01Facts
The petitioners challenged the tender evaluation and the appellate authority’s orders dated 4 and 5 March 2026 concerning Packages 5, 14 and 23 issued by Bangalore Solid Waste Management Limited.
¶ 1–3They sought to set aside the appellate orders and the Tender Evaluation Committee’s proceedings, and to have the competing bidders’ eligibility and qualifications re-examined.
¶ 1–3For Package 5, they challenged the successful consortium’s use of credentials and alleged overlapping consortium participation; for Package 14, they challenged A.L. Satish Kumar’s selection; and for Package 23, they alleged that Sathya Construction was ineligible, including under Clause 2.2.13.
¶ 4–6, 12–18Petitioner No. 2 died during the proceedings; his Package 14 challenge concerned a bid made in his individual capacity.
¶ 13–1402Issues
i.1. Whether the declaration of the successful bidder for Package 5 was liable to be set aside for alleged improper use of credentials or participation in multiple consortiums.
¶ 4–11ii.2. Whether the challenge to the successful bidder for Package 14 could continue after the death of the petitioner who had submitted the individual bid.
¶ 12–14iii.3. Whether Sathya Construction was ineligible for Package 23 under Clause 2.2.13 or otherwise, such that its selection should be set aside.
¶ 15–25iv.4. Whether the appellate authority’s tender decisions disclosed grounds warranting judicial review under Article 226.
¶ 26–2703Law Applied
The Court applied Article 226 of the Constitution and the principle that judicial review of tender decisions is limited: the Court does not sit in appeal over the tendering or appellate authority’s decision and will interfere only where a decision is arbitrary, irrational, mala fide, or contrary to the tender conditions.
¶ 26Clause 2.2.13 of the tender conditions disqualified a bidder for failure to perform a contract in the preceding five years only where that failure was evidenced by a penalty imposed by an arbitral or judicial authority, a judicial pronouncement, or an arbitration award.
¶ 16, 23–2404Reasoning
For Package 5, the petitioners did not produce material showing that credentials had been improperly fragmented or that the alleged common participation in consortiums violated the tender conditions; the additional contention about Sunil G. was distinct from the objection raised before the appellate authority and was also unsupported by evidence of a resulting breach.
¶ 7–10The Package 14 challenge abated because it concerned only Petitioner No. 2’s individual bid and could not be continued by the remaining petitioners.
¶ 13–14For Package 23, the appellate authority had assessed Sathya Construction’s qualification documents and the circumstances of its bids across packages; the petitioners did not establish that this assessment was contrary to the tender conditions.
¶ 19–22The earlier work-order cancellation did not, on the material presented, satisfy Clause 2.2.13’s specified evidentiary requirements for disqualification.
¶ 23–25The Court therefore found no demonstrated basis for intervention under Article 226.
¶ 26–2705Holding
The Court rejected the challenges concerning Packages 5 and 23 and held the Package 14 proceedings abated insofar as they concerned Petitioner No. 2’s individual bid.
¶ 11, 14, 25Finding no ground for judicial interference, it dismissed the writ petition.
¶ 27–28 · Order, clauses i–iiThe dismissal was not to prevent the petitioners from participating in tenders already issued or subsequently issued by Respondent No. 3.
¶ 27–28 · Order, clauses i–iiOriginal Court PDF