In brief

The question

1. Whether, pending disposal of statutory appeals under Section 250 of the GBG Act where the Appellate Authority has not considered interim relief, the writ court should restrain the respondents from taking coercive measures against the petitioners' standing structures.

The court held

The petitions must be allowed in the limited sense that the respondents are restrained from taking coercive measures to dismantle or demolish the standing structures on the petitioners' respective properties during the pendency of the appeals.

It also directed

Any coercive measure is made subject to the final outcome of those appeals, and the petitioners are specifically directed not to change the nature of the properties by recommencing construction or otherwise. The petitions were disposed of accordingly. No finding was recorded on the merits of the construction violation, the revenue-entry entitlement, or the Appellate Authority's pending decision on interim relief.

01Facts

The petitioners own separate properties in Bengaluru. Each was served with a Confirmation Order under Sections 243(3)(e) and 244 of the Greater Bengaluru Governance Act, 2024 ("GBG Act") and filed appeals under Section 250 against those orders.

¶ 1

The proceedings under Section 243(3) were initiated on the ground that the petitioners commenced or completed construction without a sanctioned plan.

¶ 2

The petitioners do not assert that they hold a sanctioned plan. They contend that, after initiation of the proceedings, the authorities issued revenue entries in Form A (earlier Form B) for their properties, entitling them to apply for sanction, and that they have so applied.

¶ 2

The Appellate Authority called for records but did not consider the petitioners' prayer for interim stay of precipitative action pending appeal.

¶ 1 · ¶ 3

On instructions, petitioner in W.P. No. 35210/2026 has stopped construction for about one year, and petitioners in W.P. No. 35234/2026 have completed a residential structure of ground and first floors. Neither set of petitioners proposes to alter the nature of construction until the appeals are finally decided.

¶ 4

Respondents appeared through standing counsel.

¶ 4

02Issues

i.1. Whether, pending disposal of statutory appeals under Section 250 of the GBG Act where the Appellate Authority has not considered interim relief, the writ court should restrain the respondents from taking coercive measures against the petitioners' standing structures.

¶ 3 · ¶ 5

ii.2. Whether such protection can be granted subject to conditions that the petitioners not change the nature of the properties by recommencing construction or otherwise.

¶ 5

03Law Applied

The court exercised jurisdiction under Article 226 of the Constitution of India to grant interim protection in aid of pending statutory remedies.

¶ 1

The enforcement and confirmation framework of Sections 243(3)(e) and 244 of the GBG Act, under which the authorities may act against construction without a sanctioned plan, and the statutory appellate remedy under Section 250, which is the petitioners' forum for challenge.

¶ 1 · ¶ 2

The regulatory position that revenue entries in Form A may be relevant to a sanction application, though the petitioners did not claim a sanctioned plan.

¶ 2

The order cites no precedent and states no independent doctrinal test.

Provisions in the judgment · 3

Greater Bengaluru Governance Act, 2024 Section 243Section 244Section 250

04Reasoning

The court identified the core problem as the Appellate Authority's failure to rule on the interim-stay request before calling for records, creating a real risk of precipitate action before the appeals were decided.

¶ 1 · ¶ 3

Because the petitioners did not claim a sanctioned plan, the court did not examine the merits of the unauthorised-construction finding.

¶ 2 · ¶ 5

The court balanced the risk of irreversible demolition against the authorities' enforcement powers by relying on counsel's statements that construction had stopped or was complete and would not be altered during the appeals.

¶ 4

The court concluded that restraint on coercive measures was appropriate in these circumstances, provided any such measure remained subject to the final outcome of the appeals and the petitioners refrained from further construction. The order thus preserves the status quo rather than adjudicating legality.

¶ 5

05Holding

The petitions must be allowed in the limited sense that the respondents are restrained from taking coercive measures to dismantle or demolish the standing structures on the petitioners' respective properties during the pendency of the appeals.

¶ 5

Any coercive measure is made subject to the final outcome of those appeals, and the petitioners are specifically directed not to change the nature of the properties by recommencing construction or otherwise. The petitions were disposed of accordingly. No finding was recorded on the merits of the construction violation, the revenue-entry entitlement, or the Appellate Authority's pending decision on interim relief.

¶ 2 · ¶ 5
Karnataka High Court

Original Court PDF

SRI. SANJEEV. A. KURUPvsCHIEF COMMISSIONER

Karnataka High Court · November 17, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment