Karnataka High Court

A jurisdiction or governing-law clause does not constitute an arbitration agreement.

M/S MANGALA CASHEW INDUSTRIES vs CONNECT INDIA TANZANIA CO LTD

Karnataka High CourtJUDGMENT: October 05, 20262 MIN READSOURCE JUDGMENT
A jurisdiction or governing-law clause does not constitute an arbitration agreement.. M/S MANGALA CASHEW INDUSTRIES vs CONNECT INDIA TANZANIA CO LTD. Karnataka High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner challenged the Commercial Court’s order referring Com.O.S. No. 1/2022 to arbitration, directing return of the plaint and refund of the court fee.

Source reference: p. 3–4, p. 10–11

It contended that the parties’ contracts dated 17 and 24 January 2017 contained no arbitration agreement and that the respondents had not produced the original agreement or a duly certified copy when seeking reference under Section 8 of the Arbitration and Conciliation Act, 1996 (“A&C Act”).

Source reference: p. 3–4, p. 10–11

The respondents relied on clauses in both contracts as arbitration clauses, while acknowledging that the originals had not been filed.

Source reference: p. 4
02

Issues

1. Whether the clauses in the contracts dated 17 and 24 January 2017 constituted an arbitration agreement between the parties.

Source reference: p. 5–9

2. Whether the Commercial Court could entertain the Section 8 application without the original arbitration agreement or a duly certified copy.

Source reference: p. 10–11
03

Law Applied

Section 7 of the A&C Act defines an arbitration agreement as an agreement to submit disputes arising from a defined legal relationship to arbitration; it may be a clause in a contract or a separate agreement, must be in writing, and may be evidenced in the ways set out in subsections (3)–(5).

Source reference: p. 7–8

Under Section 8(1), a judicial authority must refer the parties to arbitration where a timely application is made in a matter covered by an arbitration agreement, unless it finds prima facie that no valid arbitration agreement exists.

Source reference: p. 9–10

Section 8(2) requires the application to be accompanied by the original arbitration agreement or a duly certified copy, subject to the statutory proviso where the agreement is retained by the other party.

Source reference: p. 9–10
04

Reasoning

The Court found that the 17 January contract’s reference to amicable settlement and “Mangalore court jurisdiction only” was, at most, a jurisdiction clause; it did not provide for arbitration.

Source reference: p. 5–9

The 24 January contract’s statement that it was governed and construed under existing UAE law addressed governing law, not arbitration.

Source reference: p. 5–9

Neither document therefore established an arbitration agreement under Section 7.

Source reference: p. 5–9

Further, the original agreement was not produced before the Commercial Court, and the record did not satisfy Section 8(2)’s requirement.

Source reference: p. 10–11

The Commercial Court had therefore erred in referring the suit to arbitration.

Source reference: p. 10–11
05

Holding

The Court held that no arbitration agreement existed between the parties and that the Section 8 application could not, in any event, be allowed without compliance with Section 8(2).

It allowed the writ petition and set aside the Commercial Court’s order dated 1 April 2023; pending applications, if any, were closed.

Source reference: p. 12
06

Acts & Sections Cited

2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19962

Karnataka High Court

Original Court PDF

M/S MANGALA CASHEW INDUSTRIESvsCONNECT INDIA TANZANIA CO LTD

Karnataka High Court · October 05, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment