Facts
The 21 writ petitioners were engaged as Pro-rata Casual Labourers on a daily wage basis in various departments of North Eastern Hill University (NEHU).
Source reference: para. 1They sought quashing of a letter dated 20.04.2011, under which wages for March 2011 were payable only on an actual-days-worked basis, without the additional payment of 1/6th day.
Source reference: para. 1The petitioners contended that they were re-engaged for 89 days instead of the customary 90 days, that their service was continuous without break, and that the resulting wage deduction was arbitrary.
Source reference: para. 1The respondents countered that the letter dated 20.04.2011 stood replaced by an order dated 15.06.2011, which granted casual labourers working a five-day week additional wages of 1/6th of the total days actually worked, effective March 2011.
Source reference: para. 3The respondents further demonstrated contradictions in the attendance registers produced by Petitioners No. 2 and 3 — the former had signed on all seven days of the week while the latter had never signed on Saturdays and Sundays — giving rise to disputed questions of fact.
Source reference: para. 4The writ petition was filed in 2023, i.e., approximately 13 years after the cause of action arose in 2011.
Source reference: para. 5Issues
1. Whether a writ petition challenging a letter dated 20.04.2011, presented after a lapse of 13 years, is maintainable in light of the doctrine of delay and laches.
Source reference: para. 5, 62. Whether the subsequent order dated 15.06.2011 — vital to the controversy but never impugned at its issuance — could be challenged for the first time by way of a rejoinder affidavit.
Source reference: para. 63. Whether disputed questions of fact arising from contradictory attendance registers can be adjudicated within the scope of writ jurisdiction.
Source reference: para. 6Law Applied
The Court applied the doctrine of delay and laches governing the exercise of writ jurisdiction, under which belated petitions are liable to be dismissed even where substantive questions may exist, relying on WG CDR A.U. Tayyaba (Retired) & Ors. v. Union of India & Ors., (2023) 5 SCC 688, and Bichitrananda Behera v. State of Orissa & Ors., 2023 SCC OnLine SC 1307.
Source reference: para. 5, 7The Court also invoked the settled principle that a writ court cannot adjudicate serious disputed questions of fact requiring appreciation of evidence.
Source reference: para. 5, 6Procedural propriety requires that a substantive fresh order must be specifically impugned in the pleadings; a challenge raised only through a rejoinder affidavit is impermissible.
Source reference: para. 6Reasoning
The Court applied the doctrine of delay and laches as a threshold bar without entering into the merits. It noted that the impugned letter dated 20.04.2011 was issued more than 13 years before the filing of the petition.
Source reference: para. 6The subsequent order dated 15.06.2011 — which was vital to the issue since it had materially replaced the impugned letter — had never been challenged upon issuance and was sought to be assailed only via the rejoinder affidavit, which the Court held "clearly indicates severe laches on the part of the petitioners".
Source reference: para. 6Applying the principle against adjudication of disputed facts in writ jurisdiction, the Court observed that the attendance sheets were evidentiary in nature and, given their internal contradictions, made adjudication impossible in a writ proceeding.
Source reference: para. 6Consciously avoiding engagement with the substantive authorities cited by both sides, the Court concluded that the delay barred relief regardless of any larger questions that "may remain".
Source reference: para. 7Holding
The Court held that the writ petition could not be entertained as it was presented after a long and unexplained delay of over 13 years and because no proper challenge was made to the substantive order dated 15.06.2011, alongside the existence of disputed questions of fact.
Accordingly, the writ petition "stands dismissed and is accordingly disposed of" on the ground of delay and laches, without any adjudication on the merits of the wage deduction claim and without granting any relief to the petitioners.
Source reference: para. 7Original Court PDF
GEORGE CHARLESTONE BASAIAWMOIT AND 20 ORS.vsNORTH EASTERN HILL UNIVERSITY AND 5 ORS.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in