Calcutta High CourtContract LawCivil Law

### Absence of Specific Forfeiture Clause Precludes Retention of Advance Consideration Despite Breach of Contract

SRI NIRMAL KANODIA & ORS.v.UMADEVI AGARWALLA & ANR.

### Absence of Specific Forfeiture Clause Precludes Retention of Advance Consideration Despite Breach of Contract. SRI NIRMAL KANODIA & ORS. vs UMADEVI AGARWALLA & ANR.. Calcutta High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the MOU dated September 20, 2010, was legal, valid, and binding upon the parties.

The court held

The court held that the Kanodias committed a breach of contract but the Agarwallas could not forfeit the advance payment without a specific clause.

It also directed

CS 124/2011: Decreed in favor of the Agarwallas for ₹5.51 crores as damages with 7% interest; CS 264/2012: Decreed in favor of the Kanodias for the refund of ₹1 crore with 7% interest; The Agarwallas were granted liberty to set off the ₹1 crore (plus interest) from the ₹5.51 crore (plus interest) award before execution.

01Facts

The Agarwallas (Plaintiffs in CS/124) owned M/s Bhoomi Minerals, which had a sponge iron unit and significant debt with Indian Overseas Bank (IOB)

p. 2

They entered into a Memorandum of Understanding (MOU) on 20/09/2010 with the Kanodias (Plaintiffs in CS/264) to transfer the company for ₹28.01 crores

p. 3

The Kanodias paid ₹1 crore as advance/earnest money

p. 5

Subsequently, the Agarwallas proposed an amended MOU modifying share transfer security clauses, which the Kanodias refused

p. 7

On 24/09/2010, the Kanodias terminated the contract via SMS, claiming anticipatory breach and suppression of the fact that the unit was mortgaged to the bank

pp. 8-9

The Agarwallas eventually sold the unit to a third party for ₹22.5 crores and sued for the loss of ₹5.51 crores

pp. 5-6

The Kanodias sued for the refund of the ₹1 crore advance

p. 12

02Issues

i.1. Whether the MOU dated September 20, 2010, was legal, valid, and binding upon the parties.

p. 18

ii.2. Whether the Agarwallas committed an anticipatory breach of contract by proposing amendments to the MOU.

p. 24

iii.3. Whether the Agarwallas are entitled to damages and the forfeiture of the ₹1 crore earnest money in the absence of an explicit forfeiture clause.

p. 20, 28

03Law Applied

Section 39 of the Indian Contract Act, 1872, regarding the refusal of a party to perform a promise in its entirety (anticipatory breach)

p. 24

Manindra Chandra Nandy v. Aswini Kumar Acharjya, establishing that anticipatory breach requires an unqualified refusal that destroys the contract's root

p. 19, 25

Section 73, following the principle in Maharashtra State Electricity Distribution Co. Ltd. v. Datar Switchgear Ltd., to place the injured party in the position they would have been in had the contract been performed

p. 27

Section 74 and principles from Fateh Chand v. Balkishan Dass and Satish Batra v. Sudhir Rawal, holding that earnest money cannot be forfeited without an express contractual clause

pp. 28-29

Provisions in the judgment · 5 · Linked ones open on LawLens

Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 Section 13

Indian Contract Act, 1872 Section 54Section 39Section 74

Interest Act, 1978 Section 3

04Reasoning

The court found the original MOU valid, noting that the Kanodias were aware of the bank liabilities and mortgages through due diligence

pp. 21-23

On the issue of anticipatory breach, the court held that the Agarwallas' proposed amendments did not constitute a "refusal to perform in entirety" under Section 39; they merely proposed a novation which, when rejected, left the original MOU subsisting

p. 26

Consequently, the Kanodias' sudden termination on 24/09/2010 constituted a breach of contract

p. 27

Regarding damages, the court accepted the Agarwallas' loss of ₹5.51 crores (the difference between the MOU price and the third-party sale price) as the Kanodias failed to rebut the evidence of loss

pp. 27-28

Regarding the ₹1 crore advance, the court observed that the MOU lacked a specific forfeiture clause. Under Supreme Court precedent, earnest money or part-payments cannot be forfeited as a penalty unless the contract explicitly provides for it

p. 29

05Holding

The court held that the Kanodias committed a breach of contract but the Agarwallas could not forfeit the advance payment without a specific clause.

CS 124/2011: Decreed in favor of the Agarwallas for ₹5.51 crores as damages with 7% interest; CS 264/2012: Decreed in favor of the Kanodias for the refund of ₹1 crore with 7% interest; The Agarwallas were granted liberty to set off the ₹1 crore (plus interest) from the ₹5.51 crore (plus interest) award before execution.

p. 30
Calcutta High Court

Original Court PDF

SRI NIRMAL KANODIA & ORS.vsUMADEVI AGARWALLA & ANR.

Calcutta High Court · May 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment