Patna High Court

### Debarment Orders Passed by Incompetent Authorities or for Indefinite Periods are Legally Unsustainable and Violate Natural Justice.

Sindhuja Engineer and Contractor vs The State of Bihar

Patna High CourtJUDGMENT: April 18, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a registered Class I contractor, was awarded a contract for the "Mukhya Mantri Peyjal Nischay Yojana" in Banka district for fluoride removal and maintenance.

Source reference: p. 2

Following the completion of the work, the Executive Engineer (Respondent No. 4) issued a directive on 17.12.2025 for the payment of electricity bills, warning of debarment for non-compliance.

Source reference: p. 3

On 29.12.2025, Respondent No. 4 issued Office Order No. 174, debarring the petitioner firm indefinitely.

Source reference: p. 1-3

The petitioner challenged this order on the grounds of lack of jurisdiction and the illegality of permanent debarment.

Source reference: p. 3-4
02

Issues

1. Whether an order of debarment can be passed for an indefinite period?

Source reference: p. 3 / para. 4

2. Whether the Executive Engineer (Respondent No. 4) was the competent authority to issue the debarment order under the Bihar Contractors Registration Rules, 2007?

Source reference: p. 4 / para. 5
03

Law Applied

The Court applied Rule 11(d) of the Bihar Contractors Registration Rules, 2007, which mandates that blacklisting/suspension orders must be passed by the officer competent to register the contractor or their superior.

Source reference: p. 4

It relied on the precedent of Kuljha Industries Limited v. Chief General Manager, BSNL (2014) 14 SCC 731, established that "debarment" is never permanent and its duration must be proportionate to the nature of the offense.

Source reference: para. 4

the court emphasized the principles of natural justice, requiring a valid show-cause notice from a competent authority before punitive action.

Source reference: p. 6
04

Reasoning

The Court found the impugned order legally flawed on two primary jurisdictional grounds. First, under Rule 11(d), the Registering Authority was the Chief Engineer (Respondent No. 3), not the Executive Engineer (Respondent No. 4); thus, the latter lacked the legal competence to issue show-cause notices or debarment orders.

Source reference: p. 5-6

The Court reasoned that a debarment order issued without a valid notice from the competent authority violates natural justice.

Source reference: p. 6

The Court observed that the petitioner was debarred indefinitely, which directly contradicts the Apex Court's ruling in Kuljha Industries, where it was held that permanent debarment violates the doctrine of proportionality and the fundamental right to carry on trade.

Source reference: p. 6
05

Holding

The Court answered both issues in the negative. It held that the debarment order was unsustainable as it was passed by an incompetent authority and lacked a finite duration.

The High Court quashed the Office Order dated 29.12.2025 and remanded the matter to the Respondent No. 3 (Chief Engineer), directing him to issue a fresh show-cause notice and pass a reasoned order in accordance with law and the agreement.

Source reference: p. 6-7

The writ petition was allowed.

Source reference: p. 7
Patna High Court

Original Court PDF

Sindhuja Engineer and ContractorvsThe State of Bihar

Patna High Court · April 18, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment