01Facts
The Petitioner-Society undertook redevelopment of its building after the requisite society resolutions and executed a registered Development Agreement with a developer.
pp. 2–5 · ¶ 2–5Seventeen of its eighteen members vacated their flats, but the Respondent, the legal representative of a member associated with Flat No. 3, did not.
pp. 2–5 · ¶ 2–5The Society sought a mandatory temporary injunction directing her to vacate.
pp. 2–5 · ¶ 2–5The Co-operative Court rejected that application, and the Co-operative Appellate Court dismissed the Society’s appeal, although it recognised that such interim relief could be granted.
pp. 2–5 · ¶ 2–5The Society then challenged both orders by writ petition.
pp. 2–5 · ¶ 2–5The High Court noted that the building was ready for demolition, redevelopment had commenced, and the Respondent had not appeared in the proceedings; the flat was found locked.
pp. 4, 13–14 · ¶ 6, 2102Issues
i.1. Whether the Society had established grounds for a mandatory temporary injunction directing the Respondent to vacate and hand over Flat No. 3 for redevelopment.
pp. 6–8, 11–12 · ¶ 10–12, 16–17ii.2. Whether the Co-operative Courts erred in refusing that relief, including by requiring the Society to make a fresh application before the Trial Court.
pp. 12–13 · ¶ 18–2003Law Applied
Under Dorab Cawasji Warden v. Coomi Sorab Warden, an interlocutory mandatory injunction ordinarily requires a strong prima facie case—applying a higher standard than that for a prohibitory injunction—likely irreparable or serious injury, and a balance of convenience favouring relief; the court must also consider whether withholding relief risks greater injustice than granting it.
p. 6 · ¶ 11The Court relied on Pranav Constructions v. Priyadarshani CHSL and Lakhani Realty LLP v. Kalina Darshan CHSL for the propositions that members are bound by the society’s redevelopment obligations and that interim directions to vacate may be appropriate to prevent redevelopment from being frustrated.
pp. 8–10 · ¶ 13–14The judgment further held that, in redevelopment cases involving a dissenting flat occupier, the majority’s redevelopment decision and the resulting risk to the project may establish a strong prima facie case for interim mandatory relief.
p. 11 · ¶ 16Provisions in the judgment · 1 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9
04Reasoning
The High Court found that the Trial Court had wrongly treated the relief as impermissible merely because it resembled final relief, and had misapplied Dorab Cawasji Warden.
pp. 6–7 · ¶ 10–12Seventeen members had vacated, the developer had commenced the redevelopment process and was paying transit rent, while the Respondent’s continued occupation could prevent demolition and prejudice the other members.
p. 5, 11, 14 · ¶ 7, 15–16, 21The Appellate Court accepted that mandatory interim relief was legally available but nevertheless declined to grant it and directed the Society to apply afresh, despite evidence that the date for vacating had passed.
pp. 12–13 · ¶ 18–20The High Court held that this approach unnecessarily prolonged litigation and failed to protect the redevelopment project.
pp. 12–13 · ¶ 18–2005Holding
The High Court allowed the writ petition and set aside both Co-operative Court orders.
pp. 14–15 · ¶ 23–24It allowed the Society’s application at Exhibit 5 and directed the Respondent to hand over Flat No. 3 by 20 November 2026.
pp. 14–15 · ¶ 23–24If she failed to do so, the Society could take possession with police assistance.
pp. 14–15 · ¶ 23–24If the Respondent was absent when possession was taken, the Society was directed to inventory any movables and notify her; unclaimed movables could thereafter be dealt with in accordance with law.
pp. 14–15 · ¶ 23–24No order as to costs was made.
pp. 14–15 · ¶ 23–24Original Court PDF
Pritam Sadan Sahakari Gruharchan Sasnth MaryaditvsJyotsna S. Rajopadhya
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in