Gurgaon Plot Buyer’s Specific-Performance Decree Stands After P&H HC Finds She Was Ready Despite Seller’s Refund Offer

(O&M) Sangeeta Malhotra Etc.v.Rama Kansal And Ors.

Gurgaon Plot Buyer’s Specific-Performance Decree Stands After P&H HC Finds She Was Ready Despite Seller’s Refund Offer. (O&M) Sangeeta Malhotra Etc. vs Rama Kansal And Ors.. Punjab and Haryana High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether time was of the essence of the agreement to sell, such that failure to complete the transfer by 31 October 1993 defeated the claim for specific performance

The court held

The High Court found no perversity in the concurrent findings of the courts below.

It also directed

It upheld the decree for specific performance and dismissed the regular second appeal; pending miscellaneous applications were disposed of accordingly.

01Facts

Smt. Rama Kansal sued for specific performance of an agreement to sell dated 2 August 1993, under which Smt. Sangeeta Malhotra, through her mother and attorney, agreed to transfer a plot for Rs. 7,78,596.

pp. 4–6, 18–19

The agreement fixed 31 October 1993 as the date for transfer and provided for interest at 24% per annum in the event of either party’s default; Rs. 78,596 was paid as earnest money

pp. 4–6, 18–19

The trial court decreed specific performance, and the first appellate court affirmed that decree

pp. 9–10, 16–17

During the second appeal, subsequent purchasers, M/s Uni Developers and its partners, were impleaded as appellants

pp. 2–3, 16–17

They challenged, among other things, the findings on time being of the essence and the plaintiff’s readiness and willingness

pp. 10–13

02Issues

i.Whether time was of the essence of the agreement to sell, such that failure to complete the transfer by 31 October 1993 defeated the claim for specific performance

pp. 10–11, 18–19

ii.Whether the plaintiff had continuously been ready and willing to perform her part of the agreement

pp. 11–13, 19–21

iii.Whether the subsequent purchasers could defeat the decree by challenging the plaintiff’s readiness and willingness or asserting their status as bona fide purchasers

pp. 13–14, 17–18, 21

03Law Applied

The court considered the agreement as a whole: a stipulated date for performance must be read alongside any contractual term addressing the consequences of delay or default.

pp. 18–19

Here, the agreement provided for interest at 24% per annum in the event of default, which the court found inconsistent with treating the stated date as an inflexible deadline

pp. 18–19

In a specific-performance claim, the plaintiff’s readiness and willingness are assessed from the parties’ conduct and the evidence, including steps taken to arrange the balance consideration

pp. 19–21

The appellants relied on *U.N. Krishnamurthy (Since Deceased) through LRs v. A.M. Krishnamurthy*, 2022 SCC OnLine SC 840, for the requirement to prove continuing readiness and willingness, including availability of funds; the judgment records that submission but does not cite the decision as the basis of its final reasoning

p. 11

The court also applied the principle of lis pendens to the subsequent transfer

p. 21

Provisions in the judgment · 1 · Linked ones open on LawLens

Code of Civil Procedure, 1908 Section 151

04Reasoning

The court read the deadline clause together with the 24% interest clause and concluded that the agreement contemplated consequences for delay rather than making 31 October 1993 an absolute cut-off

pp. 18–19

It found that the plaintiff’s correspondence calling on the vendor to complete the transaction, evidence of bank drafts and arrangements for the balance consideration, and the vendor’s notice offering to return the earnest money supported the finding that the plaintiff was ready and willing, while the vendor had not taken positive steps to complete the transfer

pp. 19–21

The subsequent purchasers acquired their interest during the litigation and could not rely on that transfer to displace the decree; the court also observed that they were not parties to the original agreement or proceedings before the lower courts

pp. 17–18, 21

05Holding

The High Court found no perversity in the concurrent findings of the courts below.

pp. 21–22

It upheld the decree for specific performance and dismissed the regular second appeal; pending miscellaneous applications were disposed of accordingly.

pp. 21–22
Punjab and Haryana High Court

Original Court PDF

(O&M) Sangeeta Malhotra Etc.vsRama Kansal And Ors.

Punjab and Haryana High Court · November 02, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment