Jammu and Kashmir High CourtAdministrative and Public LawContract Law

Departmental lapses in codal formalities cannot deny a contractor payment for admittedly executed works.

NEHAL SINGH MANHASv.UT OF J AND K TH. COMMISSIONER SECRETARY, P.H.E., IRIGATION AND FLOOD CONTROL, JAMMU AND OTHERS

Departmental lapses in codal formalities cannot deny a contractor payment for admittedly executed works.. NEHAL SINGH MANHAS vs UT OF J AND K TH. COMMISSIONER SECRETARY, P.H.E., IRIGATION AND FLOOD CONTROL, JAMMU AND OTHERS. Jammu and Kashmir High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the respondents can refuse payment for admittedly executed works on the ground of absent tendering, administrative approval, technical sanction, approved plan, or funds, which are departmental responsibilities.

The court held

The respondents cannot withhold payment for admittedly executed works on the ground of departmental non-compliance with tendering, approval, sanction, or codal formalities.

It also directed

The impugned order dated 18.03.2025 is quashed. The respondents are directed to release ₹21,22,200 to the petitioner with interest at 9% per annum from the date WP(C) No. 717/2023 was filed until actual payment. The Court did not grant the 18% penal interest sought. The petition is disposed of.

01Facts

The petitioner, a contractor, claimed payment for seven works executed in the Irrigation Division-II, Jammu: two modernization works on Jagtu Chak Minor of D-13 (₹10.38 lakh and ₹9.44 lakh) and five silt clearance and allied works on Khore Branch of D-II (aggregate ₹2.39 lakh), totalling ₹21.221 lakh.

¶ 2

The petitioner had earlier approached this Court in WP(C) No. 717/2023, which was disposed of by order dated 05.04.2023 with directions.

¶ 1

Respondent No. 3 rejected the claim by order dated 18.03.2025, which is impugned here.

¶ 1, 3

The rejection rested on the absence of a tendering process, administrative approval, technical sanction, an approved plan, and funds at the time of execution.

¶ 3

The respondents stated that the Chief Engineer approved Works 1 and 2 without codal formalities, and that Works 3 to 7 were executed departmentally without codal formalities.

¶ 3

The respondents further stated that the erring officials had been identified and action was being initiated.

¶ 3

The respondents did not dispute that the works were executed.

¶ 5

The petitioner sought release of ₹21,22,200 with 18% penal interest.

¶ 1

02Issues

i.1. Whether the respondents can refuse payment for admittedly executed works on the ground of absent tendering, administrative approval, technical sanction, approved plan, or funds, which are departmental responsibilities.

¶ 5 · ¶ 7

ii.2. Whether a contractor who executed works at the department's instance can be denied payment for non-compliance with codal formalities, or be held responsible for them.

¶ 6, 8, 9

iii.3. Whether the impugned order dated 18.03.2025 is sustainable, and what relief is appropriate.

¶ 10

03Law Applied

The Court applied no specific statutory provision; the respondents' reference to the J&K CSR Rules was made only as an allegation of misconduct against officials.

¶ 3

In Chief Engineer PMGSY JKRRDA Jammu & Ors. v. M/s C and Z Associates (JV), LPA No. 73/2025, the Division Bench held that a contractor is unlikely to execute work on his own without being asked by officials, so where execution is not denied and the objection rests only on lack of administrative approval or tendering, the department is obliged to clear the liability.

¶ 8

In Union Territory of J&K v. Sanjeev Kumar, 2021 Legal Eagle (J&K) 110, it was held that a contractor need not verify jurisdiction or refuse work merely because it was not put to open tender.

¶ 8

Responsibility for following codal procedure rests with the departments, not the contractor, and once work is executed, the department cannot refuse release on non-compliance with codal formalities.

¶ 7, 9

04Reasoning

The Court first observed that the execution of the works was undisputed and that each ground cited for rejection (tendering, contract allotment, administrative approval, technical sanction, approved plan, funds) was a departmental responsibility.

¶ 5

Regarding Works 1 and 2, the Chief Engineer's approval was alleged to be defective, but the Court held that this defect could not be used to deny payment once the works were executed.

¶ 7

Rejecting the respondents' contention that the petitioner knew the approval requirements, the Court applied the Division Bench reasoning in C and Z Associates and Sanjeev Kumar to hold that the contractor cannot shift the departmental responsibility to itself but also cannot be left unpaid.

¶ 6, 8, 10

The Court criticised the routine denial of genuine contractor claims on codal grounds and noted that no departmental action had been shown despite eight years having elapsed.

¶ 9

Since the works were admittedly executed, the petitioner "cannot be left high and dry".

¶ 10

05Holding

The respondents cannot withhold payment for admittedly executed works on the ground of departmental non-compliance with tendering, approval, sanction, or codal formalities.

¶ 7, 8, 9

The impugned order dated 18.03.2025 is quashed. The respondents are directed to release ₹21,22,200 to the petitioner with interest at 9% per annum from the date WP(C) No. 717/2023 was filed until actual payment. The Court did not grant the 18% penal interest sought. The petition is disposed of.

¶ 1, 10, 11
Jammu and Kashmir High Court

Original Court PDF

NEHAL SINGH MANHASvsUT OF J AND K TH. COMMISSIONER SECRETARY, P.H.E., IRIGATION AND FLOOD CONTROL, JAMMU AND OTHERS

Jammu and Kashmir High Court · November 23, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in