Rajasthan High Court

Denial of compensation under specific heads constitutes "determination" and is maintainable for arbitration under Section 3G(5).

SUKHDARSHAN SINGH vs UNION OF INDIA

Rajasthan High CourtJUDGMENT: May 08, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioners’ lands were acquired for the Bharatmala Project Package 3.

Source reference: p.3

During acquisition, a Tehsildar's report confirmed the existence of orchards (kinnu and date palm trees) on the land.

Source reference: p.3

However, the Competent Authority for Land Acquisition (CALA), in its award dated 24.06.2022, denied compensation for the trees, alleging they were planted solely to claim higher compensation.

Source reference: p.3-4

The petitioners challenged this denial before the Arbitrator-cum-District Collector under Section 3G(5) of the National Highways Act (NH Act), 1956.

Source reference: p.4

The Arbitrator rejected the applications as non-maintainable via order dated 16.11.2023, reasoning that since no amount was "quantified" or "determined" by CALA for the trees, there was no "amount" to dispute or adjudicate under Section 3G(5).

Source reference: p.4

The petitioners approached the High Court challenging this refusal.

Source reference: p.4
02

Issues

1. Whether an application for arbitration under Section 3G(5) of the National Highways Act, 1956, is maintainable when compensation under a specific head (such as standing trees) has been entirely denied/refused by the Competent Authority.

Source reference: p.5 / para. 8
03

Law Applied

The court applied Section 3(b) of the National Highways Act, 1956, which provides an inclusive definition of "land" that encompasses things attached to the earth, such as trees.

Source reference: p.6

It relied on Section 3G(5) of the Act, which mandates that if the "amount determined" by the competent authority is not acceptable, it shall be determined by an arbitrator.

Source reference: p.6

The court further adopted the principle from Sagar Dey vs. State of West Bengal (2018), which establishes that "land" includes structures and trees, and any dispute regarding compensation for such attachments—whether undervalued or denied—is amenable to arbitration under Section 3G(5).

Source reference: p.7-8
04

Reasoning

The High Court rejected the Arbitrator's "narrow and hyper-technical" interpretation that only quantified numerical values could be challenged.

Source reference: p.5

The Court reasoned that "determination" is a process of application of mind; therefore, a reasoned denial of compensation constitutes a "determination" of a "nil" amount.

Source reference: p.9-10

Since Section 3(b) defines land to include trees, the CALA's decision to refuse payment for those trees is inherently a determination regarding the total compensation for the "land".

Source reference: p.6-7

The Court emphasized that treating "undervalued" claims as arbitrable while treating "denied" claims as non-arbitrable would create an "anomalous situation" where a landowner would have to approach multiple forums for a single acquisition project, defeating the legislative intent of the NH Act as a self-contained code.

Source reference: p.10-11
05

Holding

The Court answered the issue in the affirmative, holding that objections regarding the denial of a claim under any head are arbitrable and maintainable under Section 3G(5).

The High Court quashed the Arbitrator's orders dated 16.11.2023. The writ petitions were allowed, and the matters were remanded to the Arbitrator-cum-District Collector, Sriganganagar, with directions to restore the applications and decide them on merits within three months.

Source reference: p.11-12
Rajasthan High Court

Original Court PDF

SUKHDARSHAN SINGHvsUNION OF INDIA

Rajasthan High Court · May 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment