Facts
BSR entered into a construction agreement with the State Project Director (SPD) for Package A-20 of the RMSA works.
Source reference: para. 5–8, 33–35The agreement included a price-adjustment clause, and the arbitral tribunal found that the clause formed part of the contract, notwithstanding a tender-document note stating that it would be treated as deleted.
Source reference: para. 5–8, 33–35BSR claimed ₹4,53,24,186 towards price adjustment, but the tribunal rejected the claim for want of evidence establishing the calculation and amount due.
Source reference: para. 16, 21–22It partly allowed other claims and awarded BSR ₹1,66,24,597, interest and costs.
Source reference: para. 16, 21–22The Commercial Court dismissed BSR’s petition under Section 34 of the Arbitration and Conciliation Act, 1996.
Source reference: para. 23–25In this appeal under Section 37, BSR challenged only the rejection of its price-adjustment claim.
Source reference: para. 23–25Issues
1. Whether the arbitral tribunal was justified in rejecting BSR’s price-adjustment claim because BSR failed to establish the amount claimed.
Source reference: para. 24, 35–392. Whether the Commercial Court’s refusal to set aside that part of the award warranted appellate interference under Section 37 of the Arbitration and Conciliation Act, 1996.
Source reference: para. 23–24, 40Law Applied
Section 34 of the Arbitration and Conciliation Act, 1996 provides the basis for an application to set aside an arbitral award, while Section 37(1)(c) provides for an appeal from an order refusing to set aside an award.
Source reference: para. 1, 23Under Clause 40.1 of the contract, price adjustment was to be calculated using the prescribed formulae in the Contract Data for the relevant components; a claimant seeking payment under that clause must establish both entitlement and the measure of the amount claimed.
Source reference: para. 29–32, 38–39Reasoning
Although the tribunal accepted that the price-adjustment clause formed part of the contract, that finding did not establish the amount payable.
Source reference: para. 33–36The Contract Data required component-specific calculations, but BSR produced no calculation sheet or supporting documents demonstrating the relevant variables or the application of the formulae.
Source reference: para. 33–36The claim was also inadequately particularised, and the amounts stated in the claim, an exhibit, and later written submissions differed without explanation; BSR did not produce the bills it said it had submitted.
Source reference: para. 28, 36–39As BSR bore the burden of proving the measure of its claim, the tribunal’s rejection was not a ground for setting aside the award, and the Commercial Court had properly declined to interfere.
Source reference: para. 38–40Holding
The Court held that BSR had failed to establish the amount due under its price-adjustment claim and found no basis to interfere with the arbitral award or the Commercial Court’s decision.
The appeal was dismissed.
Source reference: para. 41Acts & Sections Cited
6 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Commercial Courts Act, 20151
Arbitration and Conciliation Act, 19965
Original Court PDF
M/S BSR INFRATECH INDIA LTDvsSTATE PROJECT DIRECTOR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
