Facts
The petitioner provided security and surveillance services for mobile-tower sites.
Source reference: no citationUnder the Service Agreement dated 18 February 2019, the petitioner was to provide surveillance services at 978 sites in Maharashtra at ₹12,152 per site per month, under Schedule II.
Source reference: pp. 2, 9–11The agreement permitted the respondent to alter the scope of work or number of sites only through a written intimation under Clause 1.6.
Source reference: p. 9Following Memoranda of Understanding concerning manpower optimisation, the respondent made payments based on progressively fewer sites from July 2019 onwards.
Source reference: pp. 12–15The respondent did not, however, issue a written communication formally reducing the number of sites.
Source reference: pp. 12–15The petitioner claimed unpaid service charges, interest, damages, GST, differential minimum wages and gratuity.
Source reference: no citationThe arbitral tribunal rejected the claims, holding, inter alia, that the petitioner had failed to prove that services were rendered at all 978 sites.
Source reference: pp. 3–5The petitioner challenged the award dated 10 August 2023 under Section 34 of the Arbitration and Conciliation Act, 1996, contending that the arbitrator had wrongly shifted the burden of proof and had disregarded Clause 1.6 and Schedule II of the Service Agreement.
Source reference: pp. 5–8Issues
1. Whether the respondent had validly reduced the number of Maharashtra sites from 978 by invoking Clause 1.6 of the Service Agreement, despite not issuing written intimation to the petitioner?
Source reference: pp. 13–15, paras. 14–182. Whether the arbitrator erred in placing upon the petitioner the burden of proving that surveillance services were rendered at all 978 sites, instead of requiring the respondent to prove the alleged reduction in sites?
Source reference: pp. 15–18, para. 223. Whether the MoUs relating to manpower optimisation, the reduced invoices and the subsequent agreements established waiver or estoppel against the petitioner’s claim for payment for 978 sites?
Source reference: pp. 17–22, paras. 23–334. Whether the arbitral award suffered from patent illegality under Section 34 of the Arbitration and Conciliation Act, 1996 by disregarding the contractual terms and containing contradictory findings?
Source reference: pp. 22–25, paras. 34–35Law Applied
The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, under which a domestic arbitral award may be set aside for patent illegality, including where the arbitrator ignores vital evidence, adopts a perverse or impossible interpretation, or fails to act in accordance with the contract.
Source reference: pp. 22–25, para. 34Section 28(3) requires the arbitral tribunal to take into account the terms of the contract.
Source reference: pp. 22–25, para. 34An arbitrator, being a creature of contract, must decide within the contractual framework; failure to act in accordance with express contractual terms constitutes patent illegality, as held in Indian Oil Corporation Ltd. v. Shree Ganesh Petroleum Rajgurunagar, (2022) 4 SCC 463, State of Chhattisgarh v. Sal Udyog (P) Ltd., (2022) 2 SCC 275, and Bharat Coking Coal Ltd. v. Annapurna Construction, (2003) 8 SCC 154.
Source reference: pp. 23–25, para. 34The general evidentiary principle under Sections 101–102 of the Evidence Act, 1872 is that the party asserting a fact bears the burden of proving it; a negative burden cannot ordinarily be imposed on the opposing party.
Source reference: pp. 15–17, para. 22Sections 58, 91 and 92 of the Evidence Act do not assist a party where the alleged admission is not conclusive and where the contractual issue must be determined from the agreement itself.
Source reference: pp. 17–18, paras. 23–25Waiver requires a conscious and intentional relinquishment of a known right, while estoppel requires a representation, reliance and alteration of position, as explained in Kalpraj Dharamshi v. Kotak Investment Advisors Ltd., (2021) 10 SCC 401, and Chhaganlal Keshavlal Mehta v. Patel Narandas Haribhai, (1982) 1 SCC 223.
Source reference: pp. 19–22, paras. 31–33Reasoning
Clauses 1.6 and 2.1, read with Schedule II, required payment for 978 Maharashtra sites at the agreed rate unless the respondent reduced the sites through written intimation.
Source reference: pp. 13–15, paras. 13–18The Court found that the respondent admittedly issued no such written communication.
Source reference: pp. 13–15, paras. 13–18The MoUs dealt with manpower optimisation and did not mention any reduction in the number of sites; payment of ₹60,000 per manpower transition concerned settlement with removed employees and did not alter the consideration payable under the Service Agreement.
Source reference: pp. 14–15, paras. 18, 21The respondent’s assertion that the petitioner had provided services only at the sites reflected in the reduced invoices was an affirmative assertion that the respondent had to establish.
Source reference: pp. 15–18, paras. 19–25The arbitrator therefore erred in shifting the burden to the petitioner to prove performance at all 978 sites, particularly when the contractual power to reduce the sites belonged to the respondent and had not been exercised in the prescribed manner.
Source reference: pp. 15–18, paras. 19–25The reduced invoices did not conclusively waive the petitioner’s contractual entitlement.
Source reference: pp. 19–22, paras. 29–33Nor did the execution of subsequent agreements, without insisting on immediate payment of earlier dues, establish conscious waiver or the elements of estoppel.
Source reference: pp. 19–22, paras. 29–33The award was additionally internally inconsistent: it recognised that payment was to be made on an on-site basis, yet relied on manpower optimisation and an email suggesting payment based on retained manpower.
Source reference: pp. 22–25, paras. 28, 34–35By disregarding the express contractual mechanism for reducing sites and by shifting the burden of proof, the arbitrator acted contrary to the Service Agreement.
Source reference: pp. 22–25, paras. 28, 34–35This amounted to patent illegality warranting interference under Section 34.
Source reference: pp. 22–25, paras. 28, 34–35Holding
The Court held that the respondent failed to prove any valid reduction of the 978 Maharashtra sites under Clause 1.6; the MoUs were not written intimations reducing the sites, and the petitioner’s reduced invoices did not establish waiver or estoppel.
The arbitrator wrongly placed the burden on the petitioner and adopted findings contrary to the contractual payment structure.
Source reference: p. 25, para. 35The award dated 10 August 2023 was therefore held to be patently illegal and was set aside.
Source reference: p. 26, para. 36The petition was allowed and all pending applications were disposed of.
Source reference: p. 26, para. 36Original Court PDF
B4S Solutions Private LimitedvsAtc Telecom Infrastructre Pvt. Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
