Facts
IRCON, the petitioner, engaged Kanchanjunga Construction Co. Pvt. Ltd. (KCCPL), the respondent, as a subcontractor for part of a highway project in Nepal.
Source reference: p. 1–6The works were delayed amid material-supply issues and political unrest, including bandhs.
Source reference: p. 1–6After the subcontract was closed, KCCPL claimed, among other things, compensation for idling of resources and interest.
Source reference: p. 1–6The sole arbitrator allowed idling compensation for 248 days, price adjustment, and compound interest, and rejected IRCON’s counterclaims.
Source reference: p. 1–6IRCON challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, principally contesting the idling award and compound interest.
Source reference: p. 1–6The Court assessed the challenge under the pre-2015 amendment framework.
Source reference: p. 6Issues
1. Whether the arbitrator’s award of idling compensation, despite contractual provisions concerning force majeure and bandh-related extensions, was contrary to the contract and the unamended Section 28(3) of the Act.
Source reference: p. 15–192. Whether, absent a contractual prohibition, the arbitrator could award compound interest for the pre-award period under Section 31(7)(a) of the Act.
Source reference: p. 19–28Law Applied
Under the pre-amendment Section 28(3) of the Arbitration and Conciliation Act, 1996, an arbitral tribunal was required to decide in accordance with the contract; an award departing from contractual terms could be set aside if the departure amounted to patent illegality going to the root of the matter.
Source reference: p. 6–12ONGC Ltd. v. Saw Pipes Ltd., Associate Builders v. DDA and related authorities set out the limits on interference under Section 34, including that a reasonable contractual interpretation is not open to review.
Source reference: p. 6–12Section 31(7)(a) empowers an arbitral tribunal, unless the parties have agreed otherwise, to award interest at a rate it considers reasonable for all or part of the period from the cause of action to the award; contractual silence is not, by itself, an exclusion of that power.
Source reference: p. 20–24In Hyder Consulting (UK) Ltd. v. State of Orissa, the Supreme Court held that the Act permits compound interest where the tribunal awards it in exercising its statutory discretion.
Source reference: p. 24–28Reasoning
On idling costs, the Court noted that the arbitrator had found the claim unsustainable under the contract when considered in isolation.
Source reference: p. 17–19However, the arbitrator also relied on IRCON’s undisputed representation that it would accept KCCPL’s claim on the same basis as IRCON’s own idling-cost recovery from the Government of Nepal, subject to supporting documentation.
Source reference: p. 17–19IRCON had itself relied on KCCPL’s records to pursue that recovery.
Source reference: p. 17–19The Court treated the representation and conduct as an admission and waiver, and held that IRCON could not rely on the contractual bar to resile from its undertaking.
Source reference: p. 17–19On interest, the Court held that the contract contained no prohibition on interest and that silence did not displace the discretion under Section 31(7)(a).
Source reference: p. 21–28Applying Hyder Consulting, it found that compound interest was within the arbitrator’s power and that no basis for interference had been shown.
Source reference: p. 21–28Holding
The Court rejected both challenges.
It held that the award of idling compensation for 248 days was sustainable in light of IRCON’s admission and waiver, and that the award of compound interest was permissible under Section 31(7)(a).
Source reference: p. 18–19, 27–28The Section 34 petition was dismissed, along with any pending applications.
Source reference: p. 28Acts & Sections Cited
17 provisions across 3 statutes referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 1996
Indian Contract Act, 18722
Original Court PDF
M/S Ircon International LimitedvsKanchanjunga Construction Co Pv Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
