Facts
The petitioner entered into an agreement with the Madhya Pradesh Warehousing and Logistic Corporation for the procurement season 2023–24 on 21 April 2023.
Source reference: p.1, para. 2Government food grains, principally wheat, remained stored in the petitioner’s warehouse since 2023, with approximately 400–421 metric tonnes allegedly still awaiting lifting by the respondents.
Source reference: p.2, paras. 7–8The petitioner made repeated representations requesting removal of the stock, but no decision was taken and the commodities were not lifted.
Source reference: p.1, paras. 2–3The petitioner also alleged that an illegal gratification was demanded by officials in connection with lifting the stock, following which a complaint was made and certain officers were allegedly suspended; however, the relevant suspension documents were not placed on record.
Source reference: p.2, para. 4The respondents relied on Condition 9.2 of the agreement, contending that the contractual arrangement continued until the stored commodities were finally lifted and that they could lift the stock at their discretion.
Source reference: p.2, para. 6The petitioner further contended that rent was payable at approximately ₹4,10,000 per month under the agreement and could not be reduced while the respondents continued occupying the warehouse.
Source reference: p.2, para. 8During final hearing, the respondents undertook to decide the petitioner’s pending representation within 30 days.
Source reference: p.3, paras. 9–10Issues
Whether the respondents could be directed to take a decision on the petitioner’s pending representation concerning the lifting of government food grains stored in its warehouse?
Source reference: p.3, paras. 9–12Whether the respondents’ continued storage of the commodities entitled the petitioner to contractual rent, notwithstanding the respondents’ reliance on Condition 9.2 of the agreement?
Source reference: p.2, paras. 6–8Whether the respondents’ reply, which did not explain the continued non-lifting of the commodities, warranted the imposition of costs?
Source reference: p.4, para. 11Law Applied
The Court applied the contractual terms governing storage and lifting of government food grains, particularly Condition 9.2 of the JBS Agreement, under which the agreement remained in force until the stored commodities were finally lifted.
Source reference: p.2, para. 6It further applied the contractual principle that, so long as the respondents continued to occupy the petitioner’s warehouse with stored commodities, rent remained payable in accordance with the agreement and could not be reduced merely because the respondents delayed lifting the stock.
Source reference: p.2, para. 8In exercising writ jurisdiction, the Court accepted the respondents’ undertaking and directed the competent authority to decide the petitioner’s pending representation within the specified period.
Source reference: p.3, paras. 9–12Reasoning
The Court noted that the respondents’ reply relied generally on policy provisions and Condition 9.2 but failed to explain why the food grains had not been lifted despite repeated requests.
Source reference: p.2, paras. 5–8The Court also recognised the petitioner’s contention that wheat has a limited shelf life and that continued storage since April 2023 could affect the commodities.
Source reference: p.2, para. 7Although the petitioner sought a direct direction for immediate lifting of the stock, the Court disposed of the petition on the basis of the respondents’ categorical undertaking to decide the pending representation within 30 days.
Source reference: p.3, paras. 9–12The Court separately observed that continued occupation of the warehouse attracted payment of rent under the agreement, and criticised the respondents’ failure to address that central issue in their reply.
Source reference: p.2, para. 8Given the inadequacy of the reply, costs of ₹25,000 were imposed on the Officer-in-Charge of the case.
Source reference: p.4, para. 11Holding
The petition was finally disposed of with a direction to Respondent No. 2 to decide the petitioner’s representation, marked Annexure P/2, within 30 days from the date of the order.
The Court did not itself direct immediate lifting of the stock but required a reasoned decision on the petitioner’s grievance.
Source reference: p.4, para. 12The Court further directed payment of ₹25,000 as costs to the M.P. High Court Bar Association within seven days, to be borne by the Officer-in-Charge, for filing an inadequate and unresponsive reply.
Source reference: p.4, para. 11Original Court PDF
Shri Nath WarehousevsMadhya Pradesh Warehousingh And Logistic Corporation Mpwlc
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
