Delhi High CourtArbitration and MediationContract Law

Existence of Valid Arbitration Agreement is a Foundational Jurisdictional Precondition for Granting Interim Measures under Section 9.

Midpoint Commodeal Private Limitedv.Fidatocity Homes Private Limited & Ors.

Existence of Valid Arbitration Agreement is a Foundational Jurisdictional Precondition for Granting Interim Measures under Section 9.. Midpoint Commodeal Private Limited vs Fidatocity Homes Private Limited & Ors.. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Petitioner established the existence of a valid and binding arbitration agreement under Section 7 of the A&C Act as a prerequisite for seeking interim measures under Section 9.

The court held

The Court held that the Petitioner failed to establish a valid, concluded, and enforceable arbitration agreement under Section 7 of the A&C Act.

It also directed

Consequently, the petition under Section 9 was held to be not maintainable and was dismissed.

The court clarified that the Petitioner remains at liberty to pursue other civil or monetary remedies, as no opinion was expressed on the merits of the underlying financial claim.

01Facts

The Petitioner (Midpoint) filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 (“A&C Act”), seeking an interim order for the Respondents to deposit ₹15.30 crore or, alternatively, an injunction against alienating land in Gurugram.

¶ 1-2

The Petitioner claimed the amount was infused as an unsecured loan and share purchase consideration based on draft Share Purchase Agreements (SPA) and Shareholders’ Agreements (SHA) exchanged in August 2024.

¶ 8f-8i

While the draft SHA contained an arbitration clause, none of the definitive documents were ever signed.

¶ 8j, 13

Respondents contested maintainability, arguing that the funds were part of a different transaction and that no concluded contract or arbitration agreement ever existed.

¶ 9-14

02Issues

i.1. Whether the Petitioner established the existence of a valid and binding arbitration agreement under Section 7 of the A&C Act as a prerequisite for seeking interim measures under Section 9.

¶ 30-31

ii.2. Whether an arbitration agreement can be inferred from unexecuted drafts and WhatsApp communications where commercial negotiations are ongoing.

¶ 34, 40

03Law Applied

The court primarily applied Section 7 of the A&C Act, which requires an arbitration agreement to be in writing and reflects a record of agreement.

¶ 35

It integrated principles from the Indian Contract Act, 1872, specifically Section 2 (proposal and acceptance) and Section 10/13 regarding consensus ad idem (meeting of minds) as the bedrock of any enforceable agreement.

¶ 36-38

The court relied on Kuber Mart Global Hub (P) Ltd. v. Kuber Mart Industries (P) Ltd. to establish that Section 9 jurisdiction is ancillary to a valid arbitration agreement.

¶ 33

It further distinguished Trimex International v. Vedanta and Glencore International AG v. Shree Ganesh Metals, noting that while signatures aren't mandatory, there must be unequivocal conduct signifying acceptance of terms.

¶ 45, 65-67

Provisions in the judgment · 7 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 7Section 9Section 11Section 45

Indian Contract Act, 1872 Section 2Section 10Section 13

04Reasoning

The court reasoned that for Section 9 jurisdiction to be invoked, a prima facie existence of an arbitration agreement must be shown.

¶ 32

In this case, the Petitioner’s own pleadings admitted that negotiations were ongoing as late as September/October 2025, with the Petitioner still requesting the "execution" of the SPA and SHA.

¶ 49-51

The court found that mere exchange of drafts—where modifications were still being suggested—does not constitute a concluded contract.

¶ 43

It rejected the Petitioner’s argument that the arbitration clause in the SHA survived independently, noting that the doctrine of separability cannot create an agreement where consensus ad idem on the substantive transaction (and the documents containing the clause) was never reached.

¶ 60-63

Unlike Glencore, where parties performed duties under a finalized contract, here the transfer of funds occurred before the drafts were even circulated, indicating the money was not moved pursuant to the disputed arbitration clause.

¶ 68-72

05Holding

The Court held that the Petitioner failed to establish a valid, concluded, and enforceable arbitration agreement under Section 7 of the A&C Act.

¶ 77

Consequently, the petition under Section 9 was held to be not maintainable and was dismissed.

¶ 78-79

The court clarified that the Petitioner remains at liberty to pursue other civil or monetary remedies, as no opinion was expressed on the merits of the underlying financial claim.

¶ 80
Delhi High Court

Original Court PDF

Midpoint Commodeal Private LimitedvsFidatocity Homes Private Limited & Ors.

Delhi High Court · May 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment