Facts
AMPL (Petitioner/Claimant) was awarded a coal transportation contract by NTPC (Respondent) on 17.12.2019.
Source reference: p. 2-3On 13.04.2020, NTPC directed AMPL to suspend work due to lower coal requirements.
Source reference: p. 3AMPL initiated arbitration seeking Rs. 24.20 Crores under four heads: Fixed Costs, Fixed Office Expenses, Retention Money, and Loss of Profit.
Source reference: p. 4The Sole Arbitrator’s award dated 19.12.2024 allowed claims for loss of profit and retention money but rejected fixed costs and office expenses.
Source reference: p. 4, 19-20Both parties challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996.
Source reference: p. 3Issues
1. Whether the rejection of claims for "fixed costs" and "fixed office expenses" was perverse given the finding that such costs were incurred.
Source reference: p. 10/para. 22.12. Whether the award of "loss of profits" was patently illegal for lack of evidence of lost opportunities and failure to account for the contractual 30% deviation limit.
Source reference: p. 11-12/para. 25.1-25.23. Whether the Arbitrator’s exercise of discretion in awarding 50% legal costs and 12% interest was valid.
Source reference: p. 13-14/para. 25.3-25.4Law Applied
The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, which limits judicial interference to grounds of patent illegality or contravention of the fundamental policy of Indian law.
Source reference: p. 15-16It relied on *Associate Builders v. DDA* and *Hindustan Construction Co. Ltd. v. NHAI* to establish that the Arbitrator is the ultimate master of quantity and quality of evidence, and an award cannot be set aside merely because an alternative view is possible.
Source reference: p. 21-23Regarding damages, the court followed *A.T. Brij Paul Singh v. State of Gujarat*, holding that a reasonable expectation of profit (often 15%) is implicit in works contracts.
Source reference: p. 29-30Costs were governed by the discretionary regime under Section 31A of the Act.
Source reference: p. 23-24Reasoning
The Court found that the Arbitrator’s rejection of fixed costs was a "possible view," as the contract price was intended to subsume such expenses; awarding them separately would constitute "double liability."
Source reference: p. 20-21Regarding the 30% deviation clause, the Court held that the Arbitrator’s decision to calculate profits on the full "fixed quantity" was a reasonable method to avoid speculation on future contingencies.
Source reference: p. 27The Court dismissed the Respondent’s reliance on *Unibros*, noting that the requirement to prove "loss of other opportunities" applies to delay claims in extended periods, not to a breach within the original contract term where profit expectation is direct.
Source reference: p. 28-29The 15% profit rate was upheld as it was backed by chartered accountant certificates and auditor reports.
Source reference: p. 30Finally, the Court ruled that the 50% legal cost award was a valid exercise of discretion under Section 31A, proportional to the partial success of the claims.
Source reference: p. 25Holding
The High Court dismissed both petitions and upheld the arbitral award in its entirety.
It held that the Arbitrator's findings were neither perverse nor patently illegal under Section 34.
Source reference: p. 31The challenge to the 12% interest rate was rejected as the contract did not expressly prohibit interest, and the Arbitrator possessed statutory discretion under Section 31(7) to award the same.
Source reference: p. 31No order as to costs was made for the present petitions.
Source reference: p. 32Original Court PDF
NTPC Ltd v. AMPL Resources Private Limited [O.M.P. (COMM) 186/2025 & O.M.P. (COMM) 240/2025]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in