Jharkhand High Court
Arbitration and MediationCivil Procedure and Evidence

Jharkhand High Court upholds Delhi as arbitration seat after State’s prolonged silence and participation in proceedings

ROAD CONSTRUCTION DEPARTMENT , GOVERNMENT OF JHARKHAND,THROUGH ASHISH KUMAR SINHA vs RAMKY INFRASTRUCTURE LIMITED

Jharkhand High CourtJUDGMENT: August 20, 20264 MIN READSOURCE JUDGMENT
Jharkhand High Court upholds Delhi as arbitration seat after State’s prolonged silence and participation in proceedings. ROAD CONSTRUCTION DEPARTMENT , GOVERNMENT OF JHARKHAND,THROUGH ASHISH KUMAR SINHA vs RAMKY INFRASTRUCTURE LIMITED. Jharkhand High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Road Construction Department, Government of Jharkhand, entered into an agreement with Ramky Infrastructure Limited on 22 September 2010 for rehabilitation and upgradation of the Barhet-Sahebganj section of the Govindpur-Sahebganj Jharkhand State Road Project.

Source reference: p.2

Clause 20.6(b)(iii) of the agreement provided that the arbitration proceedings would be held at the Conference Building, Mantralaya, Ranchi, Jharkhand, with English as the language of arbitration.

Source reference: p.2

In Procedural Order No. 1 dated 22 September 2023, passed in the presence of the parties’ representatives, the tribunal fixed Delhi as the seat of arbitration and stated that the venue would be decided with the parties from time to time.

Source reference: p.2

The State did not immediately challenge this determination and continued participating in the arbitration for more than two and a half years.

Source reference: pp.4–5, 8–10

Ramky Infrastructure thereafter filed a petition under Section 29A of the Arbitration and Conciliation Act, 1996 before the Delhi High Court for extension of the tribunal’s mandate.

Source reference: pp.3–4

The Delhi High Court nevertheless extended the tribunal’s mandate, observing that Delhi was, at that stage, the seat of arbitration.

Source reference: pp.3–4

The State subsequently filed an application under Section 16 of the Arbitration Act challenging the tribunal’s determination of Delhi as the seat.

Source reference: p.4

The tribunal rejected the application through Procedural Order No. 30 dated 8 May 2026. The State challenged that order under Article 226 of the Constitution before the Jharkhand High Court.

Source reference: p.4
02

Issues

Whether the arbitral tribunal could fix Delhi as the seat of arbitration when the agreement specified Ranchi as the venue of arbitration but did not expressly designate the seat.

Source reference: pp.4–6, 8–9

Whether the State had waived or acquiesced in its objection to Delhi being treated as the seat by participating in the arbitration without timely objection.

Source reference: pp.8–10

Whether the High Court should interfere under Article 226 with the arbitral tribunal’s order rejecting the State’s jurisdictional objection under Section 16 of the Arbitration Act.

Source reference: pp.4–5, 10
03

Law Applied

The Court applied Section 20 of the Arbitration and Conciliation Act, 1996, under which parties may agree on the place of arbitration; failing such agreement, the tribunal may determine it having regard to the circumstances and convenience of the parties, while hearings or meetings may be held elsewhere under Section 20(3).

Source reference: p.5

It relied on Bharat Aluminium Co. v. Kaiser Aluminium Technical Services Inc., (2012) 9 SCC 552, and Bharat Broadband Network Ltd. v. United Telecoms Ltd.—as cited in the judgment through the distinction discussed in BALCO—and BBR (India) Pvt. Ltd. v. S.P. Singla Constructions Pvt. Ltd., (2023) 1 SCC 693, for the principle that the seat is the juridical home of the arbitration, determines the supervisory court and procedural law, remains static once fixed, and is distinct from the movable venue.

Source reference: pp.6–8

Section 4 of the Arbitration Act was applied to hold that a party aware of non-compliance with an arbitrational requirement, but proceeding without timely objection, is deemed to have waived its right to object.

Source reference: p.9

The Court relied on Bharat Sanchar Nigam Ltd. v. Motorola India Pvt. Ltd., (2009) 2 SCC 337, on waiver by failure to object without undue delay.

Source reference: p.9

The Court relied on Tarini Prasad Mohanty v. Sunflag Iron & Steel Co. Ltd., 2026 SCC OnLine SC 973, for the proposition that writ jurisdiction should not be used to examine the merits of an order passed under Section 16.

Source reference: p.10
04

Reasoning

The Court distinguished between the contractual venue at Ranchi and the juridical seat of arbitration.

Source reference: pp.5–6, 8

Since the agreement did not expressly designate the seat or confer exclusive jurisdiction on any court, the tribunal was competent under Section 20 to determine the seat.

Source reference: pp.5–6, 8

The tribunal fixed Delhi as the seat in its first procedural order in the presence of the parties, and the State continued participating in the proceedings without raising a timely challenge.

Source reference: p.8

The State also appeared before the Delhi High Court in the Section 29A proceedings, accepted the extension of the tribunal’s mandate, and did not challenge that order despite the court’s observation that Delhi was the seat.

Source reference: p.8

This conduct was held to constitute acquiescence and waiver under Section 4.

Source reference: pp.9–10

The Court further held that the challenge arose from an order under Section 16 and that the statutory remedy under Section 34 remained available; therefore, writ interference was unwarranted, particularly where the petition effectively sought adjudication of the merits of the tribunal’s jurisdictional determination.

Source reference: p.10
05

Holding

The Court held that Delhi validly operated as the seat of arbitration because the agreement specified only Ranchi as the venue and did not determine the seat.

In any event, the State had waived its objection by failing to challenge the tribunal’s determination without undue delay and by continuing with the arbitration.

Source reference: pp.8–10

The Court declined to interfere under Article 226 with Procedural Order No. 30 dated 8 May 2026, dismissed the writ petition, and disposed of any pending interlocutory applications.

Source reference: p.10
06

Acts & Sections Cited

5 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19965

Jharkhand High Court

Original Court PDF

ROAD CONSTRUCTION DEPARTMENT , GOVERNMENT OF JHARKHAND,THROUGH ASHISH KUMAR SINHAvsRAMKY INFRASTRUCTURE LIMITED

Jharkhand High Court · August 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment