01Facts
The Appellant, a sole proprietorship, worked as a sub-contractor for main contractors M/s UB Engineering Ltd. and M/s Reacon Engineers India Pvt. Ltd. on two NTPC projects, providing erection, installation and construction services classifiable under Works Contract Services.
¶ 2Receipts were Rs. 17,43,000 from UB Engineering (2016-17) and Rs. 1,53,84,708 plus Rs. 10,65,259 from Reacon (2016-17 and April-June 2017).
¶ 2, 2.1The taxable value adopted in the demand (Rs. 2,27,28,285) exceeded the Form 26AS receipts (Rs. 1,81,92,967) by Rs. 45,35,318.
¶ 2.2The Appellant contended it bona fide believed the main contractors had discharged service tax on the entire contract value, as shown by bills mentioning service tax.
¶ 2.3The Department issued a Show Cause Notice dated 07/08.10.2021 proposing a demand of Rs. 34,09,243 with interest and penalties under Sections 78, 77(1) and 77(2) of the Finance Act, 1994.
¶ 3The Adjudicating Authority confirmed the demand and penalties.
¶ 4The Commissioner (Appeals) upheld the order, prompting the present appeal.
¶ 4The SCN was issued after the 30-month period for the three return periods in question, between 1 year 5 months and 2 years 5 months beyond it.
¶ 5, tableThe Appellant's counsel conceded the sub-contractor status and the bona fide belief.
¶ 602Issues
i.1. Whether the extended period of limitation under the proviso to Section 73(1) of the Finance Act, 1994 can be invoked to demand service tax from a sub-contractor where the main contractor has discharged service tax on the full contract value, and the sub-contractor held a bona fide belief of non-liability.
¶ 5, 9ii.2. Whether the penalties imposed under Sections 77 and 78 can be sustained once the extended-period demand fails.
¶ 10, 12 of the quoted Hari & Co. order03Law Applied
The proviso to Section 73(1) of the Finance Act, 1994 permits recovery beyond the normal period only where there is suppression of facts, misstatement, fraud, collusion, or intent to evade tax.
¶ 9Section 73(6) applies for the relevant date of limitation, and Section 78 applies for penalties.
¶ 5, table · ¶ 3Melange Developers Pvt. Ltd. (Tri.-LB, 2019) holds that a sub-contractor is independently liable to pay service tax irrespective of whether the main contractor has paid it, and that Master Circular No. 96/7/2007-ST overrides earlier circulars.
¶ 7, 9.1, 9.3Where the sub-contractor's liability was unsettled until Melange and no suppression is shown, the extended period cannot be invoked, as laid down in Hari & Co. (CESTAT Chennai, 2023), DGP Steel Star Engg. (CESTAT Kolkata, 2024), Vinoth Shipping Services (2021), Synergy Engineers Group (2023) and Vishal Engineering Co. (2023).
¶ 9.2–9.4, 10Provisions in the judgment · 4
Finance Act, 1994 Section 73Section 75Section 78Section 77
04Reasoning
The Court first accepted that the Appellant's liability as a sub-contractor was contested before Melange (decided 23.05.2019), which settled the law only after the entire disputed period.
¶ 9.1Given these conflicting Tribunal decisions, the Court held that the Appellant's belief it was not liable was plausible and bona fide, and could not be doubted.
¶ 9The Court found no material showing wilful suppression, delay in registration, or non-filing of returns with intent to evade tax.
¶ 9.1Following Hari & Co., the Court treated the main contractor's communications and its collection of tax from the client as the reason the Appellant believed tax was remitted, and found no evidence of mala fides on the Appellant's part.
¶ 9.2Applying DGP Steel Star and Vinoth Shipping, the Court held that the extended period could not be sustained on this record.
¶ 9.3, 9.4Because the demand rested on the extended period, the Court set it aside on limitation alone without deciding the merits of the sub-contractor's liability.
¶ 10The Court did not separately discuss the Notification 25/2012 exemption argument or the normal-period demand.
¶ 7, 1005Holding
The extended period of limitation could not be invoked against the sub-contractor because the Appellant's bona fide belief, arising from conflicting judicial positions before Melange, negated any suppression or intent to evade.
¶ 9, 10The impugned order is set aside and the appeal is allowed with consequential relief, if any, in accordance with law. The order does not expressly state whether a normal-period demand survives, or address the penalties under Section 78 separately; the penalty set-aside follows from the extended-period holding.
¶ 10, 12 of the quoted Hari & Co. orderOriginal Court PDF