The question

1. Whether the High Court should adjudicate the merits of the Commissioner's order dated 08.09.2026 while statutory revisions under Section 99 are pending before the Government.

The court held

The Court declined to decide the merits of the challenge to the Commissioner's order dated 08.09.2026, because the revisions under Section 99 must first be decided by the Government.

It also directed

Both writ petitions are disposed of to the limited extent of directing the Government to dispose of the respective revisions, following due procedure and affording all parties, including the Devaswom, an opportunity of hearing, as expeditiously as possible and not later than four months from receipt of the judgment. The interim orders granted by the High Court continue in effect until the revisional orders are passed and communicated to the parties.

01Facts

Both petitions challenge the order of the Commissioner, Malabar Devaswom Board, dated 08.09.2026 (Order No. H6-322/2022/MDB).

¶ 1

Both petitioners have filed statutory revisions against that order before the Government under Section 99 of the Madras Hindu Religious and Charitable Endowments (Amendment) Act, 2008.

¶ 2

The petitioners are protected by interim orders of this Court, which remain in force.

¶ 6

The underlying dispute concerns a 2017 lease between the Ramanathapuram Grama Devaswom and M/s Club VI, and related construction and Devaswom payment issues, with earlier proceedings in W.P.(C) No. 21044/2022.

The revision dates are given inconsistently in the Appendix (09.11.2026 in WP(C) 39295, Ex. P16; 3.11.2026 in WP(C) 40137, Ex. P6).

02Issues

i.1. Whether the High Court should adjudicate the merits of the Commissioner's order dated 08.09.2026 while statutory revisions under Section 99 are pending before the Government.

¶ 3

ii.2. Whether the petitioners are entitled to a direction requiring the Government to dispose of the pending revisions expeditiously, and on what timeline.

¶ 4–6

03Law Applied

Section 99 of the Madras Hindu Religious and Charitable Endowments (Amendment) Act, 2008 provides a statutory revision to the Government against the Commissioner's order.

¶ 2

The writ court should not decide issues that are primarily factual or mixed questions of fact and law where the statutory authority has not yet decided them at first instance, so that the Government's revisional decision becomes imperative.

¶ 3

The judgment cites no precedents and no other statutory provisions.

Provisions in the judgment · 1

Madras Hindu Religious and Charitable Endowments (Amendment) Act, 2008 Section 99

04Reasoning

The contentions raised were largely factual or mixed questions of fact and law, and therefore could not be examined on the merits by the writ court before the Government ruled on the revisions.

¶ 3

Both petitioners and the Standing Counsel for the Malabar Devaswom Board sought an early disposal of the revisions. The Special Government Pleader agreed that the revisions could be decided after hearing the parties and requested four months.

¶ 4–5

Accepting this framework, the Court allowed the writ petitions only to the extent of directing the Government to decide the revisions, after due procedure and after hearing the parties, including the Devaswom. The Court kept the interim orders in place until the Government's orders are passed and communicated. The disposal was structured to avoid prejudging the merits while preventing indefinite delay in the statutory remedy.

¶ 6

05Holding

The Court declined to decide the merits of the challenge to the Commissioner's order dated 08.09.2026, because the revisions under Section 99 must first be decided by the Government.

¶ 3

Both writ petitions are disposed of to the limited extent of directing the Government to dispose of the respective revisions, following due procedure and affording all parties, including the Devaswom, an opportunity of hearing, as expeditiously as possible and not later than four months from receipt of the judgment. The interim orders granted by the High Court continue in effect until the revisional orders are passed and communicated to the parties.

¶ 6
Kerala High Court

Original Court PDF

RAMANATHAPURAM GRAMA DEVASWOMvsTHE STATE OF KERALA

Kerala High Court · November 24, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment