Karnataka High CourtArbitration and MediationConstruction Law

Karnataka HC Appoints Ex-Judge As Sole Arbitrator In Contractor's Dispute With Housing Board Over Sedam Mini Vidhana Soudha Payment Claims

M/S KMV PROJECTS LIMITEDv.KARNATAKA HOUSING BOARD

Karnataka HC Appoints Ex-Judge As Sole Arbitrator In Contractor's Dispute With Housing Board Over Sedam Mini Vidhana Soudha Payment Claims. M/S KMV PROJECTS LIMITED vs KARNATAKA HOUSING BOARD. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the court should appoint a Sole Arbitrator under Section 11(5) and (6) of the Arbitration and Conciliation Act, 1996, where a valid arbitration clause exists, the petitioner has invoked it by Section 21 notice, and the respondent has not responded and has no objection.

The court held

The court held that a Sole Arbitrator was required to adjudicate the disputes under the Construction Agreement dated 31.03.2017.

It also directed

The CMP is allowed. Hon'ble Shri Justice A.N. Venugopala Gowda, former Judge of the High Court of Karnataka, is appointed Sole Arbitrator to be conducted at the Arbitration and Conciliation Centre (Domestic & International), Bengaluru, under its rules. All claims and contentions of both parties are left open. The Registry is directed to e-mail the order to the Centre and the arbitrator, and to return original documents after retaining photocopies. The parties are directed to appear before the Director, Arbitration and Conciliation Centre, Bengaluru, on 04.11.2026 at 11:30 a.m.

01Facts

The petitioner, a construction and infrastructure company, was the successful bidder under a tender dated 17.08.2016 for construction of a Mini Vidhana Soudha at Sedam Taluk, Kalaburagi District.

pp. 2–3

A Letter of Acceptance issued on 28.02.2017 and a Construction Agreement was executed on 31.03.2017.

pp. 2–3

The Notice to Proceed issued on 13.04.2017, but possession of the site was delivered only on 01.06.2017.

p. 3

The petitioner alleges delay in site handover, increase in quantities, revision of estimates and delayed payments.

p. 3

Time was extended up to 31.12.2019, and the petitioner asserts completion within that period.

p. 3

Certain claims (RA bills, price adjustment, escalation, additional quantities, GST and other dues) allegedly remain unpaid, and the respondent took possession of the completed project only on 27.03.2024, which allegedly caused additional security and maintenance expenditure.

pp. 3–4

Disputes arose, and the petitioner issued a notice under Section 21 of the Act dated 10.02.2026, with a Corrigendum dated 25.03.2026, both duly served.

p. 4

Clause 4 of the Special Conditions of Contract (Clause 24) provides for a Sole Arbitrator appointed by agreement, failing which by an Appointing Authority; seat at Bangalore; and continuation of performance and payments during arbitration.

pp. 4–6

The respondent did not reply to the notice.

p. 6

At the hearing, the respondent's counsel stated it had no objection to appointment of a Sole Arbitrator, with all contentions left open.

p. 6

02Issues

i.1. Whether the court should appoint a Sole Arbitrator under Section 11(5) and (6) of the Arbitration and Conciliation Act, 1996, where a valid arbitration clause exists, the petitioner has invoked it by Section 21 notice, and the respondent has not responded and has no objection.

p. 2 · p. 6 / para. 6

ii.2. Whether the court should appoint a specific named arbitrator, seated at the Arbitration and Conciliation Centre, Bengaluru, leaving all claims and contentions open for the arbitrator.

pp. 6–7 / para. 7(b)–(c)

03Law Applied

Sections 11(5) and 11(6) of the Arbitration and Conciliation Act, 1996, which empower the High Court to appoint an arbitrator where the agreed procedure fails.

pp. 1–2 / para. 1

Section 21 of the Arbitration and Conciliation Act, 1996, which fixes commencement of arbitration upon receipt of a notice invoking the clause.

p. 4 / para. 3

Clause 4 (Clause 24) of the Special Conditions of Contract, which provides for a Sole Arbitrator by agreement or, failing agreement, by an Appointing Authority, with the seat at Bangalore and continuation of performance and payments during arbitration.

pp. 4–6 / para. 3

The order cites no precedent.

Provisions in the judgment · 2 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 11Section 21

04Reasoning

The court first confirmed the existence of an arbitration clause governing disputes arising under the Construction Agreement.

p. 6 / para. 6

It then found the clause was validly invoked, since the petitioner's Section 21 notice and Corrigendum were duly served and the respondent did not reply.

p. 4 · pp. 6 / para. 3–4, 6

The respondent's unconditional non-objection to a Sole Arbitrator, with all contentions reserved, removed any contest on appointment.

p. 6 / para. 5

On that basis, the court held that a Sole Arbitrator was required.

p. 6 / para. 6

The order does not record that the parties failed to agree on an arbitrator or that the Appointing Authority was approached, which the clause makes a precondition to appointment by the court.

p. 5 / para. 3, Clause 4.1(a)

The appointment therefore appears to rest on the respondent's consent rather than on a recorded default under the clause.

pp. 6 / para. 5–6

The court named a former High Court judge as sole arbitrator and fixed the Bengaluru Arbitration and Conciliation Centre as the forum, reserving all merits for the arbitrator.

pp. 6–7 / para. 7(b)–(c)

05Holding

The court held that a Sole Arbitrator was required to adjudicate the disputes under the Construction Agreement dated 31.03.2017.

p. 6 / para. 6

The CMP is allowed. Hon'ble Shri Justice A.N. Venugopala Gowda, former Judge of the High Court of Karnataka, is appointed Sole Arbitrator to be conducted at the Arbitration and Conciliation Centre (Domestic & International), Bengaluru, under its rules. All claims and contentions of both parties are left open. The Registry is directed to e-mail the order to the Centre and the arbitrator, and to return original documents after retaining photocopies. The parties are directed to appear before the Director, Arbitration and Conciliation Centre, Bengaluru, on 04.11.2026 at 11:30 a.m.

pp. 7 / para. 7(a)–(f)
Karnataka High Court

Original Court PDF

M/S KMV PROJECTS LIMITEDvsKARNATAKA HOUSING BOARD

Karnataka High Court · October 15, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment