Facts
The Petitioner was awarded a contract by the CPWD for the construction of internal roads at the 33rd Bn. ITBP, Sonapur, Guwahati
Source reference: p. 3-4The Petitioner failed to complete the work, citing a lack of permissions from the Forest Department and a ban by the District Administration
Source reference: p. 4Consequently, the CPWD issued a show-cause notice and subsequently terminated the contract and invoked the Bank Guarantee
Source reference: p. 4The Petitioner approached the High Court under Article 226 seeking to quash the termination and show-cause notice, and for a refund of the performance guarantee
Source reference: p. 3Issues
1. Whether the failure to perform the contract was due to a breach by the Petitioner or circumstances beyond their control
Source reference: p. 42. Whether the High Court should exercise its writ jurisdiction under Article 226 when the dispute involves complex factual determinations and a contractual dispute resolution mechanism exists
Source reference: p. 4, 7-8Law Applied
Clause 25 of the General Conditions of Contract (GCC), 2014, which provides a comprehensive Dispute Redressal Committee (DRC) and Arbitration framework for all disputes arising out of the contract, including termination
Source reference: p. 5-7Section 14 of the Limitation Act, 1963, which allows for the exclusion of time spent in bona fide litigation before a forum that lacks jurisdiction when computing the period of limitation for a subsequent proceeding
Source reference: p. 8Reasoning
The court determined that the crux of the matter—whether the Petitioner was restricted by conditions beyond its control—is a disputed question of fact requiring evidence to be led
Source reference: p. 4In its reasoning, the court observed that such factual inquiries are not suited for summary writ proceedings under Article 226
Source reference: p. 4-5Referring to Clause 25 of the GCC, the court noted that the parties had already agreed upon a specific forum (DRC followed by Arbitration) to resolve such grievances
Source reference: p. 5Since the agreement provides an efficacious alternative remedy and the issues require detailed factual examination, the court found it inappropriate to exercise its extraordinary jurisdiction
Source reference: p. 7Holding
The Court dismissed the writ petition, holding that it was not inclined to entertain the matter due to the existence of an alternative dispute resolution mechanism and the intensive factual nature of the dispute
The Court directed that the dismissal shall not prejudice the Petitioner’s right to initiate proceedings under Clause 25 of the GCC
Source reference: p. 8Under Section 14 of the Limitation Act, the Court ordered that the period from the filing of the writ (26.04.2021) until the date of the judgment shall be excluded from the limitation period calculation for any future proceedings
Source reference: p. 8Original Court PDF
Surajit DekavsUnion Of India And 3 Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in