Delhi High Court

Absence of Proof of Execution of Main Agreement Negates Existence of Incorporated or Independent Arbitration Clause

Galaxy Infra and Engineering Pvt. Ltd. v. Pravin Electricals Pvt. Ltd. [O.M.P. (COMM) 463/2023]

Delhi High Court2 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner, a consultancy firm, claimed it entered into a Consultancy Agreement (CA) dated 07.07.2014 with the Respondent to provide services for a power distribution tender in Bihar.

Source reference: p. 1-2

Following a dispute over an unpaid invoice dated 01.07.2017, the Petitioner invoked arbitration under Section 21 of the Arbitration and Conciliation Act, 1996.

Source reference: p. 2

The Supreme Court, in a prior appeal, set aside a High Court finding that a contract concludedly existed, instead directing the Sole Arbitrator to decide as a preliminary issue whether an arbitration agreement existed between the parties.

Source reference: p. 3

The Arbitrator subsequently issued an award on 07.08.2023, finding that the CA was not executed, signatures were forged, and no independent agreement was formed through subsequent correspondence.

Source reference: p. 4

The Petitioner challenged this award under Section 34 of the Act.

Source reference: no citation
02

Issues

1. Whether the Arbitrator erred in finding that the Consultancy Agreement (CA) dated 07.07.2014 was not executed and that the signatures were forged.

Source reference: p. 6, para 8

2. Whether an independent arbitration agreement was concluded through correspondence exchanged between the parties subsequent to 07.07.2014.

Source reference: p. 6, para 7; p. 8, para 13

3. Whether the arbitral award suffered from patent illegality or perversity warranting interference under Section 34 of the Act.

Source reference: p. 11, para 23-24
03

Law Applied

The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, which limits judicial interference to grounds of patent illegality, contravention of fundamental policy of Indian law, or basic notions of justice.

Source reference: p. 11-12

It relied on *Vidya Drolia v. Durga Trading Corpn.* regarding the "prima facie" review of arbitration agreements.

Source reference: p. 3

It relied on *Ramesh Kumar Jain v. BALCO* (2025) and *Consolidated Construction Consortium Ltd. v. STPI* (2025) to affirm that Section 34 is not an appellate provision and courts cannot re-appreciate evidence or correct mere factual/legal errors unless they are perverse.

Source reference: p. 11-13
04

Reasoning

The Court observed that the Petitioner failed to discharge the initial onus of proving the CA's execution.

Source reference: p. 7

Several factors supported the Arbitrator’s finding of forgery and non-execution: the agreement was notarized in Faridabad despite neither party having a presence there; the notary’s license had expired; and witnesses were not examined.

Source reference: p. 6-7

Furthermore, an email dated 15.07.2014 (after the alleged execution date) showed the parties were still exchanging drafts, proving no concluded contract existed on 07.07.2014.

Source reference: p. 7, 10

Regarding the alternative plea of an "agreement by correspondence," the Court held it was inconsistent with the primary plea of a signed CA.

Source reference: p. 8

Even on merits, the correspondence showed ongoing negotiations rather than a *consensus ad idem*, as the Petitioner had rejected financial terms in subsequent emails.

Source reference: p. 10

The Court found the Arbitrator’s reasoning plausible and held that a "roving inquiry" to find jurisdiction is not permissible once the foundation of the referral (the CA) is found to be non-existent.

Source reference: p. 11
05

Holding

The High Court dismissed the petition, holding that the Arbitrator’s findings were well-reasoned and not vitiated by patent illegality or perversity.

The Court affirmed that it cannot sit in appeal or re-evaluate evidence under Section 34.

Source reference: p. 12

The final holding is that no arbitration agreement existed between the parties, and the award dated 07.08.2023 is upheld.

Source reference: p. 13
Delhi High Court

Original Court PDF

Galaxy Infra and Engineering Pvt. Ltd. v. Pravin Electricals Pvt. Ltd. [O.M.P. (COMM) 463/2023]

Delhi High Court

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment