Delhi High CourtArbitration and MediationContract Law

Court cannot test MSMED Council reference's validity under Section 9; tribunal decides under Section 16.

Ms Interarch Building Solutions Limited (Formerly Ms Interarch Building Products Ltdv.Agrima Rood And Facade Systems

Court cannot test MSMED Council reference's validity under Section 9; tribunal decides under Section 16.. Ms Interarch Building Solutions Limited (Formerly Ms Interarch Building Products Ltd vs Agrima Rood And Facade Systems. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Respondent's reference under Section 18 of the MSMED Act affects the maintainability of the Section 9 petition.

The court held

The dispute stands referred to arbitration under Section 18(3) of the MSMED Act, and the 1996 Act applies to it.

It also directed

The Petitioner's objections to the validity of the reference are for the arbitral tribunal under Section 16, and Clause 19's incorporation remains open.

The petition, not entertained before the tribunal's constitution and lacking any showing of inefficacy of Section 17, is barred by Section 9(3).

The petition was dismissed. The Petitioner was granted liberty to approach the tribunal under Section 17 for the same reliefs or other interim measures, to be decided expeditiously and without influence from the judgment's observations, without prejudice to its Section 16 objections.

All contentions on jurisdiction and merits were left open, and the observations were stated to be prima facie only. No costs were awarded.

01Facts

The Petitioner, a pre-engineered building contractor, entered into a Works Contract with the Respondent, a Bengaluru-based registered small enterprise under the MSMED Act, on 12.01.2022.

¶ 6–7

Clause 19 of the Contract provided for arbitration.

¶ 1

A Work Order dated 03.09.2025 for works worth Rs. 10.5 crores contained no arbitration clause but incorporated the Contract's terms.

¶ 11

The Petitioner alleged delay, poor workmanship and sub-vendor payments, and on 24.12.2025 revised the Work Order downward.

¶ 12–16

The Respondent abandoned the site on 25.01.2026, and its equipment remains at the site.

¶ 17

A cheque of Rs. 1.05 crores furnished for the mobilisation advance was dishonoured on presentation.

¶ 18

The Petitioner invoked arbitration on 17.02.2026.

¶ 20

On 01.02.2026, before the Petitioner's invocation, the Respondent filed a reference before the Micro and Small Enterprises Facilitation Council, Bengaluru (Case No. CP/00655(KA)/2026), claiming Rs. 9,55,00,550.

¶ 21, 36, 50

Conciliation failed and the Council referred the dispute to the Arbitration and Conciliation Centre, Bengaluru, under Section 18(3) on 23.07.2026.

¶ 21, 50

The Petitioner filed this Section 9 petition on 15.04.2026 seeking non-dissipation of equipment, return of materials, deposit of Rs. 62.94 lakhs (sub-vendor payments) and deposit of Rs. 2 crores (penalty/excess payment).

¶ 2, 3

The petition was first heard on 15.05.2026, when the Respondent was unrepresented and notice was issued.

¶ 51, 93

On 31.08.2026 the Court was informed that the arbitral tribunal stood constituted, and the matter was adjourned at the Petitioner's request.

¶ 51, 93

02Issues

i.1. Whether the Respondent's reference under Section 18 of the MSMED Act affects the maintainability of the Section 9 petition.

¶ 44(i)

ii.2. Whether objections concerning the nature of the contract (works contract), the "appointed day," limitation, the nature of the claims and the Respondent's MSME status can be adjudicated by this Court or must be decided by the statutory arbitral tribunal.

¶ 44(ii), 57

iii.3. Whether, upon constitution of the arbitral tribunal, the bar in Section 9(3) of the 1996 Act precludes the Court from entertaining the petition.

¶ 44(iii), 84

iv.4. Whether the Petitioner has established circumstances warranting interim protection.

¶ 44(iv)

03Law Applied

Section 18 of the MSMED Act permits "any party to a dispute" regarding an amount due under Section 17 to refer the dispute to the Council, which conciliates and, on failure, arbitrates "as if" under an arbitration agreement under Section 7(1) of the 1996 Act, with overriding effect under Section 24.

¶ 45–48

Under Gujarat State Civil Supplies Corporation v. Mahakali Foods (P) Ltd., the statutory mechanism prevails over a contractual arbitration agreement, and the Council or institution acts as an arbitral tribunal competent to rule on its own jurisdiction under Section 16 of the 1996 Act (kompetenz-kompetenz).

¶ 49, 58–59

The same principle is drawn from Dalmia Cement (Bharat) Ltd. v. ESS ESS Technofabs (P) Ltd. and Corrtech International (P) Ltd. v. DIAC.

¶ 60–61

The Limitation Act applies to Section 18(3) arbitrations, as held in Silpi Industries v. KSRTC and Sonali Power Equipments v. MSEB.

¶ 75–76

Section 9(3) of the 1996 Act bars the Court from entertaining a Section 9 application after the tribunal is constituted unless circumstances render the Section 17 remedy inefficacious.

¶ 84

Under Arcelor Mittal Nippon Steel (India) Ltd. v. Essar Bulk Terminal Ltd., "entertain" requires the Court to have applied its mind to the application before constitution of the tribunal, and the bar operates after constitution.

¶ 86–88, 92

Energo Engineering and Benara Bearings were referenced on the Court's residual power.

¶ 90–91

04Reasoning

The Court held that the Respondent's Section 18 reference was validly made, as the Council's order and the parties' correspondence confirm the proceedings.

¶ 50

Under Mahakali Foods, the statutory reference is maintainable even where a separate arbitration clause exists, so the Petitioner's priority argument was immaterial.

¶ 52

The Court declined to decide whether Clause 19 is incorporated into the Work Order, because under either outcome the statutory tribunal governs the dispute.

¶ 54

On the Petitioner's challenges (works contract exclusion, appointed day, limitation, nature of claims, misrepresentation of MSME status), the Court held that each goes to the tribunal's jurisdiction and must be decided under Section 16.

¶ 57–62

A buyer's denial of liability is itself a "dispute" under Section 18(1), and accepting the contrary view would let a buyer defeat the reference by denial.

¶ 57–62

The works-contract question is divergent in judicial opinion and pending before the Supreme Court, and is a mixed question of fact and law that a prima facie court should not resolve.

¶ 64–67

The appointed-day dispute turns on disputed facts, limitation is a defence for the tribunal, and the claim heads must be examined individually.

¶ 71–79

On Section 9(3), the Court found the petition was not "entertained" before the tribunal's constitution: on 15.05.2026 notice was merely issued, and on 31.08.2026 the matter was adjourned, so Arcelor Mittal was distinguishable.

¶ 93

The Petitioner showed no circumstance rendering the Section 17 remedy inefficacious; the reliefs sought are of a kind the tribunal can grant under Section 17(1)(ii)(b)–(d), and the mere assertion of lack of jurisdiction does not suffice.

¶ 94–95

The Court therefore did not reach the merits of the interim reliefs.

¶ 96

05Holding

The dispute stands referred to arbitration under Section 18(3) of the MSMED Act, and the 1996 Act applies to it.

¶ 97(i)

The Petitioner's objections to the validity of the reference are for the arbitral tribunal under Section 16, and Clause 19's incorporation remains open.

¶ 97(ii)

The petition, not entertained before the tribunal's constitution and lacking any showing of inefficacy of Section 17, is barred by Section 9(3).

¶ 96, 97(iii)

The petition was dismissed. The Petitioner was granted liberty to approach the tribunal under Section 17 for the same reliefs or other interim measures, to be decided expeditiously and without influence from the judgment's observations, without prejudice to its Section 16 objections.

¶ 98(i)–(ii)

All contentions on jurisdiction and merits were left open, and the observations were stated to be prima facie only. No costs were awarded.

¶ 98(iii), 99–100
Delhi High Court

Original Court PDF

Ms Interarch Building Solutions Limited (Formerly Ms Interarch Building Products LtdvsAgrima Rood And Facade Systems

Delhi High Court · November 27, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment