Patna High Court
Arbitration and MediationCivil Procedure and Evidence

₹16.64-crore arbitral award set aside after contractor raised ₹13.77-lakh claim to ₹14.58 crore post-hearing without evidence; Patna High Court finds patent illegality

The General Manager, East Central Railway, vs Praphull Infrastructure Pvt. Ltd. Sidharth Construction and Trading Pvt. Ltd. (J.V.),

Patna High CourtJUDGMENT: September 11, 20264 MIN READSOURCE JUDGMENT
₹16.64-crore arbitral award set aside after contractor raised ₹13.77-lakh claim to ₹14.58 crore post-hearing without evidence; Patna High Court finds patent illegality. The General Manager,  East Central Railway, vs Praphull Infrastructure Pvt. Ltd. Sidharth Construction and Trading Pvt. Ltd. (J.V.),. Patna High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

East Central Railway issued Tender Notice No. 28 of 2008–09 for earthwork, construction of minor bridges and allied works between Athmalgola and Barh.

Source reference: paras. 3

The respondent’s tender was accepted through a Letter of Acceptance dated 27 April 2009, for a total contract value of approximately Rs. 6.95 crore, with the work to be completed within twelve months.

Source reference: paras. 3, 53

The Railways alleged that the respondent neither furnished the required performance guarantee nor commenced the work adequately, despite repeated notices, and ultimately terminated the arrangement under Clause 62 of the General Conditions of Contract.

Source reference: paras. 4–6, 59

The dispute was referred to arbitration.

Source reference: para. 8

The sole arbitrator awarded Rs. 16,64,34,132 with 12% annual interest, besides arbitration and secretarial charges, in favour of the respondent on 18 March 2023.

Source reference: paras. 8, 25

The Railways’ application under Section 34 of the Arbitration and Conciliation Act, 1996 was dismissed by the Commercial Court on 20 February 2026.

Source reference: paras. 2, 33
02

Issues

Whether the arbitral award was liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 for violation of natural justice and the requirement of equal treatment, where the claimant substantially altered and enhanced its claims after conclusion of the hearing without giving the Railways an opportunity to respond?

Source reference: paras. 62–68, 74, 78–79

Whether the award was vitiated by patent illegality and perversity because substantial damages were awarded without supporting oral or documentary evidence and without adequate reasons under Section 31(3) of the Act of 1996?

Source reference: paras. 35–45, 66–74, 79

Whether the Commercial Court erred in refusing to interfere with the award by treating the Railways’ objections as an impermissible attempt to reappreciate evidence, without examining the alleged absence of evidence and procedural violations?

Source reference: paras. 75–78
03

Law Applied

The Court applied Sections 18 and 24(3) of the Arbitration and Conciliation Act, 1996, which require equal treatment of parties, a full opportunity to present one’s case, and communication of statements and documents relied upon by the tribunal.

Source reference: para. 70

Section 31(3) requires an arbitral award to state the reasons on which it is based, unless the parties have agreed otherwise.

Source reference: para. 69

Under Sections 34(2)(a)(iii), 34(2)(b) and 34(2A), an award may be set aside for denial of a fair opportunity, conflict with the fundamental policy of Indian law or public policy, and patent illegality appearing on the face of the award.

Source reference: paras. 70–71, 79

The Court relied on Som Datt Builders Ltd. v. State of Kerala, (2009) 10 SCC 259, for the mandatory requirement of reasons; Ssangyong Engineering & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131, for natural justice and fair opportunity under Section 34; Associate Builders v. DDA, (2015) 3 SCC 49, for perversity and fundamental policy; and Unibros v. All India Radio, 2023 SCC OnLine SC 1366, for the principle that damages and loss of profit cannot be awarded without credible evidence of actual loss.

Source reference: paras. 69–72

The Court also applied Section 73 of the Indian Contract Act, 1872, which requires proof of loss before damages can be granted.

Source reference: para. 39
04

Reasoning

The High Court found that the arbitrator relied on an enhanced and newly particularised claim annexed to the claimant’s written submissions after the arbitral hearing had concluded.

Source reference: paras. 62–68, 78

The Railways were neither served with the revised claim nor given an opportunity to rebut it, contrary to Sections 18 and 24(3) of the Act.

Source reference: paras. 62–68, 78

The increase of the machinery-hire claim from Rs. 13,77,000 to Rs. 14,58,00,000 was not a mere clarification but a material enlargement of the claim without amendment of pleadings.

Source reference: para. 78

Further, the claimant produced no invoices, hiring agreements, payment records, wage records, or other evidence to establish that the machinery, labour and alleged expenses had actually been incurred.

Source reference: paras. 66–68

The arbitrator nevertheless awarded Rs. 14,58,00,000 under that head and granted substantial damages without explaining the evidentiary or contractual basis for the calculation.

Source reference: para. 67

Such findings were unsupported by evidence, ignored material aspects of the record, and were therefore perverse and patently illegal under Section 34(2A).

Source reference: paras. 72–74, 79

The Commercial Court failed to examine these specific objections and incorrectly treated them as an attempt to invite a merits review.

Source reference: paras. 75–77
05

Holding

The High Court held that the arbitral award violated the principles of natural justice and equal treatment, was based on claims introduced after the hearing without notice, and awarded substantial damages without supporting evidence or adequate reasons.

The award consequently suffered from perversity, legal infirmity and patent illegality on its face.

Source reference: paras. 74, 79

The Court set aside the Commercial Court’s order dated 20 February 2026, allowed the Railways’ Section 34 application in Miscellaneous (Arbitration) Case No. 66 of 2023, and set aside the arbitral award dated 18 March 2023 in its entirety.

Source reference: para. 80

The commercial appeal was accordingly allowed.

Source reference: para. 81
06

Acts & Sections Cited

14 provisions across 3 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 199611 provisions

Indian Contract Act, 18721

India International Arbitration Centre Act, 20192

Patna High Court

Original Court PDF

The General Manager, East Central Railway,vsPraphull Infrastructure Pvt. Ltd. Sidharth Construction and Trading Pvt. Ltd. (J.V.),

Patna High Court · September 11, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment