Karnataka High CourtArbitration and MediationContract Law

Steel Contractor Loses ₹72 Lakh Minimum Wage Claim Against SAIL As Contract Has No Reimbursement Clause

PRAGATI METALLURGICAL SERVICESv.THE STEEL AUTHORITY OF INDIA LTD.,

Steel Contractor Loses ₹72 Lakh Minimum Wage Claim Against SAIL As Contract Has No Reimbursement Clause. PRAGATI METALLURGICAL SERVICES vs THE STEEL AUTHORITY OF INDIA LTD.,. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the appellant has made out any ground warranting interference with the arbitral award dated 16.09.2021 and the Commercial Court's judgment dated 30.01.2025 under the limited scope of Section 37 of the Arbitration and Conciliation Act, 1996.

The court held

The appellant had not shown any patent illegality or jurisdictional error warranting interference with the arbitral award dated 16.09.2021 in AC No. 136/2020 or the Commercial Court's judgment dated 30.01.2025 in Com.A.P. No. 5002/2023. A statutory obligation to pay revised minimum wages, absent an express contractual reimbursement term, does not create a contractual liability for the principal to reimburse the enhanced wages, and Section 37 review cannot re-weigh a plausible arbitral view.

It also directed

The appeal was dismissed as devoid of merit. The Commercial Court's judgment was affirmed, and no order was made as to costs.

01Facts

The appellant (Pragati), a contractor, was awarded a three-year work order (26.04.2016; term 01.05.2016 to 30.04.2019; value ₹8,95,51,250) by the respondent SAIL for finishing and related work at the Visvesvaraya Iron and Steel Plant, Bhadravati.

¶ 3

Condition 12(8) read with Clause 4.3 of the General Terms required the contractor to pay minimum wages as fixed by the appropriate Government from time to time.

¶ 4

After the Central Government's notified wage revisions (notably January 2017, about 40%), the appellant claimed reimbursement of ₹72,10,119 in enhanced wages, plus ₹26,70,280 as interest at 18%.

¶ 5–6

SAIL relied on the contract, its letter of 26.09.2017 (stating that Central Government notifications applied and that reimbursement was not available), and Clause 25 (arbitration).

¶ 7–9

The sole arbitrator (Hon. M.N. Dharwadkar, retd.) rejected the claim by award dated 16.09.2021 in AC No. 136/2020.

¶ 11–17

The Commercial Court dismissed the Section 34 challenge (Com.A.P. No. 5002/2023) by judgment dated 30.01.2025.

¶ 27–34

The appellant then filed this appeal under Section 13(1) of the Commercial Courts Act, 2015, read with Section 37(1) of the Arbitration and Conciliation Act, 1996.

¶ 35–36

02Issues

i.1. Whether the appellant has made out any ground warranting interference with the arbitral award dated 16.09.2021 and the Commercial Court's judgment dated 30.01.2025 under the limited scope of Section 37 of the Arbitration and Conciliation Act, 1996.

¶ 39

ii.2. Whether the contractual obligation to pay revised statutory minimum wages carries a corresponding contractual liability on SAIL to reimburse enhanced wages absent an express reimbursement clause.

¶ 42–44

iii.3. Whether the reimbursement of enhanced statutory bonus, the RW.1 evidence, and the legal notice/reply of 2018 amounted to an admission of liability for enhanced wages.

¶ 45–48

03Law Applied

Section 37 of the Arbitration and Conciliation Act, 1996 confines appellate review to whether the Section 34 court acted within its limits, read with Section 34(2A) on patent illegality.

¶ 49–50, 59

MMTC Ltd. v. Vedanta Ltd. (2019) 4 SCC 163: the appellate court cannot independently assess the merits of an award and must be cautious in disturbing concurrent findings.

¶ 50

Konkan Railway Corporation Ltd. v. Chenab Bridge Project Undertaking (2023) 9 SCC 85: a merely possible alternative view does not justify interference.

¶ 51

Punjab State Civil Supplies Corpn. Ltd. v. Sanman Rice Mills (2024 SCC OnLine SC 2632): interference is limited to cases where the Section 34 court failed to exercise, or exceeded, its jurisdiction.

¶ 52

Bombay Slum Redevelopment Corporation v. Samir Narain Bhojwani (2024) 7 SCC 218 and Somdatt Builders-NCC-NEC (JV) v. NHAI (2025) 6 SCC 757: restraint regarding contractual interpretation.

¶ 53

Jan De Nul Dredging India v. Tuticorin Port Trust (2026) 3 SCC 186: the confined jurisdiction under Section 37.

¶ 53

Saisudhir Energy Ltd. v. NTPC Vidyut Vyapar Nigam Ltd. (2026 SCC OnLine SC 125): substituting a plausible view under Section 37 is impermissible.

¶ 55

A statutory wage obligation does not, by itself, create a contractual reimbursement obligation.

¶ 44, 49

Provisions in the judgment · 3 · Linked ones open on LawLens

Commercial Courts Act, 2015 Section 13

Arbitration and Conciliation Act, 1996 Section 34Section 37

04Reasoning

The Court held that the appellant's central claim is contractual, not statutory. Condition 12(8) and Clause 4.3 required the contractor to pay minimum wages as revised from time to time, but the work order contained no reimbursement or escalation clause.

¶ 43–44

Since the appellant had accepted a fixed lump-sum consideration as lowest bidder, the Court found no perversity in the view that a statutory obligation to pay revised wages could not be converted into a liability of SAIL.

¶ 44

The bonus reimbursement under the letter of 20.09.2016 was treated as a discrete arrangement for a different liability and was not an admission extending to wages.

¶ 45–46

The RW.1 testimony on bonus knowledge did not establish any undertaking to pay enhanced wages.

¶ 47

The 2018 legal notice and SAIL's reply referring to Clause 25 were not an admission of monetary liability, and proof of actual disbursement did not establish contractual entitlement.

¶ 48–49

Applying Section 37 limits, the Court found that the Commercial Court had addressed each ground and that the appellant's arguments sought reappraisal of evidence and a different contractual interpretation, which was impermissible.

¶ 54, 56, 60

05Holding

The appellant had not shown any patent illegality or jurisdictional error warranting interference with the arbitral award dated 16.09.2021 in AC No. 136/2020 or the Commercial Court's judgment dated 30.01.2025 in Com.A.P. No. 5002/2023. A statutory obligation to pay revised minimum wages, absent an express contractual reimbursement term, does not create a contractual liability for the principal to reimburse the enhanced wages, and Section 37 review cannot re-weigh a plausible arbitral view.

¶ 44, 56, 59, 61

The appeal was dismissed as devoid of merit. The Commercial Court's judgment was affirmed, and no order was made as to costs.

¶ 61 · Order paras. 1–2
Karnataka High Court

Original Court PDF

PRAGATI METALLURGICAL SERVICESvsTHE STEEL AUTHORITY OF INDIA LTD.,

Karnataka High Court · September 29, 2026