01Facts
The parties entered into a sub-contract dated 18 December 2025 for works forming part of a PM-KUSUM solar power project in Nanded, Maharashtra.
¶ 1–4After disputes arose over progress and responsibility for delay, Skymax issued a termination notice on 22 October 2026.
¶ 5–7Mbook sought, under Section 9 of the Arbitration and Conciliation Act, 1996, to stay the termination and preserve its position at the project sites; it also sought security for its monetary claim.
¶ 8Skymax filed a cross-petition seeking Mbook’s vacation of the sites and delivery of project documents and records.
¶ 29–3002Issues
i.1. Whether interim relief staying Skymax’s termination of the sub-contract could be granted when the contract concerned an energy-sector infrastructure project and the injunction could impede or delay the project.
¶ 17–22ii.2. Whether, under Section 9 of the Arbitration and Conciliation Act, the Court could direct Mbook to vacate the project sites pending arbitration without thereby finally adjudicating the parties’ disputes.
¶ 31–4003Law Applied
Section 20A of the Specific Relief Act, 1963 bars an injunction in a suit involving a scheduled infrastructure project where granting it would impede or delay the project; the Schedule includes the energy sector.
¶ 17–22Section 41(ha) of that Act similarly bars an injunction if it would impede or delay an infrastructure project, or interfere with the continued provision of a related facility or service.
¶ 21–22Section 9(1)(ii)(c) and (e) of the Arbitration and Conciliation Act, 1996 empowers a court to order interim measures to preserve or protect property and to grant other just and convenient interim protection, but not to make an interim order that amounts to final adjudication of the dispute.
¶ 36, 39–40The Court distinguished Mahajan Imaging (P) Ltd. v. Pushpawati Singhania Research Institute, which concerned a non-infrastructure contract, and considered National Highways Authority of India v. Bhubaneswar Expressway Private Limited for the limit on granting final relief under Section 9.
¶ 14–16, 27 · ¶ 32–36Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9Section 36
Specific Relief Act, 1963 Section 20Section 41
04Reasoning
The Court found that the sub-contract related to a solar project within the energy-sector category in the Specific Relief Act Schedule.
¶ 17–20Staying termination and restoring Mbook to the project could delay completion; the Court therefore declined to grant an injunction, leaving the validity of termination and any claim for damages to arbitration.
¶ 23–28In Skymax’s petition, the Court treated vacation of the site as an interim measure to enable project completion, rather than as final adjudication of Mbook’s damages claim.
¶ 37–42Relying on the breadth of Section 9(1)(ii)(c) and (e), it ordered Mbook to vacate within three weeks, while leaving Skymax’s other requested reliefs for further consideration.
¶ 37–4205Holding
Mbook’s Section 9 petition, O.M.P.(I)(COMM.) 503/2026, was dismissed.
¶ 28, 44Skymax’s petition, O.M.P.(I)(COMM.) 512/2026, was partly allowed: Mbook was directed to vacate the project site within three weeks.
¶ 41–46The remaining reliefs were left pending, with Mbook directed to file a reply and the matter re-notified for 16 December 2026.
¶ 41–46Original Court PDF
Mbook Technology Pvt. Ltd.vsSkymax Infrapower Pvt. Ltd.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in