01Facts
The appellant was the successful bidder for providing hired vehicle services to HESCOM for commutation of officers in the Hubballi and Belagavi Zones.
¶ 3The appellant furnished two bank guarantees, for ₹36,69,500/- (No. 250063BG000014) and ₹36,43,000/- (No. 250063BG000013), dated 22.01.2025, as performance security.
¶ 4 · ¶ 2 of the Single Judge order, quoted at para. 5The work order was issued on 28.01.2025 and services commenced on 01.02.2025.
¶ 9 · ¶ 5Services were disrupted from 07.04.2025, and HESCOM issued a show-cause notice dated 08.04.2025 citing service lapses and non-payment to drivers and vehicle owners.
¶ 11The appellant replied on 11.04.2025, attributing the stoppage to miscommunication and stating that services had resumed.
¶ 12By letter dated 29.04.2025, the appellant unilaterally withdrew services, citing lack of official support and rejected amendment requests.
¶ 13HESCOM terminated the contract and forfeited the bank guarantees by order dated 17.07.2025.
¶ 5 · prayer IIIThe appellant's representation of 24.06.2025 seeking release was not acceded to.
¶ 13, 14The Single Judge dismissed the writ petition (W.P. No. 105345 of 2025) on 01.08.2025, holding that the withdrawal was a contractual breach entitling invocation.
¶ 5, 6The appellant appealed the Single Judge's order by way of Writ Appeal No. 100579 of 2025.
02Issues
i.1. Whether the respondent could forfeit the bank guarantees without first determining the loss or damages caused by the appellant's non-performance.
¶ 6 · ¶ 15, 16ii.2. Whether the forfeiture of the bank guarantees was in accordance with law, such that the High Court in writ jurisdiction should refrain from interfering.
¶ 15 · ¶ 1903Law Applied
The court relied on contractual Clauses 32, 33 and 37 of the work award, which permit termination and forfeiture for breach and provide for recovery of losses, with Clause 33 expressly allowing termination at HESCOM's discretion for unsatisfactory or non-performing services.
¶ 9A bank guarantee is an independent and distinct contract, unaffected by disputes under the underlying contract, and an unconditional guarantee payable on demand must be honoured, as laid down in General Electric Technical Services Co. v. Punj Sons (1991) 4 SCC 230.
¶ 17.1The principle that a bank guarantee is an independent contract was applied following Hindustan Steelworks Construction Ltd. v. Tarapore & Co. (1996) 5 SCC 34.
¶ 17.2Courts cannot restrain invocation made in accordance with the guarantee's terms, as held in National Highways Authority of India v. Ganga Enterprises (2003) 7 SCC 410.
¶ 17.3The court applied U.P. Co-operative Federation Ltd. v. Singh Consultants and Engineers (1998) 1 SCC 174 on the scope of interference with bank guarantees.
¶ 18.1The court applied Andhra Pradesh Pollution Control Board v. CCL Products (India) Ltd. (2019) 20 SCC 669, which quotes Ansal Engg. Projects Ltd. v. Tehri Hydro Development Corpn. (1996) 5 SCC 450 and Hindustan Construction Co. Ltd. v. State of Bihar (1999) 8 SCC 436.
¶ 18.2Absent fraud, irretrievable injustice or special equities, courts must not interfere with invocation or encashment of a bank guarantee made in terms of the guarantee.
¶ 19Provisions in the judgment · 1 · Linked ones open on LawLens
KARNATAKA HIGH COURT ACT, 1961 Section 4
04Reasoning
The court treated the appellant's unilateral withdrawal of services, which the appellant itself admitted in its letter of 29.04.2025, as a breach of contract.
¶ 15Since breach was established by the appellant's own communication, the court held that a separate quantification of damages was unnecessary.
¶ 16Termination followed as a natural consequence, and forfeiture of the guarantees followed from termination.
¶ 15, 16The court found that a show-cause notice had been issued, satisfying the requirement of notice before invocation.
¶ 16Because the guarantees were invoked under their terms and no fraud or special equity was shown, the court held that the High Court could not interfere with invocation under the Apex Court principles.
¶ 17–19The appellant's grievances regarding lack of official support were not accepted as justification for withdrawal, and the court did not separately examine them.
¶ 13 · ¶ 1505Holding
The appellant's withdrawal of services was a breach of contract, and termination and forfeiture of the bank guarantees were a legitimate consequence.
¶ 15, 16No damages assessment was required before invocation of the bank guarantees.
¶ 16No fraud, irretrievable injustice or special equity had been shown to justify interference with invocation. The Division Bench found no error in the Single Judge's order and dismissed the writ appeal. The prayers for quashing the forfeiture order dated 17.07.2025, for release of the guarantees, and for release of encashed amounts with interest were refused.
¶ 19, 20Original Court PDF
M/S TRAVELS WORLDvsHUBLI ELECTRICITY SUPPLY COMPANY LIMITED (HESCOM)
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in