencies, such as cameras going offline and lack of technical support, and threatened to forfeit the EMD/BGs and blacklist the Appellants
Source reference: para. 14, 26The Appellants challenged this SCN via a writ petition, which was dismissed by a learned Single Judge on July 15, 2025
Source reference: para. 1, 16This appeal was filed against said dismissal.
Source reference: no citationIssues
1. Whether a writ court should interfere with a show-cause notice issued by a state authority in a contractual matter alleging breach of performance
Source reference: para. 18, 282. Whether the release of final payment and issuance of completion certificates by the state acts as an estoppel against subsequent punitive action for contractual deficiencies
Source reference: para. 17(b), 333. Whether the High Court can interdict the invocation of unconditional Bank Guarantees within its writ jurisdiction when factual disputes exist
Source reference: para. 34-35Law Applied
The court applied the principles governing judicial review of show-cause notices as established in Union of India v. Vicco Laboratories, which holds that interference at the SCN stage is rare unless there is a total lack of jurisdiction or abuse of process
Source reference: para. 18, 36(v)It further relied on Siemens Ltd v. State of Maharashtra regarding the maintainability of writs when a notice is issued with a pre-meditated or "closed mind"
Source reference: para. 36(ii)On contractual maintainability, the court cited Unitech Limited v. Telangana State Industrial Infrastructure Corp., noting that while Article 226 applies to state contracts, it should not be used to resolve disputed questions of fact requiring evidentiary trial
Source reference: para. 31, 36(vi)Regarding Bank Guarantees, the court followed Gujarat Maritime Board v. Larsen & Toubro, which emphasizes that a bank guarantee is an independent, unconditional contract, and its invocation should not be stayed by a writ court when performance breaches are alleged
Source reference: para. 35Reasoning
The Court observed that the SCN was not without jurisdiction, nor was it an abuse of process
Source reference: para. 29It rejected the Appellants' argument of "pre-meditation," finding no tangible material to suggest the Respondent had already pre-judged the issue
Source reference: para. 29The Court emphasized that the dispute was essentially factual, involving technical parameters like camera uptime, server logs, and onsite support, which are unsuitable for summary adjudication under Article 226
Source reference: para. 30, 32While the Appellants argued that the release of payment implied "satisfactory performance," the Court held that clearing bills does not precludes an authority from later discovering and acting upon deficiencies that may have escaped notice during initial processing
Source reference: para. 33Regarding the BGs, the Court held they are independent contracts between the bank and the beneficiary; since they were irrevocable and unconditional, the writ court would not interfere, especially when the underlying dispute involves complex facts
Source reference: para. 34-35Holding
The Division Bench dismissed the appeal and upheld the Single Judge’s order, finding no infirmity in the refusal to quash the SCN
The Court held that the Appellants must reply to the SCN within a fortnight
Source reference: para. 38It directed the Respondent to decide the matter fairly, following principles of natural justice, after providing a hearing
Source reference: para. 38However, to protect the Appellants, the Court ordered that any adverse decision passed by the Respondent shall not be given effect for two weeks from the date of such decision to allow the Appellants to seek legal recourse
Source reference: para. 38The prayer to restrain the invocation of Bank Guarantees was denied
Source reference: para. 34Original Court PDF
PHO COM NET PVT LTD AND ANRvsTHE OFFICE OF THE CHIEF ELECTORAL OFFICER GOVT OF WEST BENGAL
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in