01Facts
The Petitioner filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking to restrain Respondent No. 1 (RVNL) from encashing five Bank Guarantees totaling approximately ₹22.7 crores
pp. 1-2Despite a stay order granted by the Court on 21.04.2026, the Respondents encashed the guarantees, claiming the action occurred prior to receiving the formal court order
p. 2The dispute arose from a Contract Agreement dated 30.08.2024 involving claims of approximately ₹170 Crores
pp. 3-402Issues
i.1. Whether interim protection should be granted to secure the encashed Bank Guarantee amounts pending arbitration
pp. 2-3ii.2. Whether the dispute should be referred to an Arbitral Tribunal despite the absence of a Section 21 notice and a Section 11 petition
pp. 3-403Law Applied
The Court primarily applied Section 9 of the Arbitration and Conciliation Act, 1996, which empowers the Court to grant interim measures of protection
p. 1Section 17 of the Act, which allows an Arbitral Tribunal to order interim measures
p. 5The principle of Party Autonomy was utilized to waive the statutory requirements of Section 21 (Notice of Arbitration) and Section 11 (Appointment of Arbitrators) because the parties were ad idem (in agreement) regarding the reference to arbitration
p. 4Clause 20.3 of the General Conditions of Contract (GCC) served as the underlying arbitration agreement
p. 3Provisions in the judgment · 5 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9Section 11Section 12Section 17Section 21
04Reasoning
The Court noted that since the Bank Guarantees had already been encashed despite a stay, a restorative interim measure was necessary. Respondent No. 1 offered to deposit the encashed funds into the Petitioner’s account, and the Petitioner undertook not to utilize those funds until the Arbitral Tribunal issued further directions
pp. 2-3Regarding the constitution of the tribunal, the Court observed that since both parties agreed to arbitrate and had already identified their respective nominee arbitrators, insisting on the formal procedure of a Section 21 notice and a Section 11 petition would cause "undue delay"
p. 4Consequently, the Court exercised its discretion to fast-track the tribunal's formation to ensure the Section 9 petition could be effectively converted into a Section 17 application
p. 505Holding
The Court directed Respondent No. 1 to deposit the encashed amounts into the Petitioner’s ICICI Bank account, with the Petitioner prohibited from withdrawing the funds pending a decision by the Arbitral Tribunal
p. 3The Court waived the requirements of Section 21 and Section 11, appointing a three-member Tribunal consisting of Mr. Justice G.P. Mittal (Retd.) and Mr. S.D. Sharma (Retd. Director, CPWD), who are to appoint a Presiding Arbitrator within two weeks. The Section 9 petition was directed to be treated as a Section 17 application before the Tribunal, to be decided within two months of the Tribunal's constitution. The petition was disposed of with all contentions left open
pp. 4-6Original Court PDF
Anant Sky Infrastructure Pvt LtdvsRail Vikas Nigam Ltd. And Anr & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
