Calcutta High Court

### Absence of Specific Forfeiture Clause Precludes Retention of Advance Consideration Despite Breach of Contract

SRI NIRMAL KANODIA & ORS. vs UMADEVI AGARWALLA & ANR.

Calcutta High CourtJUDGMENT: May 12, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Agarwallas (Plaintiffs in CS/124) owned M/s Bhoomi Minerals, which had a sponge iron unit and significant debt with Indian Overseas Bank (IOB)

Source reference: p. 2

They entered into a Memorandum of Understanding (MOU) on 20/09/2010 with the Kanodias (Plaintiffs in CS/264) to transfer the company for ₹28.01 crores

Source reference: p. 3

The Kanodias paid ₹1 crore as advance/earnest money

Source reference: p. 5

Subsequently, the Agarwallas proposed an amended MOU modifying share transfer security clauses, which the Kanodias refused

Source reference: p. 7

On 24/09/2010, the Kanodias terminated the contract via SMS, claiming anticipatory breach and suppression of the fact that the unit was mortgaged to the bank

Source reference: p. 8-9

The Agarwallas eventually sold the unit to a third party for ₹22.5 crores and sued for the loss of ₹5.51 crores

Source reference: p. 5-6

The Kanodias sued for the refund of the ₹1 crore advance

Source reference: p. 12
02

Issues

1. Whether the MOU dated September 20, 2010, was legal, valid, and binding upon the parties.

Source reference: p. 18

2. Whether the Agarwallas committed an anticipatory breach of contract by proposing amendments to the MOU.

Source reference: p. 24

3. Whether the Agarwallas are entitled to damages and the forfeiture of the ₹1 crore earnest money in the absence of an explicit forfeiture clause.

Source reference: p. 20, 28
03

Law Applied

Section 39 of the Indian Contract Act, 1872, regarding the refusal of a party to perform a promise in its entirety (anticipatory breach)

Source reference: p. 24

Manindra Chandra Nandy v. Aswini Kumar Acharjya, establishing that anticipatory breach requires an unqualified refusal that destroys the contract's root

Source reference: p. 19, 25

Section 73, following the principle in Maharashtra State Electricity Distribution Co. Ltd. v. Datar Switchgear Ltd., to place the injured party in the position they would have been in had the contract been performed

Source reference: p. 27

Section 74 and principles from Fateh Chand v. Balkishan Dass and Satish Batra v. Sudhir Rawal, holding that earnest money cannot be forfeited without an express contractual clause

Source reference: p. 28-29
04

Reasoning

The court found the original MOU valid, noting that the Kanodias were aware of the bank liabilities and mortgages through due diligence

Source reference: p. 21-23

On the issue of anticipatory breach, the court held that the Agarwallas' proposed amendments did not constitute a "refusal to perform in entirety" under Section 39; they merely proposed a novation which, when rejected, left the original MOU subsisting

Source reference: p. 26

Consequently, the Kanodias' sudden termination on 24/09/2010 constituted a breach of contract

Source reference: p. 27

Regarding damages, the court accepted the Agarwallas' loss of ₹5.51 crores (the difference between the MOU price and the third-party sale price) as the Kanodias failed to rebut the evidence of loss

Source reference: p. 27-28

Regarding the ₹1 crore advance, the court observed that the MOU lacked a specific forfeiture clause. Under Supreme Court precedent, earnest money or part-payments cannot be forfeited as a penalty unless the contract explicitly provides for it

Source reference: p. 29
05

Holding

The court held that the Kanodias committed a breach of contract but the Agarwallas could not forfeit the advance payment without a specific clause.

CS 124/2011: Decreed in favor of the Agarwallas for ₹5.51 crores as damages with 7% interest; CS 264/2012: Decreed in favor of the Kanodias for the refund of ₹1 crore with 7% interest; The Agarwallas were granted liberty to set off the ₹1 crore (plus interest) from the ₹5.51 crore (plus interest) award before execution.

Source reference: p. 30
Calcutta High Court

Original Court PDF

SRI NIRMAL KANODIA & ORS.vsUMADEVI AGARWALLA & ANR.

Calcutta High Court · May 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment