Facts
SAIL contracted with Primetals for installation of a power supply facility at Bhilai Steel Plant.
Source reference: paras. 2.1–2.5; pp. 2–4Article 2.1 stated that a minimum of ₹2,16,42,894 was to be passed on to SAIL as CENVAT credit.
Source reference: paras. 2.1–2.5; pp. 2–4During performance, changes in duty rates meant that Primetals paid and recovered only ₹1,08,81,516 in duty, and passed on CENVAT credit for that amount.
Source reference: paras. 2.1–2.5; pp. 2–4SAIL later deducted the alleged shortfall of ₹1,07,61,378 from Primetals’ invoices.
Source reference: paras. 2.1–2.5; pp. 2–4The arbitral tribunal upheld the deduction, treating the minimum credit as an assured contractual benefit.
Source reference: paras. 2.1–2.5; pp. 2–4The Single Judge set aside the award under Section 34, finding no contractual provision authorising recovery of the alleged shortfall from the invoices.
Source reference: paras. 2.1–2.5; pp. 2–4SAIL appealed under Section 37.
Source reference: paras. 2.7–2.9; pp. 2–4Issues
Whether the arbitral award’s interpretation of Article 2.1 and the GCC, permitting SAIL to deduct the alleged CENVAT-credit shortfall from Primetals’ invoices, was a plausible interpretation or an illegality going to the root of the award
Source reference: paras. 7.2–8.3, 14–23; pp. 11–15, 18–21Whether the Single Judge correctly applied the patent-illegality standard under Section 34, such that the order setting aside the award should be upheld in the Section 37 appeal
Source reference: paras. 9–13; pp. 15–18Whether differing arbitral interpretations of materially identical contractual clauses between the same parties supported applying a consistent interpretation in this appeal
Source reference: paras. 24–28; pp. 21–23Law Applied
Under Section 34(2A) of the Arbitration and Conciliation Act, 1996, a domestic arbitral award may be set aside for patent illegality where the illegality goes to its root, including where the award travels beyond the contract or is contrary to its terms; mere legal error or a different plausible interpretation is insufficient.
Source reference: paras. 9–13; pp. 15–18Section 37 provides a limited appeal, with review no broader than the restrictions under Section 34, but permits examination of whether the Single Judge correctly applied that standard.
Source reference: paras. 9–13; pp. 15–18The Court relied on Ramesh Kumar Jain v. Bharat Aluminium Company Limited, 2025 SCC OnLine SC 2857, on the limits of patent-illegality review, and National Highway Authority of India v. Progressive-MVR (JV), (2018) 14 SCC 688, on avoiding inconsistent outcomes where arbitral tribunals have interpreted the same contractual clause differently in pending proceedings.
Source reference: paras. 10, 13, 25–26; pp. 16–18, 22–23Reasoning
The Court held that Article 2.1 required the passing on of CENVAT credit, but did not authorise SAIL to recover a shortfall by deducting it from invoices.
Source reference: paras. 21–23; pp. 20–21Read with Clause 14.5.2, the contractual scheme linked credit to duty actually paid and supporting documents; the contract provided for non-reimbursement where the required documents were not furnished, not for a separate deduction in the circumstances here.
Source reference: paras. 21–23; pp. 20–21Because the duty rate had fallen, SAIL reimbursed less duty and received credit corresponding to that lower amount; it had not paid the alleged shortfall and was not out of pocket for it.
Source reference: paras. 16–20; pp. 18–20The asserted “shortfall” therefore did not establish an amount recoverable from Primetals under Article 2.1.
Source reference: paras. 16–20; pp. 18–20The tribunal’s deduction lacked contractual support and was not even a plausible interpretation of the relevant terms, making the award patently illegal.
Source reference: paras. 21–28; pp. 20–23The Court also considered the interpretation adopted in the related proceeding involving the same parties and materially identical clauses, and declined to sustain contrary outcomes.
Source reference: paras. 21–28; pp. 20–23Holding
The Court answered the principal issues against SAIL.
It held that the contract did not permit deduction of the alleged CENVAT-credit shortfall from Primetals’ invoices and that the Single Judge rightly set aside the award for patent illegality.
Source reference: paras. 23, 29–30; p. 24The appeal was dismissed, the impugned judgment was upheld, and pending applications were disposed of.
Source reference: paras. 23, 29–30; p. 24Acts & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19962
Original Court PDF
Steel Authority Of India Limited (Sail)vsM/S Primetals Technologies India Pvt. Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
