Delhi High Court

High Court Enforces Undertaking to Complete Construction Under Arbitration Act Section 17 Order and Grants Site Access

Bvm Engineering Industries Limited vs Imperia Heights Private Limited & Anr.

Delhi High CourtJUDGMENT: July 13, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner filed a contempt petition alleging wilful disobedience of an interim order dated 24th June 2025, passed by a Sole Arbitrator under Section 17 of the Arbitration and Conciliation Act, 1996.

Source reference: para. 1

The Arbitrator had directed the Respondents to resume re-development and construction at the subject site per the Principal Collaboration Agreement.

Source reference: para. 3

Despite the High Court subsequently noting specific timelines for work in an order dated 25th February 2026, the Petitioner contended that the Respondents failed to comply.

Source reference: paras. 5, 6, 9

The Respondents filed an affidavit on 11th July 2026 admitting the delay but stating that the building structure was complete and full completion would occur by March 2027.

Source reference: paras. 7, 10

Disputes also arose regarding the Petitioner’s access to the site.

Source reference: para. 11
02

Issues

1. Whether the Respondents committed wilful disobedience of the Court’s directions and the Arbitrator's Section 17 order regarding construction timelines.

Source reference: para. 6, 9

2. Whether the Petitioner, as a co-owner, is entitled to access the construction site without interfering with the ongoing redevelopment.

Source reference: paras. 11–12
03

Law Applied

The court exercised its jurisdiction under the Contempt of Courts Act, 1971, to ensure compliance with judicial orders and interim measures granted under Section 17 of the Arbitration and Conciliation Act, 1996.

Source reference: para. 1

The court relied on the principle of "holding a party bound to an undertaking" given to the court to ensure the time-bound performance of contractual obligations that have been reinforced by judicial orders.

Source reference: paras. 13–14

It also balanced the property rights of a co-owner to access premises with the necessity of non-interference in construction activities.

Source reference: paras. 15–16
04

Reasoning

The Court observed that although the Respondents failed to meet the initial timelines noted in the order dated 25th February 2026, they submitted an affidavit affirming that the primary structure was complete.

Source reference: paras. 9–10

The Court accepted the Respondents' fresh undertaking to complete the entire project by 31st March 2027, thereby substituting the previous failed timelines with a final terminal date to which the Respondents are now legally bound.

Source reference: paras. 13–14

Regarding the site access dispute, the Court noted the Petitioner's status as a co-owner and the Respondents' claim of interference; it resolved this by granting a right of access while simultaneously imposing a restrictive injunction against the Petitioner to prevent disruption of the works.

Source reference: paras. 15–16
05

Holding

The Court disposed of the contempt petition by binding the Respondents to their undertaking to complete all redevelopment work by 31st March 2027 in accordance with the Collaboration and Supplementary Agreements.

The Court specifically directed that the Petitioner be granted access to the premises at A-20, Mohan Cooperative Industrial Estate, New Delhi, subject to the condition that the Petitioner shall not interfere in the construction work being carried out by the Respondents.

Source reference: para. 15, 16
Delhi High Court

Original Court PDF

Bvm Engineering Industries LimitedvsImperia Heights Private Limited & Anr.

Delhi High Court · July 13, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment