01Facts
The petitioner applied on 03.06.2016 for a quarry lease over 12 acres in Sy. No. 290/1, Karekal Village, Ballari Taluk, for murram and building stone for 20 years.
¶ 1 · ¶ 4.1A Geologist's technical report of 28.07.2016 found the land suitable for murram, but the application was not processed.
¶ 4.1Successive writ proceedings followed: W.P. No. 16753/2017 led to a direction to consider the application, and an endorsement rejecting it (05.09.2017) was set aside in W.P. No. 49371/2017 by a common order dated 23.07.2018, which directed the authorities to decide the application.
¶ 4.2–4.3 · ¶ 8The Deputy Conservator of Forests (15.03.2019) and the Tahsildar (18.07.2019) issued NOCs.
¶ 4.4 · ¶ 9The Senior Geologist issued a grant notification on 06.08.2020 for murram only, for 20 years, with a note requiring execution of the lease deed within six months.
¶ 4.5 · ¶ 11, 16A Geologist's report of 29.03.2023 found building stone present, and a corrigendum dated 30.05.2023 extended the grant to murram and building stone. That corrigendum required execution of the lease deed within three months and EC within 180 days.
¶ 4.7, 18–19The petitioner obtained EC on 29.11.2023 and, on 30.12.2023, requested execution of the lease deed.
¶ 4.8, 21The respondents refused execution on three grounds: (i) Rule 8B(2)(e) KMMC Rules (24-month registration window from 12.08.2016); (ii) deemed revocation under Rule 30(1) for non-execution within three months of the corrigendum; and (iii) lack of competence of the Senior Geologist without State Government approval.
¶ 2 · ¶ 3 · ¶ 502Issues
i.1. Whether the respondents can refuse execution of the lease on the ground that the 24-month period under Rule 8B(2)(e) of the KMMC Rules, as amended in 2016, had expired, where the delay arose from the respondents' own failure to process the application.
¶ 5 · ¶ 7–11ii.2. Whether the grant stood deemed revoked under Rule 30(1) of the KMMC Rules, as in force prior to 12.08.2016, for non-execution of the lease deed within the period stated in the grant notification or corrigendum.
¶ 12 · ¶ 14–15 · ¶ 19–21iii.3. Whether the Senior Geologist, as Competent Authority, lacked power to execute the lease without prior State Government approval.
¶ 3 · ¶ 5 · ¶ 2303Law Applied
Rule 8B(2)(e) of the KMMC Rules, as substituted by the KMMC (Amendment) Rules, 2016 and extended by the notification dated 18.07.2017, preserved pending applications for execution and registration within 24 months of 12.08.2016.
¶ 6 · ¶ 7Rule 30(1) of the KMMC Rules, as in force before 12.08.2016, required execution of the lease deed within six months of the grant order, or within such further period as the Competent Authority allowed, failing which the Competent Authority was to communicate cancellation.
¶ 13–14Rule 18 of the amended KMMC Rules permits the Competent Authority to extend the time for execution.
¶ 22The grant notification's own terms define the execution timeline, and the authorities cannot rely on a deadline they themselves created or failed to act upon.
¶ 10–11 · ¶ 15, 21The Court relied on no Supreme Court authority; its reasoning rests on the rules and this Court's earlier orders in W.P. Nos. 16753/2017 and 49371/2017.
¶ 4.2–4.3 · ¶ 8, 10Provisions in the judgment · 1
the Act (alias, unresolved) Section 8A
04Reasoning
On the first issue, the Court held that the 24-month period expired only because the respondents had wrongly rejected the application, which this Court had set aside. The application was then processed on the basis of those orders, and the grant notification of 06.08.2020 was issued after the 24 months had already elapsed.
¶ 8–10The respondents could not rely on a limitation period that their own unlawful rejection had caused, and they could not raise the bar after issuing a notification directing execution within six months.
¶ 10–11On the second issue, the Court held that Rule 30(1) was not triggered because no cancellation communication had been issued before the petition was filed. The grant was not in accordance with the petitioner's application until the corrigendum of 30.05.2023, which is the operative date of grant.
¶ 15 · ¶ 15–17The three-month period in the corrigendum was erroneous because it referred to the pre-16.12.2013 text of Rule 30(1), which provided six months or such further period as the Competent Authority allowed; the respondents conceded this error. The petitioner had obtained EC and requested execution, so no impediment to execution remained.
¶ 21On the third issue, the Court held that the petitioner had complied with the conditions. If State Government approval was required, it was the authorities' duty to obtain it, and they could not refuse execution for their own failure to do so.
¶ 2305Holding
The respondents cannot refuse execution on the ground of the expired 24-month period under Rule 8B(2)(e).
¶ 10–11The grant was not deemed revoked under Rule 30(1), because the operative grant date was 30.05.2023, the three-month period in the corrigendum was erroneous, and no cancellation had been communicated. The lack of State Government approval is no ground to refuse execution, since the authorities were bound to obtain any required approval.
¶ 15, 21 · ¶ 23The writ petition is allowed. The concerned authorities are directed to take steps for execution of the lease, subject to the petitioner's compliance with all formalities and conditions. The Court did not fix a specific time limit for execution.