01Facts
The parties entered into a sub-contract dated 18 December 2025 for works forming part of a PM-KUSUM solar power project in Nanded, Maharashtra.
¶ 1–4After disputes arose over progress and responsibility for delay, Skymax issued a termination notice on 22 October 2026.
¶ 5–7Mbook applied under Section 9 of the Arbitration and Conciliation Act, 1996, seeking, among other reliefs, to stay the termination and prevent Skymax from engaging another contractor.
¶ 8Skymax separately applied under Section 9 for Mbook to vacate the project site and hand over project-related assets and records.
¶ 29–3002Issues
i.1. Whether interim relief could be granted to stay Skymax’s termination of the sub-contract, given the statutory restrictions on injunctions affecting infrastructure projects.
¶ 17–22ii.2. Whether, under Section 9 of the Arbitration and Conciliation Act, 1996, the Court could direct Mbook to vacate the project site to facilitate completion of the project.
¶ 31–4003Law Applied
Section 20A of the Specific Relief Act, 1963 bars injunctions in suits under that Act involving scheduled infrastructure contracts where the injunction would impede or delay the project; Section 41(ha) bars an injunction if it would impede or delay an infrastructure project or interfere with the continued provision of a related facility or service.
¶ 20–22Section 9(1)(ii)(c) and (e) of the Arbitration and Conciliation Act, 1996 empowers a court to grant interim measures to preserve or protect property and to make other just and convenient interim orders, but not to determine finally the substantive dispute reserved for arbitration.
¶ 36, 39–40The Court distinguished Mahajan Imaging (P) Ltd. v. Pushpawati Singhania Research Institute, which concerned a non-infrastructure contract, and considered Deepak Balutia v. Anu Manglani and National Highways Authority of India v. Bhubaneswar Expressway Private Limited on the scope and limits of Section 9 relief.
¶ 14–16, 27, 32–36Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9Section 36
Specific Relief Act, 1963 Section 20Section 41
04Reasoning
The Court declined to stay termination because the contract concerned a solar energy project falling within the infrastructure category in the Schedule to the Specific Relief Act.
¶ 17–22Although Mbook alleged that Skymax had not given the contractually required 30-day cure notice, and asserted that it could complete the works if given the opportunity, the Court considered that staying termination could impede or delay the project.
¶ 9–13, 23–28The termination’s validity and the parties’ allegations were left for arbitration; the Court observed that Mbook’s remedy for wrongful termination would be a claim for damages.
¶ 9–13, 23–28As to Skymax’s application, the Court held that directing Mbook to vacate would not decide Mbook’s damages claim and could assist timely project completion.
¶ 37–41It therefore treated the direction as an interim protective measure within Section 9, rather than a final adjudication of the contractual dispute.
¶ 37–4105Holding
The Court dismissed Mbook’s petition to stay the termination and disposed of its pending application.
¶ 28, 44It partly allowed Skymax’s petition and directed Mbook to vacate the project site within three weeks; the remaining reliefs concerning project records and other matters remained pending, with directions for pleadings and the matter re-notified for 16 December 2026.
¶ 41–46Original Court PDF
Skymax Infra Power LtdvsMbook Technology Pvt Ltd