Bombay High CourtAdministrative and Public LawProperty and Real Estate Law

Bombay HC upholds BMC order to vacate and demolish unsafe Andheri (East) building, says courts won't second-guess expert TAC findings

Dharmesh Book Mfg Co.Pvt. Ltd., Thru Director Jyesh Champshi Shahv.The Assistant Commissioner (K/Eastward) Bmc

Bombay HC upholds BMC order to vacate and demolish unsafe Andheri (East) building, says courts won't second-guess expert TAC findings. Dharmesh Book Mfg Co.Pvt. Ltd., Thru Director Jyesh Champshi Shah vs The Assistant Commissioner (K/Eastward) Bmc. Bombay High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the TAC Order dated 20 May 2026 is vitiated by breach of the principles of natural justice, in view of the non-supply of the SPCE SAR and non-consideration of the petitioners' consultant's SAR.

The court held

The Court answered all three issues against the petitioners. The TAC Order dated 20 May 2026, which accepted the SPCE SAR and classified the building as C-1, and the consequential notice dated 29 May 2026 were held to be legal, within the four corners of law, and not vitiated by natural justice violations, arbitrariness, or non-application of mind.

It also directed

The Court declined to interfere under Article 226.

The writ petitions, including the connected petitions, were dismissed, the rule was discharged, and no costs were awarded.

01Facts

The petitioners, tenants/occupiers of Commercial Unit No. 16 in "Krishna Dyeing & Printing Works," Andheri (East), challenged a Technical Advisory Committee (TAC) Order dated 20 May 2026 classifying the building as "C-1" (unsafe; to be vacated and demolished) and a consequential notice dated 29 May 2026 issued under Section 354 of the MMC Act.

¶ 4–5

The BMC issued a Section 353B notice, and multiple structural audit reports (SARs) followed.

¶ 7–8

The owner's SAR (Avon Consulting Engineers) classified the building as C-1.

¶ 7, 10

The tenants' SARs were conflicting: Aarch Consultants classified it as C-3, Tech-Resurgo as C-2A, and B.J. Mehta (petitioners' consultant) as C-2A.

¶ 7–8, 12

A further SAR by Sardar Patel College of Engineering (SPCE), appointed by the owner after a TAC direction for third-party audit, classified it as C-1.

¶ 11–12

The petitioners applied on 20 February 2026 for a certified copy of the SPCE SAR.

¶ 14

The TAC held a site inspection on 17 February 2026, attended by representatives of all consultants, and a meeting the same day.

¶ 35

The TAC accepted the SPCE report and ordered evacuation and demolition on 20 May 2026.

¶ 13, 33

02Issues

i.1. Whether the TAC Order dated 20 May 2026 is vitiated by breach of the principles of natural justice, in view of the non-supply of the SPCE SAR and non-consideration of the petitioners' consultant's SAR.

¶ 14, 36–38

ii.2. Whether the TAC Order is non-speaking, arbitrary, or reflects non-application of mind, such that the Court should interfere under Article 226 despite conflicting structural reports.

¶ 15–19, 37–38, 45

iii.3. Whether the High Court may re-appraise the technical findings of the TAC and prefer one expert report over another.

¶ 42–45

03Law Applied

Article 226 of the Constitution, under which writ courts do not decide whether a structure is actually dilapidated or substitute their views for expert findings, and interfere only on grounds of fraud, gross perversity, or complete non-application of mind.

¶ 42, 44(a), (e)–(f)

Sections 353B and 354 of the Mumbai Municipal Corporation Act, 1888, under which the Corporation may act on structural condition reports, and Section 354(5), together with the Maharashtra Rent Control Act, 1999, which protect tenancy rights despite demolition.

¶ 4, 29, 44(b)

The 2014 Co-ordinate Bench order in Municipal Corporation of Greater Mumbai v. State of Maharashtra (WP (L) No. 1135 of 2014) and the BMC TAC guidelines of 25 May 2018, which provide for referral of conflicting SARs to a TAC.

¶ 6, 39–41

Shaha Ratanshi Khimji & Sons v. Kumbhar Sons Hotel Pvt. Ltd., (2014) 14 SCC 1, on the unaffected rights of tenants.

¶ 30

Andheri Purab Paschim Cooperative Housing Society Ltd. v. MCGM, 2023 SCC OnLine Bom 2522, that the TAC is a check against unilateral declarations and is not a fresh cause of action in writ jurisdiction.

¶ 43

The principles summarised in Tushar Ranglidas Notaria and the cases cited therein, including that mala fides must be proved, that a TAC report is not invalidated merely by a rival report, and that an absolutist preference for repair reports is impermissible.

¶ 44, quoting paras 18–20

Provisions in the judgment · 2 · Linked ones open on LawLens

Mumbai Municipal Corporation Act. Section 354

Maharashtra Rent Control Act, 1999 Section 14

04Reasoning

The Court held that the natural justice challenge was misconceived, as the impugned order reproduces a detailed, consultant-by-consultant analysis of all five SARs, and the TAC expressly considered the SPCE and B.J. Mehta reports.

¶ 36–37

The petitioners' consultant was present at the 17 February 2026 site inspection and meeting, which weighed against the claim of prejudice.

¶ 35

The Court treated the TAC's reasoned findings as curing any alleged gap in opportunity to object.

¶ 38

The non-speaking and arbitrariness challenges failed because the order contains reasons for preferring the C-1 classification, so it cannot be characterised as non-speaking.

¶ 37–38

The minority-view objection, that two of five reports classified the building as C-1, was rejected, as the TAC, as an expert body, weighed the reports and returned reasoned findings, and a report recommending repair is not to be preferred absolutely.

¶ 24 (quoted), 45

The Court reaffirmed that it does not decide structural stability and reviews only the decision-making process, since TAC reports determine no rights and tenancy rights survive demolition.

¶ 44 (quoting paras 19–20)

The judgment does not expressly record whether the SPCE SAR was physically supplied to the petitioners before 20 May 2026; the rejection of the natural justice challenge rests on the TAC's consideration of the report and the consultant's participation.

¶ 36–38

05Holding

The Court answered all three issues against the petitioners. The TAC Order dated 20 May 2026, which accepted the SPCE SAR and classified the building as C-1, and the consequential notice dated 29 May 2026 were held to be legal, within the four corners of law, and not vitiated by natural justice violations, arbitrariness, or non-application of mind.

¶ 37–38, 45–46

The Court declined to interfere under Article 226.

¶ 47

The writ petitions, including the connected petitions, were dismissed, the rule was discharged, and no costs were awarded.

¶ 48
Bombay High Court

Original Court PDF

Dharmesh Book Mfg Co.Pvt. Ltd., Thru Director Jyesh Champshi ShahvsThe Assistant Commissioner (K/Eastward) Bmc