Facts
The petitioner, a registered contractor with the Water Resources Department, Assam, was awarded work under the scheme for protection of the Brahmaputra dyke from erosion in the Dikhowmukh–Mukaloni/Rupahimukh area.
Source reference: p.3, para. 3After completing the work in 2016, he submitted a bill for ₹10,87,131. The authorities paid ₹9,62,584, leaving a balance of ₹1,24,547, which remained unpaid despite repeated requests.
Source reference: p.3, para. 3In its affidavit, the Water Resources Department admitted the total bill, the amount already paid, and the outstanding balance, but stated that payment could not be made owing to non-receipt of the Central Government’s share.
Source reference: pp.4–5, para. 5The Central Government, however, submitted that no Central share remained outstanding under the relevant scheme code.
Source reference: p.5, para. 6Issues
Whether the petitioner was entitled to payment of the admitted outstanding contractual amount of ₹1,24,547.
Source reference: pp.4–5, para. 5; p.5, para. 7Whether the High Court could direct the Water Resources Department to release the admitted dues despite the department’s contention that the Central funds had not been received.
Source reference: p.5, paras. 6–7Law Applied
The Court applied the principle that a public authority must honour and discharge an admitted financial liability arising from completed government contract work, and that the High Court may issue an appropriate direction in writ jurisdiction where the liability is undisputed and non-payment is arbitrary or unjustified.
Source reference: p.5, para. 7No specific statutory provision or judicial precedent was cited; the decision was based principally on the Department’s clear admission of the outstanding amount and the obligation of the concerned authority to make payment.
Source reference: no citationReasoning
The Water Resources Department expressly admitted that the petitioner’s total bill was ₹10,87,131, that ₹9,62,584 had been paid, and that ₹1,24,547 remained due.
Source reference: pp.4–5, para. 5Although the Department attributed the non-payment to non-receipt of the Central share, the Central Government asserted that the entire Central and State funding under the relevant scheme had already been released.
Source reference: p.5, para. 6The Court therefore treated the petitioner’s entitlement as established and held that an internal funding dispute could not justify withholding an admitted amount payable for work already completed.
Source reference: p.5, para. 7Accordingly, responsibility for payment was placed on the Water Resources Department, through its Chief Engineer.
Source reference: p.5, para. 7; p.6, para. 8Holding
The Court held that the petitioner was entitled to the admitted balance of ₹1,24,547.
It directed the Chief Engineer, Water Resources Department, Assam, to pay the amount after deducting applicable taxes within six months from service of a certified copy of the order.
Source reference: p.6, paras. 8–9The writ petition was consequently disposed of.
Source reference: p.6, para. 10Original Court PDF
Jibon SarmahvsUnion Of India And 6 Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
