01Facts
The petitioners obtained a composite housing loan of ₹1 crore from the erstwhile Vijaya Bank, comprising ₹50 lakh for purchasing a site and ₹50 lakh for construction.
¶ 2–3Only the site-purchase component was disbursed.
¶ 2–3The loan sanction required construction to be completed within 36 months from the first drawal for the site, failing which the bank could charge commercial interest from the date of first release.
¶ 2–3, 7–8The petitioners did not construct, citing BDA-related litigation, the COVID-19 pandemic and other circumstances beyond their control; they sought to close the loan without commercial interest.
¶ 1, 5–6The bank demanded ₹17,43,906 as commercial interest for the period from 24 May 2018 to 31 January 2024.
¶ 1, 5–6The petitioners challenged the demand and sought consideration of their representations under Articles 226 and 227 of the Constitution.
¶ 102Issues
i.1. Whether the bank’s demand for commercial interest under the loan-sanction condition could be challenged and resolved in writ proceedings where the dispute arose from contractual obligations and involved disputed questions of fact.
¶ 8–10ii.2. Whether the petitioners’ reliance on Section 56 of the Indian Contract Act, 1872, to explain their failure to construct could be determined in the writ petition.
¶ 903Law Applied
Article 226 jurisdiction is discretionary; although the existence of a contractual dispute is not an absolute bar to writ jurisdiction, the Court may decline to exercise it where resolution requires determination of disputed facts and an appropriate alternative forum is available.
¶ 10Section 56 of the Indian Contract Act, 1872, was invoked by the petitioners in support of their contention that circumstances beyond their control made construction impossible; the Court did not determine the provision’s application to the case, observing that this required examination of the facts, the nature of the obligation and the contractual terms.
¶ 9The loan sanction’s express condition provided for commercial interest from the date of first release if construction was not completed within 36 months.
¶ 7–8Provisions in the judgment · 1 · Linked ones open on LawLens
Indian Contract Act, 1872 Section 56
04Reasoning
The Court found that the sanction memorandum expressly set a 36-month construction deadline and stipulated the consequence of non-compliance: commercial interest from the date of first release.
¶ 7–8Whether the BDA litigation, pandemic and other circumstances made performance impossible or merely delayed it, and whether Section 56 applied, required factual and contractual examination that the Court considered unsuitable for determination in these writ proceedings.
¶ 9Given the contractual nature of the dispute and the availability of an appropriate forum, the Court declined to exercise its writ jurisdiction.
¶ 1005Holding
The Court dismissed the writ petition without deciding the merits of the petitioners’ Section 56 contention or the underlying contractual dispute.
¶ 11It reserved liberty to the petitioners to approach the appropriate forum, including to raise their contention that circumstances beyond their control prevented construction.
¶ 11Original Court PDF