Delhi High CourtCivil LawArbitration and Mediation

Delhi HC Refuses To Stay Solar Subcontract Termination, Finding A Stay Could Delay The Project, And Orders Subcontractor To Vacate Within 3 Weeks

Mbook Technology Pvt. Ltd.v.Skymax Infrapower Pvt. Ltd.

Delhi HC Refuses To Stay Solar Subcontract Termination, Finding A Stay Could Delay The Project, And Orders Subcontractor To Vacate Within 3 Weeks. Mbook Technology Pvt. Ltd. vs Skymax Infrapower Pvt. Ltd.. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether interim relief staying Skymax’s termination of the sub-contract could be granted when the contract concerned an energy-sector infrastructure project and the injunction could impede or delay the project.

The court held

Mbook’s Section 9 petition, O.M.P.(I)(COMM.) 503/2026, was dismissed.

It also directed

Skymax’s petition, O.M.P.(I)(COMM.) 512/2026, was partly allowed: Mbook was directed to vacate the project site within three weeks.

The remaining reliefs were left pending, with Mbook directed to file a reply and the matter re-notified for 16 December 2026.

01Facts

The parties entered into a sub-contract dated 18 December 2025 for works forming part of a PM-KUSUM solar power project in Nanded, Maharashtra.

¶ 1–4

After disputes arose over progress and responsibility for delay, Skymax issued a termination notice on 22 October 2026.

¶ 5–7

Mbook sought, under Section 9 of the Arbitration and Conciliation Act, 1996, to stay the termination and preserve its position at the project sites; it also sought security for its monetary claim.

¶ 8

Skymax filed a cross-petition seeking Mbook’s vacation of the sites and delivery of project documents and records.

¶ 29–30

02Issues

i.1. Whether interim relief staying Skymax’s termination of the sub-contract could be granted when the contract concerned an energy-sector infrastructure project and the injunction could impede or delay the project.

¶ 17–22

ii.2. Whether, under Section 9 of the Arbitration and Conciliation Act, the Court could direct Mbook to vacate the project sites pending arbitration without thereby finally adjudicating the parties’ disputes.

¶ 31–40

03Law Applied

Section 20A of the Specific Relief Act, 1963 bars an injunction in a suit involving a scheduled infrastructure project where granting it would impede or delay the project; the Schedule includes the energy sector.

¶ 17–22

Section 41(ha) of that Act similarly bars an injunction if it would impede or delay an infrastructure project, or interfere with the continued provision of a related facility or service.

¶ 21–22

Section 9(1)(ii)(c) and (e) of the Arbitration and Conciliation Act, 1996 empowers a court to order interim measures to preserve or protect property and to grant other just and convenient interim protection, but not to make an interim order that amounts to final adjudication of the dispute.

¶ 36, 39–40

The Court distinguished Mahajan Imaging (P) Ltd. v. Pushpawati Singhania Research Institute, which concerned a non-infrastructure contract, and considered National Highways Authority of India v. Bhubaneswar Expressway Private Limited for the limit on granting final relief under Section 9.

¶ 14–16, 27 · ¶ 32–36

Provisions in the judgment · 4 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9Section 36

Specific Relief Act, 1963 Section 20Section 41

04Reasoning

The Court found that the sub-contract related to a solar project within the energy-sector category in the Specific Relief Act Schedule.

¶ 17–20

Staying termination and restoring Mbook to the project could delay completion; the Court therefore declined to grant an injunction, leaving the validity of termination and any claim for damages to arbitration.

¶ 23–28

In Skymax’s petition, the Court treated vacation of the site as an interim measure to enable project completion, rather than as final adjudication of Mbook’s damages claim.

¶ 37–42

Relying on the breadth of Section 9(1)(ii)(c) and (e), it ordered Mbook to vacate within three weeks, while leaving Skymax’s other requested reliefs for further consideration.

¶ 37–42

05Holding

Mbook’s Section 9 petition, O.M.P.(I)(COMM.) 503/2026, was dismissed.

¶ 28, 44

Skymax’s petition, O.M.P.(I)(COMM.) 512/2026, was partly allowed: Mbook was directed to vacate the project site within three weeks.

¶ 41–46

The remaining reliefs were left pending, with Mbook directed to file a reply and the matter re-notified for 16 December 2026.

¶ 41–46
Delhi High Court

Original Court PDF

Mbook Technology Pvt. Ltd.vsSkymax Infrapower Pvt. Ltd.

Delhi High Court · November 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment