Bombay High Court
Arbitration and MediationCommercial and Corporate Law

A non-signatory cannot be referred to arbitration without prima facie evidence of consent.

New Consolidated Construction Company Limited vs Limitless Contracting Pvt Ltd

Bombay High CourtJUDGMENT: September 29, 20263 MIN READSOURCE JUDGMENT
A non-signatory cannot be referred to arbitration without prima facie evidence of consent.. New Consolidated Construction Company Limited vs Limitless Contracting Pvt Ltd. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

Respondent No. 1 appointed the Applicant as a subcontractor under four Work Orders dated 25 September 2017 for construction work at the “One Park Avenue” project; an Addendum followed on 17 February 2020.

Source reference: paras. 2–12

The Applicant claimed outstanding payments and invoked arbitration under Clause 17 of the Work Orders.

Source reference: paras. 2–12

Respondent No. 1 did not oppose reference, while Respondent No. 2 denied being a party to the arbitration agreement and Respondent No. 3 denied involvement in the relevant transaction.

Source reference: paras. 2–12

The Applicant sought reference against all three Respondents.

Source reference: paras. 2–12
02

Issues

Whether Respondent No. 2, a non-signatory with a corporate and commercial connection to Respondent No. 1 and the project, was prima facie a party to the arbitration agreement.

Source reference: paras. 13, 15–21

Whether Respondent No. 3 could be referred to arbitration based on its alleged connection with the project and the subsequent property transaction.

Source reference: paras. 13, 32–38

Whether the disputes between the Applicant and Respondent No. 1 were referable to arbitration under the Work Orders.

Source reference: paras. 42–45
03

Law Applied

Section 11 of the Arbitration and Conciliation Act, 1996 empowers the Court to appoint an arbitrator where an arbitration agreement exists and a dispute is referable to it.

Source reference: no citation

Under Cox and Kings Ltd. v. SAP India (P) Ltd., (2024) 4 SCC 1, a non-signatory may be bound where consent to arbitrate is established; commercial connection or common ownership alone is insufficient, and consent may be inferred from conduct and the parties’ relationship.

Source reference: paras. 15–20

Hindustan Petroleum Corporation Ltd. v. BCL Secure Premises (P) Ltd., (2026) 3 SCC 711, requires the Referral Court to be prima facie satisfied that a non-signatory is a “veritable party” before referring it to arbitration; the issue cannot automatically be left to the tribunal.

Source reference: paras. 22, 38–40

Mukesh Patel v. Pant Nagar Ganesh Krupa Cooperative Housing Society Ltd., 2025 SCC OnLine Bom 6393, emphasises de facto privity and the foundational requirement of consent to arbitrate.

Source reference: paras. 24–28, 37

A person claiming “through or under” a signatory must have a derivative basis, such as assignment, subrogation or novation; mere legal or commercial connection is insufficient.

Source reference: para. 35
04

Reasoning

Respondent No. 1 and the Applicant were the parties to the Work Orders and Addendum, and the Applicant raised its bills and payment demand against Respondent No. 1.

Source reference: paras. 14, 17

Although Respondent No. 2 participated in project discussions and communications and was connected to Respondent No. 1, the record did not show that it assumed Respondent No. 1’s obligations or consented to Clause 17; those circumstances established project involvement, not consent to arbitrate.

Source reference: paras. 15–19, 29–30

Respondent No. 3 was not shown to have acquired the property: the Sale Certificates named Purva Oak Private Limited as purchaser, and no assignment, novation or succession binding Respondent No. 3 to the arbitration agreement was established.

Source reference: paras. 33–36, 41

The Court therefore found no prima facie basis to refer Respondent Nos. 2 or 3 to arbitration, while the arbitration agreement and dispute between the Applicant and Respondent No. 1 were established.

Source reference: paras. 42–44
05

Holding

The Court allowed the application to proceed against Respondent No. 1 and appointed Mr. Tushad Kakalia as sole arbitrator to adjudicate disputes arising out of and in connection with Clause 17 of the Work Orders dated 25 September 2017.

It declined to refer Respondent Nos. 2 and 3 to arbitration, without deciding whether the Applicant might have an independent remedy against either of them.

Source reference: paras. 44–46

The arbitrator may determine the merits, claims and any counterclaims.

Source reference: para. 47
06

Acts & Sections Cited

4 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19964

Bombay High Court

Original Court PDF

New Consolidated Construction Company LimitedvsLimitless Contracting Pvt Ltd

Bombay High Court · September 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment