Facts
BSR was awarded a construction package by the State Project Director (SPD).
Source reference: no citationThe contract included a price-adjustment clause, which the Arbitral Tribunal found had formed part of the executed agreement despite a tender-document notation stating that the clause would be treated as deleted.
Source reference: para. 33–35BSR claimed ₹4,53,24,186 in price adjustment but did not set out in its statement of claims how that amount was calculated or produce supporting bills and evidence applying the contractual formulae.
Source reference: para. 28, 31, 36–37The Tribunal rejected the claim for want of proof. BSR’s Section 34 challenge was dismissed by the Commercial Court, and BSR appealed under Section 13(1A) of the Commercial Courts Act, 2015, read with Section 37 of the Arbitration and Conciliation Act, 1996. In the appeal, BSR confined its challenge to rejection of the price-adjustment claim.
Source reference: para. 1, 23–24Issues
Whether the arbitral award’s rejection of BSR’s price-adjustment claim warranted appellate interference, given BSR’s failure to establish the amount claimed.
Source reference: para. 24, 38–40Whether BSR’s assertion that the SPD did not dispute the quantum relieved BSR of the burden to prove the measure of its claim.
Source reference: para. 25, 32, 38–39Law Applied
The appeal was brought under Section 13(1A) of the Commercial Courts Act, 2015, read with Section 37 of the Arbitration and Conciliation Act, 1996; BSR’s underlying challenge was under Section 34 of the latter Act.
Source reference: para. 1Under Clause 40 of the contract, price adjustment was to be calculated using the prescribed formulae in the Contract Data for the relevant components.
Source reference: para. 29–30A claimant seeking contractual payment must establish both its entitlement and the amount claimed; the burden to prove the claim’s measure rests on the claimant.
Source reference: para. 32, 38–39Reasoning
Although the Tribunal accepted that the price-adjustment clause formed part of the contract, that finding did not establish the amount payable under it.
Source reference: para. 34–35BSR provided no calculation showing the relevant variables or supporting documents, and the amounts stated in its claim, spreadsheet and later submission were inconsistent and unexplained.
Source reference: para. 31, 36–37The SPD had denied the claim, so BSR remained responsible for proving both its entitlement and its quantum; the alleged absence of a specific dispute over quantum did not overcome the evidentiary deficiencies.
Source reference: para. 32, 38–39The High Court therefore found no ground to interfere with the Tribunal’s rejection of the claim.
Source reference: para. 40Holding
The Court answered the issues against BSR. It held that BSR had failed to prove the measure of its price-adjustment claim and that the Commercial Court had correctly declined to set aside the award on that ground.
The appeal was dismissed as unmerited.
Source reference: para. 41Acts & Sections Cited
5 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Commercial Courts Act, 20151
Arbitration and Conciliation Act, 19964
Original Court PDF
M/S BSR INFRATECH INDIA LTDvsSTATE PROJECT DIRECTOR
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
